BLD-Final | 4/18/2018 | 4/19/2018 | 4/19/2018 | A | PASS |
Dave Hannah
|
|
|
Call 15 minutes before to meet there **PLEASE CHECK FOR MEC WORK OR NOT TOO. THANK YOU** Scott Phone #: ###-#### no mec done all mec was installed at time of bldg construction
|
Permanent Occupancy | | | 4/19/2018 | | DONE |
|
|
|
|
FIRE-Final Inspection | 4/17/2018 | 4/18/2018 | 4/18/2018 | P | PASS |
Jim Page
|
|
|
No fire sprinkler modifications required, no fire alarm modifications required, fire extinguisher is in common area with a current inspection tag. Final life fire safety inspection for area of work complete.
|
BLD-Final | 4/2/2018 | 4/3/2018 | 4/3/2018 | A | NR |
Dave Hannah
|
|
|
Scott Kimball-call for access Phone #: ###-####
|
BLD-Framing/Rough-in | 3/16/2018 | 3/19/2018 | 3/23/2018 | P | PASS |
Dave Hannah
|
|
|
Scott Phone #: ###-####
|
BLD-Conference | 3/6/2018 | 3/8/2018 | 3/22/2018 | A | PASS |
Dave Hannah
|
|
|
Status? Steve @ ###-#### work in progress
|
BLD-Conference | 1/11/2018 | 1/16/2018 | 1/17/2018 | P | NH |
Dave Hannah
|
|
|
Project status? Attempt access during office hours. no one on site
|
BLD-Conference | 10/31/2017 | 11/1/2017 | 11/3/2017 | P | PEND |
Dave Hannah
|
|
|
Status? no access
|
Route to Impact Fee Review | 7/19/2017 | 7/24/2017 | 7/19/2017 | | PASS |
Marissa Taylor
|
|
|
|
Issue PAID IN FULL permit | | | 7/19/2017 | | DONE |
|
|
|
|
Print Occupancy Form | | | 7/19/2017 | | DONE |
|
|
|
|
Plan assigned to (CJW) | 5/8/2017 | 5/8/2017 | 7/14/2017 | | PASS |
Carl Westfall
|
|
|
(2nd done) (May 26 - 15 days) (1 sheet) 401 - Aspen Lofts
|
Routing - PLAN CHECK | 7/13/2017 | | 7/14/2017 | | PASS |
Carl Westfall
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/14/2017 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 7/14/2017 | | DONE |
|
|
|
all met 7/19/17 leg// need GC and rev cert of val
|
Plan resubmittals received | | | 7/13/2017 | | DONE |
|
|
|
|
Plan resubmittals requested | | | 7/11/2017 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 7/4/2017 | | 7/5/2017 | | FAIL |
Carl Westfall
|
|
|
One item is still not resolved. Sent an Email to the Architect.
|
Routing - PLANNING | 4/5/2017 | | 7/5/2017 | | PASS |
Cody Riddle
|
|
|
Cody, just wanted confirmation that a live-work unit is not required by some planning provision and that just a dwelling unit is allowed. Thanks. CJW
Allowed use; P-1 Parking Overlay, so no additional parking required.
|
Plan resubmittals received | | | 7/4/2017 | | DONE |
Carl Westfall
|
|
|
|
Route to Impact Fee Review | 6/13/2017 | 6/16/2017 | 6/14/2017 | | PASS |
Marissa Taylor
|
|
|
Review requested for Commercial Permit
|
1st review completed | | | 6/13/2017 | | DONE |
|
|
|
|
Plan resubmittals requested | | | 6/13/2017 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 5/8/2017 | | 6/13/2017 | | FAIL |
Carl Westfall
|
|
|
1st review done
|
Routing - FIRE | 5/8/2017 | 5/8/2017 | 5/8/2017 | | PASS |
Katie Marron
|
|
|
No comments required.
|
Routing - Addressing | 5/8/2017 | | 5/8/2017 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | 5/8/2017 | | 5/8/2017 | | PASS |
Rachael Beierle
|
|
|
|
Intake Approval | | | 5/8/2017 | | PASS |
Julie Romig
|
|
|
Julie completed per screen, notified applicant major TI
|
Intake Approval | | | 5/3/2017 | | FAIL |
|
|
|
1. Site specific fire flow at hydrants letter (required).
2. Rotate drawing.
3. Fire rated assembly for 2-hr wall that was extended south from kitchenette. This is a new wall not shown in the last permitted drawings on file and fire rated construction will need to be verified.
|
Intake Approval | | | 4/19/2017 | | FAIL |
Julie Romig
|
|
|
520 Major Tenant Improvement since it is a first time build-out of the space, not a 518 Minor. Please submit the following:
1. Completed 520 Major TI Submittal Checklist.
2. All additional information required in the 520 checklist.
|
Application received | | | 4/15/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Apr 15 2017 10:14AM
|
BLD-Other | 8/23/2017 | 8/24/2017 | | A | |
Dave Hannah
|
|
|
Check status?
|