Second Notice | | 9/29/2017 | 10/12/2017 | | DONE |
|
|
|
Mailed 10-13-17
|
First Notice | | 8/12/2017 | 9/19/2017 | | DONE |
|
|
|
Mailed 9/19/17
|
BLD-Final | 8/1/2017 | 8/2/2017 | 8/2/2017 | A | PASS |
Jim Sly
|
|
|
Jake Phone #: ###-#### OK for Perm Occ.
|
Permanent Occupancy | | | 8/2/2017 | | DONE |
|
|
|
|
FIRE-Final Inspection | 7/31/2017 | 8/1/2017 | 8/1/2017 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
FIRE-Final Inspection | 7/28/2017 | 7/28/2017 | 7/28/2017 | P | FAIL |
Jim Page
|
|
|
Fire extinguisher needs to be serviced, last tagged inspection was in 2010. All emergency exit/egress lighting in space needs to be serviced, exit lights/egress lighting did no illuminate when power was shut off.
|
Issue PAID IN FULL permit | | | 7/28/2017 | | DONE |
|
|
|
|
Print Occupancy Form | | | 7/28/2017 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 7/27/2017 | | DONE |
|
|
|
No work authorized under this permit/ no GC required/ min. value only
|
Routing - FIRE | 7/20/2017 | 7/20/2017 | 7/25/2017 | | PASS |
Scott Arellano
|
|
|
Attached revised comments to case and plan package.
|
Plan assigned to (JG) | 4/12/2017 | 4/12/2017 | 7/25/2017 | | PASS |
Javier Guzman
|
|
|
1st rev comp, 5/09 L3 Hero's Academy ePlan pend fire
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/25/2017 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 7/20/2017 | | 7/22/2017 | | PASS |
Javier Guzman
|
|
|
|
Routing - MECHANICAL | 7/20/2017 | | 7/21/2017 | | PASS |
Troy James
|
|
|
|
Route to Impact Fee Review | 5/8/2017 | 5/11/2017 | 5/9/2017 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
1st review completed | | | 5/8/2017 | | FAIL |
Javier Guzman
|
|
|
|
Routing - PLAN CHECK | 4/12/2017 | | 5/8/2017 | | FAIL |
Javier Guzman
|
|
|
|
Routing - Erosion and Sediment | 4/12/2017 | | 5/2/2017 | | PASS |
Melissa Jannusch
|
|
|
signed off w/ conditions by Erosion Melissa Jannusch
|
Routing - PLANNING | 4/12/2017 | | 4/24/2017 | | PASS |
Leon Letson
|
|
|
|
Routing - MECHANICAL | 4/12/2017 | | 4/18/2017 | | FAIL |
Troy James
|
|
|
|
Routing - FIRE | 4/12/2017 | 4/12/2017 | 4/13/2017 | | FAIL |
Katie Marron
|
|
|
Report attached to case and emailed to architect.
|
Routing - Addressing | 4/12/2017 | | 4/13/2017 | | PASS |
Laura Hunter
|
|
|
Ste 101
|
Routing - PUBLIC WORKS | 4/12/2017 | | 4/12/2017 | | PASS |
Rachael Beierle
|
|
|
|
Plan Reviewer's activity | | | 4/12/2017 | | DONE |
Adele J Schaffeld-Griffin
|
|
|
Randy, Please make sure that you reach out to ACHD for review on this change of use/occupancy. If additional fees are due they will need to be paid or paid when the permit is issued. If no fees are do please submit the documentation from ACDH as such.
Thank you
Adele Schaffeld-Griffin
Assistant Building Official / Plan Review Manager
Planning & Development Services Department
City of Boise - 150 N. Capitol Blvd.
P.O. Box 500
Boise, ID 83701
Office ###-####
Email – aschaffeldgriffin@cityofboise.org
“Building Boise Together.”
|
Intake Approval | | | 4/12/2017 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
Julie completed pre screen, plan review fee paid
|
Application received | | | 4/11/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Apr 11 2017 9:22AM
|