Print Statement | | | 12/3/2018 | | DONE |
|
|
|
|
Third Notice | | 10/16/2018 | 11/6/2018 | | DONE |
|
|
|
mailed 11-12
|
Second Notice | | 9/20/2018 | 10/11/2018 | | DONE |
|
|
|
mailed 10-12-18
|
First Notice | | 8/26/2018 | 9/10/2018 | | DONE |
|
|
|
mailed 9-11-18
|
Permanent Occupancy | | | 8/16/2018 | | DONE |
|
|
|
|
BLD-Final | 8/15/2018 | 8/15/2018 | 8/15/2018 | P | PASS |
Jim Storey
|
|
|
Tom Phone #: ###-#### final ok pending others
|
FIRE-Final Inspection | 8/14/2018 | 8/15/2018 | 8/15/2018 | A | PASS |
Jim Page
|
|
|
Fire sprinkler inspection complete, fire alarm inspection complete, fire extinguishers are placed with current inspection tags. Final life fire safety inspection complete.
Tom Phone #: ###-####
|
Temporary Occupancy | 8/15/2018 | 11/13/2018 | 8/15/2018 | | DONE |
Candy A. Nichols
|
|
|
|
FIRE-Final Inspection | 8/13/2018 | 8/14/2018 | 8/14/2018 | A | CANC |
Troy Cobbley
|
|
|
Life safety will be ok to pass when the project related fire alarm and fire sprinkler permits are finaled.
Tom Phone #: ###-####
|
BLD-Final | 8/10/2018 | 8/13/2018 | 8/13/2018 | A | CANC |
Jim Storey
|
|
|
Tom Phone #: ###-####
|
Zoning Approval | 8/10/2018 | 8/10/2018 | 8/10/2018 | | DONE |
Andrea Tuning
|
|
|
|
PubWorks Occupancy Approval | 8/9/2018 | 8/9/2018 | 8/9/2018 | | DONE |
Tiffany Lowery
|
|
|
|
BLD-Ceiling Grid Inspection | 7/18/2018 | 7/18/2018 | 7/18/2018 | P | PASS |
Mike Jordan
|
|
|
2nd floor // Tom Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 6/25/2018 | 6/25/2018 | 6/25/2018 | P | PASS |
Jim Storey
|
|
|
Tom Phone #: ###-####
|
BLD-Framing/Rough-in | 6/7/2018 | 6/7/2018 | 6/7/2018 | P | PASS |
Jim Storey
|
|
|
Tom Phone #: ###-#### 2nd floor ok
|
BLD-Energy code compliance | 5/10/2018 | 5/11/2018 | 5/11/2018 | A | PART |
Brandon Shaw
|
|
|
Second floor exterior walls to window sill and South East stair landing
|
BLD-Energy code compliance | 4/24/2018 | 4/25/2018 | 4/25/2018 | A | PASS |
Jim Storey
|
|
|
roof insulation // Tom Phone #: ###-#### c/n made good// insulation ok to cover
|
BLD-Energy code compliance | 4/23/2018 | 4/23/2018 | 4/23/2018 | P | PEND |
Dave Hannah
|
|
|
roof insulation // ###-#### Tom spray on insulation ok but need to remove paper backed insulation
|
BLD-Energy code compliance | 4/13/2018 | 4/13/2018 | 4/13/2018 | P | PART |
Jim Storey
|
|
|
Tom Phone #: ###-#### 1st floor ok
|
BLD-Framing/Rough-in | 4/9/2018 | 4/9/2018 | 4/9/2018 | P | PASS |
Jim Storey
|
|
|
elevator shaft-Tom Phone #: ###-####first floor ok
|
BLD-Wall Bracing | 3/30/2018 | 4/2/2018 | 4/2/2018 | A | PASS |
Jim Storey
|
|
|
Tom Phone #: ###-#### sheer walls at drive thru as well as frame ok ok to cover.
|
BLD-Other | 3/20/2018 | 3/21/2018 | 3/21/2018 | A | PASS |
Brandon Shaw
|
|
|
roof shear for drive-thru
|
BLD-Other | 3/16/2018 | 3/16/2018 | 3/16/2018 | P | PASS |
Jim Storey
|
|
|
roof nailing // Tom Phone #: ###-####
|
BLD-Other | 3/5/2018 | 3/6/2018 | 3/6/2018 | A | PASS |
Jim Storey
|
|
|
Tom-inspection to look at the metal trusses to cover Phone #: ###-#### wip truss framing ok to cover
|
CHANGE STATUS TO (ISS) | | | 3/6/2018 | | DONE |
|
|
|
|
Telephone call | | | 3/5/2018 | | DONE |
|
|
|
Tom called and will be in 1st thing in the morning to pay and sign for the plan mod fees. i scheduled the inspection because he is from outta town and couldn't make it today and really need the inspection set up for AM
|
OVERRIDE | | | 2/23/2018 | | |
|
|
|
|
Plan assigned to (CDM) | 1/30/2018 | 1/30/2018 | 2/23/2018 | | PASS |
Carl D Madsen
|
|
|
|
Routing - PLAN CHECK | 2/23/2018 | | 2/23/2018 | | PASS |
Carl D Madsen
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/23/2018 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 2/23/2018 | | DONE |
Christina Prado
|
|
|
DO NOT RE-ISSUE - PLAN MOD
Change status to ISS once all fees are paid in full
|
BLD-Other | 2/21/2018 | 2/22/2018 | 2/22/2018 | A | PASS |
Jim Storey
|
|
|
Tom-exterior stud framing-this has nothing to do with the plan mod that''s in for review Phone #: ###-#### exterior framing ok to start cover/
|
Plan Modification Accepted | | | 1/30/2018 | | DONE |
Christina Prado
|
|
|
Plan Mod requested to add aluminum storefront with door access to seperate the stair from the lobby
|
BLD-Other | 1/25/2018 | 1/26/2018 | 1/26/2018 | P | PART |
Jim Storey
|
|
|
Welding - Tom Phone #: ###-#### work in progress/ need to finsh si insp.
