Information based on query as of Wednesday, July 3, 2024.
Permit Information
Permit NumberBLD17-01025
StatusFinaled
Name CM COMPANY
Site Address 2770 S VISTA AVE
Project NameIdaho Central Credit Union
Customer Number 
ePlanReviewYes
Description
(IDAHO CENTRAL CREDIT UNION) ""Plan modification to add a door and related glazing to the NW stairs.""" Permit for the construction of a new 12,823 sq. ft. building with work to include general site work and the construction of the new building. The existing 6,400 sq. ft building is being demolished. This building is fully fire sprinklered and alarmed. CDM
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Print Statement  12/3/2018 DONE
Third Notice 10/16/201811/6/2018 DONE
mailed 11-12
Second Notice 9/20/201810/11/2018 DONE
mailed 10-12-18
First Notice 8/26/20189/10/2018 DONE
mailed 9-11-18
Permanent Occupancy  8/16/2018 DONE
BLD-Final8/15/20188/15/20188/15/2018PPASS
DetailsJim Storey
Tom Phone #: ###-#### final ok pending others
FIRE-Final Inspection8/14/20188/15/20188/15/2018APASS
DetailsJim Page
Fire sprinkler inspection complete, fire alarm inspection complete, fire extinguishers are placed with current inspection tags. Final life fire safety inspection complete.

Tom Phone #: ###-####
Temporary Occupancy8/15/201811/13/20188/15/2018 DONE
DetailsCandy A. Nichols
FIRE-Final Inspection8/13/20188/14/20188/14/2018ACANC
DetailsTroy Cobbley
Life safety will be ok to pass when the project related fire alarm and fire sprinkler permits are finaled.


Tom Phone #: ###-####
BLD-Final8/10/20188/13/20188/13/2018ACANC
DetailsJim Storey
Tom Phone #: ###-####
Zoning Approval8/10/20188/10/20188/10/2018 DONE
DetailsAndrea Tuning
PubWorks Occupancy Approval8/9/20188/9/20188/9/2018 DONE
DetailsTiffany Lowery
BLD-Ceiling Grid Inspection7/18/20187/18/20187/18/2018PPASS
DetailsMike Jordan
2nd floor // Tom Phone #: ###-####
BLD-Ceiling Grid Inspection6/25/20186/25/20186/25/2018PPASS
DetailsJim Storey
Tom Phone #: ###-####
BLD-Framing/Rough-in6/7/20186/7/20186/7/2018PPASS
DetailsJim Storey
Tom Phone #: ###-#### 2nd floor ok
BLD-Energy code compliance5/10/20185/11/20185/11/2018APART
DetailsBrandon Shaw
Second floor exterior walls to window sill and South East stair landing
BLD-Energy code compliance4/24/20184/25/20184/25/2018APASS
DetailsJim Storey
roof insulation // Tom Phone #: ###-#### c/n made good// insulation ok to cover
BLD-Energy code compliance4/23/20184/23/20184/23/2018PPEND
DetailsDave Hannah
roof insulation // ###-#### Tom spray on insulation ok but need to remove paper backed insulation
BLD-Energy code compliance4/13/20184/13/20184/13/2018PPART
DetailsJim Storey
Tom Phone #: ###-#### 1st floor ok
BLD-Framing/Rough-in4/9/20184/9/20184/9/2018PPASS
DetailsJim Storey
elevator shaft-Tom Phone #: ###-####first floor ok
BLD-Wall Bracing3/30/20184/2/20184/2/2018APASS
DetailsJim Storey
Tom Phone #: ###-#### sheer walls at drive thru as well as frame ok ok to cover.
BLD-Other3/20/20183/21/20183/21/2018APASS
DetailsBrandon Shaw
roof shear for drive-thru
BLD-Other3/16/20183/16/20183/16/2018PPASS
DetailsJim Storey
roof nailing // Tom Phone #: ###-####
BLD-Other3/5/20183/6/20183/6/2018APASS
DetailsJim Storey
Tom-inspection to look at the metal trusses to cover Phone #: ###-#### wip truss framing ok to cover
CHANGE STATUS TO (ISS)  3/6/2018 DONE
Telephone call  3/5/2018 DONE
Tom called and will be in 1st thing in the morning to pay and sign for the plan mod fees. i scheduled the inspection because he is from outta town and couldn't make it today and really need the inspection set up for AM
OVERRIDE  2/23/2018  
Plan assigned to (CDM)1/30/20181/30/20182/23/2018 PASS
DetailsCarl D Madsen
Routing - PLAN CHECK2/23/2018 2/23/2018 PASS
DetailsCarl D Madsen
PLANS/APPL TAKEN TO FRONT DESK  2/23/2018 DONE
Permit Ready to Issue  2/23/2018 DONE
DetailsChristina Prado
DO NOT RE-ISSUE - PLAN MOD

