Permanent Occupancy | | | 7/17/2017 | | DONE |
|
|
|
|
BLD-Final | 7/12/2017 | 7/13/2017 | 7/13/2017 | P | PASS |
Jim Sly
|
|
|
Alex Phone #: ###-#### OK for Perm Occ.
|
FIRE-Final Inspection | 7/7/2017 | 7/10/2017 | 7/10/2017 | P | PASS |
Troy Cobbley
|
|
|
life safety passed
|
BLD-Final | 6/27/2017 | 6/29/2017 | 6/29/2017 | P | NR |
Jim Sly
|
|
|
Alex Phone #: ###-#### Need fire final.
|
FIRE-Final Inspection | 6/27/2017 | 6/28/2017 | 6/28/2017 | P | FAIL |
Troy Cobbley
|
|
|
Remove the thumb turn dead bolts from both restraunt doors, keyed is ok on the main entry/exit.
Repair the west side exit discharge light Repair the restruant emergency light Repair the stairwell emergency light
Provide fire extinguisher for basement Provide annual inspection for all extinguishers Provide inspection/certification for the hood suppression system
Contact plan review to verify that the restraunt door swing is acceptable.Plans show swing out but they only swing in.
|
Issue PAID IN FULL permit | | | 6/6/2017 | | DONE |
|
|
|
|
Plan assigned to (CJW) | 4/14/2017 | 4/14/2017 | 5/9/2017 | | PASS |
Carl Westfall
|
|
|
(1st done) (Apr 18 - 3 days) Occupancy
|
Routing - PLAN CHECK | 4/25/2017 | | 5/9/2017 | | PASS |
Carl Westfall
|
|
|
Routing completed
|
Routing PW Sewer Rating | 5/9/2017 | | 5/9/2017 | | PASS |
Rachael Beierle
|
|
|
see imaging for letter
|
Routing - PUBLIC WORKS | 5/9/2017 | | 5/9/2017 | | PASS |
Rachael Beierle
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/9/2017 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 5/9/2017 | | DONE |
|
|
|
|
Print Occupancy Form | | | 5/9/2017 | | DONE |
|
|
|
|
Telephone call | | | 5/9/2017 | | DONE |
|
|
|
Left a message for Alex informing him that this permit is ready and that one of the techs will go over the required inspections needed for occupancy.
|
Routing - PLAN CHECK | 4/19/2017 | | 4/25/2017 | | PASS |
Carl Westfall
|
|
|
Insert PW sheet and upload application and documents
|
Routing - FIRE | 4/25/2017 | | 4/25/2017 | | PASS |
Katie Marron
|
|
|
Comments attached.
|
1st review completed | | | 4/25/2017 | | FAIL |
|
|
|
Failed Public Works
|
Routing - Addressing | 4/14/2017 | | 4/19/2017 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | 4/14/2017 | | 4/19/2017 | | FAIL |
Rachael Beierle
|
|
|
sewer balance from previous tenant due. waitng for returned info
|
Routing PW Environmental | 4/17/2017 | | 4/19/2017 | | PASS |
Rick Christenson
|
|
|
pass per rwc
|
Routing PW Sewer Rating | 4/19/2017 | | 4/19/2017 | | FAIL |
Rachael Beierle
|
|
|
WAITING ON EMAIL CONFIRMATION FROM BUILDING OWNER THAT THEY AGREE TO REMAIN PAYING SEWER AGREEMENT. SPOKE W/ ALEX 4-17-17. WILL PASS WHEN INFO IS RETURNED.
|
Plans ACCEPTED BY PLAN TECH | | | 4/14/2017 | | DONE |
|
|
|
|
Intake Approval | | | 4/14/2017 | | PASS |
Carl Westfall
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 4/14/2017 | | DONE |
|
|
|
|
First Notice | | 7/27/2017 | | | |
|
|
|
|
Application received | | 4/14/2017 | | | |
|
|
|
|