|
BLD-Foundation | 11/21/2017 | 11/21/2017 | 11/21/2017 | P | PASS |
Jim Storey
|
|
|
insulation for foundation - Tom Phone #: ###-####
|
BLD-Foundation | 11/9/2017 | 11/9/2017 | 11/9/2017 | P | PART |
Jim Storey
|
|
|
Tom Phone #: ###-#### placed w/si pending report
|
BLD-Footing | 10/26/2017 | 10/27/2017 | 10/27/2017 | P | PASS |
Jim Storey
|
|
|
footing rebar // Tom Phone #: ###-#### ok pending si report for compaction/rebar and concrete
|
Issue PAID IN FULL permit | | | 9/8/2017 | | DONE |
|
|
|
|
Print Occupancy Form | | | 9/8/2017 | | DONE |
|
|
|
|
OVERRIDE | | | 7/10/2017 | | |
|
|
|
|
Permit Ready to Issue | | | 7/10/2017 | | |
Christina Prado
|
|
|
ALL MET
Need RP, GC Form & Revised Certificate of Value for issuance
|
Plan assigned to (CDM) | 5/4/2017 | 5/4/2017 | 7/8/2017 | | PASS |
Carl D Madsen
|
|
|
1st comp. 6/4 Idaho Central Credit Union
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/8/2017 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 6/19/2017 | | 7/8/2017 | | PASS |
Carl D Madsen
|
|
|
|
Routing Off Site - STRUCTURAL | 6/19/2017 | | 7/5/2017 | | PASS |
Carl D Madsen
|
|
|
|
Routing PW Drainage | 6/19/2017 | | 6/29/2017 | | PASS |
Brian Murphy
|
|
|
|
Routing - FIRE | 6/19/2017 | 6/19/2017 | 6/20/2017 | | PASS |
Scott Arellano
|
|
|
Revised report attached to case.
|
Routing - Design Review | 6/19/2017 | | 6/19/2017 | | PASS |
Andrea Tuning
|
|
|
|
Routing - PUBLIC WORKS | 6/19/2017 | | 6/19/2017 | | PASS |
Rachael Beierle
|
|
|
|
Route to Impact Fee Review | 5/29/2017 | 6/1/2017 | 5/31/2017 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
Routing - PLAN CHECK | 5/4/2017 | | 5/29/2017 | | FAIL |
Carl D Madsen
|
|
|
|
Routing Off Site - STRUCTURAL | 5/4/2017 | | 5/29/2017 | | FAIL |
Carl D Madsen
|
|
|
|
1st review completed | | | 5/29/2017 | | FAIL |
|
|
|
|
Routing PW Sewer Design | 5/4/2017 | | 5/15/2017 | | PASS |
Kyle S. Rosenmeyer
|
|
|
|
Routing PW Drainage | 5/4/2017 | | 5/12/2017 | | FAIL |
Brian Murphy
|
|
|
need perc rate
|
Routing - FIRE | 5/4/2017 | 5/4/2017 | 5/9/2017 | | FAIL |
Katie Marron
|
|
|
Report attached to case and emailed to architect.
|
Routing PW Solid Waste | 5/4/2017 | | 5/9/2017 | | PASS |
Evan Carpenter
|
|
|
Solid waste is OK as planned.
|
Routing - MECHANICAL | 5/4/2017 | | 5/8/2017 | | PASS |
Troy James
|
|
|
|
Routing - Erosion and Sediment | 5/4/2017 | | 5/5/2017 | | PASS |
Andy J. Long
|
|
|
Plan approved.
|
Intake Approval | | | 5/4/2017 | | PASS |
|
|
|
|
Routing PW Street Lights | 5/4/2017 | | 5/4/2017 | | PASS |
Tom Marshall
|
|
|
|
Routing - PLUMBING | 5/4/2017 | | 5/4/2017 | | PASS |
Bill VanDegrift
|
|
|
1) Will use existing sewer
2) see redlines on plans
3) ok per plans and ISPC
|
Routing - PLANNING | 5/4/2017 | | 5/4/2017 | | PASS |
Celine Acord
|
|
|
|
Routing - PLANNING Land Div | 5/4/2017 | | 5/4/2017 | | PASS |
Todd Tucker
|
|
|
|
Routing - Addressing | 5/4/2017 | | 5/4/2017 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | 5/4/2017 | | 5/4/2017 | | PASS |
Rachael Beierle
|
|
|
|
Routing - Design Review | 5/4/2017 | | 5/4/2017 | | FAIL |
Andrea Tuning
|
|
|
Street trees on Vista shall be located within the planter strip.
Street trees on Cal shall be spaced appropriately.
All lighting shall be located outside of planter islands.
|
Plan Reviewer's activity | | | 4/26/2017 | | PASS |
|
|
|
The 1st plan intake review was approved
|
Application received | | | 4/12/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Apr 12 2017 4:29PM
|