Information based on query as of Sunday, June 30, 2024.
Permit Information
Permit NumberBLD17-01054
StatusFinaled
Name MIRAGE POOLS IDAHO INC
Site Address 2964 E PARKCENTER BLVD
Project NameArboretum Pool and Spa
Customer NumberESC15-01579
ePlanReviewNo
Description
(SWIMMING POOL AND SPA – NEXT TO CLUB HOUSE BUILDING – ARBORETUM AT BARBER STATION APARTMENTS) (DRH15-00381 AND DRH15-00490) To construct an in-ground concrete swimming pool and a separate spa. The water surface area of the swimming pool will be about 855 square feet, the pool perimeter will be about 111 lineal feet, and the volume will be about 25,933 gallons. The water surface area of the spa will be about 95 square feet, the spa perimeter will be about 36 lineal feet, and the volume will be about 1,551 gallons. Work is to include a reinforced concrete gunite swimming pool (pool walls and pool floor), a concrete stairway to serve the pool, two pool ladders, handrails, a pool lift accessible to the disabled, and pool equipment. Work is to include a reinforced concrete gunite spa (spa walls and spa floor), a concrete stairway to serve the spa, handrails, concrete bench around the inside spa perimeter, a transfer wall accessible to the disabled, and spa equipment. Special Inspection is required for soils and for concrete. The club house building was constructed under permit BLD16-01060. The pool deck and fence with 2 egress gates to enclose the swimming pool and spa area were covered under that permit. The pool and/or spa are not allowed to be filled with water until the fence is completed. The pool and/or spa are not allowed to be used until this permit is finaled and a Certificate of Occupancy for the pool, for the spa, and for the fenced pool and spa enclosure is issued. Compliance with the 2012 ISPSC is allowed in lieu of the 2012 IBC for the swimming pool and spa. The restrooms, showers, drinking fountains, and pump room that will serve the swimming pool and spa fenced area are located within the club house building that was constructed under permit BLD16-01060. The pool and/or spa shall not be used until the work authorized under permit BLD16-01060 (i.e. the club house building) is completed and a Certificate of Occupancy is issued under that permit. The work is required to comply with the approved drawings, with the structural design, and with all applicable codes and ordinances. **CJW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Plan Reviewer's activity  12/21/2018 DONE
Took the paper drawings to Records
DOC - Permit Finaled  7/26/2018 DONE
Scope of work completed. Associated permits finaled.
BLD-Final6/29/20186/29/20186/29/2018PPASS
DetailsJim Sly
FIRE-Final Inspection6/29/20186/29/20186/29/2018PPASS
DetailsJim Page
Final life fire safety inspection for pool area complete.

sched final inspections for pool per Jim Sly Phone #: ###-####
Zoning Approval6/28/20186/28/20186/28/2018 DONE
DetailsAndrea Tuning
(F) Reprint permit  5/17/2018 DONE
BLD-Aging Inspection11/16/201711/16/201711/17/2017 CANC
DetailsJim Sly
BLD-Final11/17/201711/17/201711/17/2017PNR
DetailsJim Sly
BLD-Aging Inspection11/17/201711/17/201711/17/2017 CANC
DetailsJim Sly
BLD-Footing6/30/20177/3/20177/5/2017PPASS
DetailsBrandon Shaw
For rebar,
Issue PAID IN FULL permit  6/7/2017 DONE
DetailsChristina Prado
Print Occupancy Form  6/7/2017 DONE
DetailsChristina Prado
Plan assigned to (CJW)4/26/20174/26/20176/6/2017 PASS
DetailsCarl Westfall
(1st done) (May 16 - 15 days) paper - Arboretum Pool
Routing - PLAN CHECK5/11/2017 6/6/2017 PASS
DetailsCarl Westfall
Routing - FIRE6/6/2017 6/6/2017 PASS
DetailsScott Arellano
No comments attached.
1st review completed  6/6/2017 PASS
Routing - PLAN CHECK6/6/2017 6/6/2017 DONE
DetailsCarl Westfall
Routing complete
PLANS/APPL TAKEN TO FRONT DESK  6/6/2017 DONE
Permit Ready to Issue  6/6/2017 DONE
**MET** (GC turned in app. number is on last page) need GC form
Print Occupancy Form  6/6/2017 DONE
Telephone call  6/6/2017 DONE
Spoke with Caty informing her that this permit is ready and the fee amount due
Routing - PLUMBING5/10/2017 5/11/2017 PASS
DetailsBill VanDegrift
per plans and ISPC
Telephone call  5/11/2017 DONE
Katie called to see where permit was-i told her where the permit was and i gave her Carl W's phone number.
Routing - Erosion and Sediment  5/10/2017 PASS
DetailsAndy J. Long
No new ESC permit required. Pool construction to be covered under exisitng site permit ESC15-01579.
Routing - MECHANICAL5/10/2017 5/10/2017 PASS
DetailsTroy James
Routing - Design Review5/9/2017 5/9/2017 PASS
DetailsSarah Schafer
Approved per the changes seen on the site plan in modifications for building elevations in DRH16-00498.
Routing - PLANNING5/3/2017 5/9/2017 PASS
DetailsSarah Schafer
Routing - PUBLIC WORKS  5/3/2017 PASS
Routing PW Drainage4/27/2017 5/3/2017 PASS
DetailsBrian Murphy
Routing PW Sewer Rating4/27/2017 4/27/2017 PASS
DetailsMorgan Webb
POOL AND SPA ONLY.
Routing - Addressing4/26/2017 4/26/2017 PASS
DetailsLaura Hunter
2964 E Parkcenter Blvd is the clubhouse address, should be used for the pool permit also
Plans ACCEPTED BY PLAN TECH  4/26/2017 DONE
Intake Approval  4/25/2017 PASS
DetailsCarl Westfall
Recd Pcfee & Taken To Pln CK  4/25/2017 DONE
Application received 4/14/2017