Change status to ISS once all fees are paid in full
BLD-Other2/21/20182/22/20182/22/2018APASS
DetailsJim Storey
Tom-exterior stud framing-this has nothing to do with the plan mod that''s in for review Phone #: ###-#### exterior framing ok to start cover/
Plan Modification Accepted  1/30/2018 DONE
DetailsChristina Prado
Plan Mod requested to add aluminum storefront with door access to seperate the stair from the lobby
BLD-Other1/25/20181/26/20181/26/2018PPART
DetailsJim Storey
Welding - Tom Phone #: ###-#### work in progress/ need to finsh si insp.
BLD-Foundation11/21/201711/21/201711/21/2017PPASS
DetailsJim Storey
insulation for foundation - Tom Phone #: ###-####
BLD-Foundation11/9/201711/9/201711/9/2017PPART
DetailsJim Storey
Tom Phone #: ###-#### placed w/si pending report
BLD-Footing10/26/201710/27/201710/27/2017PPASS
DetailsJim Storey
footing rebar // Tom Phone #: ###-#### ok pending si report for compaction/rebar and concrete
Issue PAID IN FULL permit  9/8/2017 DONE
Print Occupancy Form  9/8/2017 DONE
OVERRIDE  7/10/2017  
Permit Ready to Issue  7/10/2017  
DetailsChristina Prado
ALL MET
Need RP, GC Form & Revised Certificate of Value for issuance
Plan assigned to (CDM)5/4/20175/4/20177/8/2017 PASS
DetailsCarl D Madsen
1st comp. 6/4 Idaho Central Credit Union
PLANS/APPL TAKEN TO FRONT DESK  7/8/2017 DONE
Routing - PLAN CHECK6/19/2017 7/8/2017 PASS
DetailsCarl D Madsen
Routing Off Site - STRUCTURAL6/19/2017 7/5/2017 PASS
DetailsCarl D Madsen
Routing PW Drainage6/19/2017 6/29/2017 PASS
DetailsBrian Murphy
Routing - FIRE6/19/20176/19/20176/20/2017 PASS
DetailsScott Arellano
Revised report attached to case.
Routing - Design Review6/19/2017 6/19/2017 PASS
DetailsAndrea Tuning
Routing - PUBLIC WORKS6/19/2017 6/19/2017 PASS
DetailsRachael Beierle
Route to Impact Fee Review5/29/20176/1/20175/31/2017 PASS
DetailsEric Bilimoria
Review requested for Commercial Permit
Routing - PLAN CHECK5/4/2017 5/29/2017 FAIL
DetailsCarl D Madsen
Routing Off Site - STRUCTURAL5/4/2017 5/29/2017 FAIL
DetailsCarl D Madsen
1st review completed  5/29/2017 FAIL
Routing PW Sewer Design5/4/2017 5/15/2017 PASS
DetailsKyle S. Rosenmeyer
Routing PW Drainage5/4/2017 5/12/2017 FAIL
DetailsBrian Murphy
need perc rate
Routing - FIRE5/4/20175/4/20175/9/2017 FAIL
DetailsKatie Marron
Report attached to case and emailed to architect.
Routing PW Solid Waste5/4/2017 5/9/2017 PASS
DetailsEvan Carpenter
Solid waste is OK as planned.
Routing - MECHANICAL5/4/2017 5/8/2017 PASS
DetailsTroy James
Routing - Erosion and Sediment5/4/2017 5/5/2017 PASS
DetailsAndy J. Long
Plan approved.
Intake Approval  5/4/2017 PASS
Routing PW Street Lights5/4/2017 5/4/2017 PASS
DetailsTom Marshall
Routing - PLUMBING5/4/2017 5/4/2017 PASS
DetailsBill VanDegrift
1) Will use existing sewer
2) see redlines on plans
3) ok per plans and ISPC
Routing - PLANNING5/4/2017 5/4/2017 PASS
DetailsCeline Acord
Routing - PLANNING Land Div5/4/2017 5/4/2017 PASS
DetailsTodd Tucker
Routing - Addressing5/4/2017 5/4/2017 PASS
DetailsLaura Hunter
Routing - PUBLIC WORKS5/4/2017 5/4/2017 PASS
DetailsRachael Beierle
Routing - Design Review5/4/2017 5/4/2017 FAIL
DetailsAndrea Tuning
Street trees on Vista shall be located within the planter strip.

Street trees on Cal shall be spaced appropriately.

All lighting shall be located outside of planter islands.
Plan Reviewer's activity  4/26/2017 PASS
The 1st plan intake review was approved
Application received  4/12/2017 DONE
Application submitted via PDS Online on Apr 12 2017 4:29PM