Second Notice | | 7/22/2017 | 8/2/2017 | | DONE |
Candy A. Nichols
|
|
|
|
Print Statement | | | 8/2/2017 | | DONE |
|
|
|
|
First Notice | | 6/26/2017 | 7/12/2017 | | DONE |
|
|
|
sent in mail 7-12-17
|
Permanent Occupancy | | | 6/16/2017 | | DONE |
|
|
|
|
BLD-Final | 6/14/2017 | 6/14/2017 | 6/14/2017 | P | PASS |
Dave Hannah
|
|
|
Call for access - Brady Phone #: ###-####
|
BLD-Final | 6/12/2017 | 6/13/2017 | 6/13/2017 | A | NR |
Jim Sly
|
|
|
Brady Phone #: ###-#### Need Electr Final.
|
FIRE-Final Inspection | 6/12/2017 | 6/12/2017 | 6/12/2017 | P | PASS |
Jim Page
|
|
|
No fire sprinklers, smoke detectors are stand-alone and not monitored, fire extinguisher is in place with a current inspection tag. Final life fire safety inspection passed/complete
|
BLD-Final | 6/7/2017 | 6/9/2017 | 6/9/2017 | A | NR |
Jim Storey
|
|
|
Brady Phone #: ###-####
|
BLD-Framing/Rough-in | 5/17/2017 | 5/17/2017 | 5/17/2017 | P | PASS |
Mike Jordan
|
|
|
Interior wood framed walls ok.
|
BLD-Framing/Rough-in | 5/16/2017 | 5/17/2017 | 5/17/2017 | A | NH |
Mike Jordan
|
|
|
Brady Phone #: ###-####. No one one site, doors locked. Called Brady, no awnser, mailbox full, could not leave message. Will need to reschedule.
|
BLD-Framing/Rough-in | 5/11/2017 | 5/12/2017 | 5/12/2017 | A | PART |
Jim Storey
|
|
|
Brady Phone #: ###-#### pending ele aproval
|
Print Occupancy Form | | | 4/25/2017 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 4/25/2017 | | DONE |
|
|
|
|
Plan assigned to (JG) | 4/12/2017 | 4/12/2017 | 4/20/2017 | | PASS |
Javier Guzman
|
|
|
5/02 L3 Old Soul Tattoo ePlan
|
Routing - PLAN CHECK | 4/12/2017 | | 4/20/2017 | | PASS |
Javier Guzman
|
|
|
|
1st review completed | | | 4/20/2017 | | DONE |
Javier Guzman
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/20/2017 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 4/20/2017 | | DONE |
|
|
|
need GC and rev cert of val
|
Routing - FIRE | 4/12/2017 | 4/12/2017 | 4/13/2017 | | PASS |
Katie Marron
|
|
|
Basic Life Safety. No comments required.
|
Routing - MECHANICAL | 4/12/2017 | | 4/13/2017 | | PASS |
Troy James
|
|
|
No mechanical work is being performed under this permit as noted on submitted plans.
|
Routing - Addressing | 4/12/2017 | | 4/13/2017 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | 4/12/2017 | | 4/13/2017 | | PASS |
Rachael Beierle
|
|
|
|
Intake Approval | | | 4/12/2017 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
Javier passed pre screen, Javier notified applicant this was major ti for 1st time build out.
|
Application received | | | 4/10/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Apr 10 2017 8:28AM
|