Second Notice | | 9/29/2017 | 9/21/2017 | | DONE |
|
|
|
This permit finaled on the web by Curtis Weedop
|
First Notice | 8/15/2017 | 8/15/2017 | 9/19/2017 | | DONE |
Dave Hannah
|
|
|
Emailed 9/19/2017
|
BLD-Final | 8/15/2017 | 8/15/2017 | 8/15/2017 | P | PASS |
Dave Hannah
|
|
|
Jay Phone #: ###-####
|
DOC - Permit Finaled | 8/15/2017 | 8/15/2017 | 8/15/2017 | P | PASS |
Dave Hannah
|
|
|
|
Issue PAID IN FULL permit | | | 7/24/2017 | | DONE |
|
|
|
|
Plan assigned to (JAR) | 5/4/2017 | 5/4/2017 | 7/5/2017 | | DONE |
Julie Romig
|
|
|
1st Review Comp - Resubmitted 06/28 - L2 AP Chiller Replacement ePlan.
|
Routing - PLAN CHECK | 6/28/2017 | | 7/5/2017 | | PASS |
Julie Romig
|
|
|
Resubmit 06/28
|
Routing Off Site - STRUCTURAL | 6/28/2017 | | 7/5/2017 | | PASS |
Julie Romig
|
|
|
Passed per ePlanReview.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/5/2017 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 7/5/2017 | | DONE |
Christina Prado
|
|
|
All met 7/14 C_P // Need GC Form and Revised Cert of Value
|
Route to Impact Fee Review | 5/17/2017 | 5/20/2017 | 5/18/2017 | | PASS |
Marissa Taylor
|
|
|
Review requested for Commercial Permit
|
Routing Off Site - STRUCTURAL | 5/4/2017 | | 5/17/2017 | | FAIL |
Julie Romig
|
|
|
Failed strucutral review per ePlanReview.
|
1st review completed | | | 5/17/2017 | | FAIL |
|
|
|
|
Routing - PLAN CHECK | 5/4/2017 | | 5/17/2017 | | FAIL |
Julie Romig
|
|
|
Pending structural approval.
|
Routing - Design Review | 5/4/2017 | | 5/13/2017 | | PASS |
Sarah Schafer
|
|
|
Approved by Sarah Schafer in ePlanReview.
|
Intake Approval | | | 5/4/2017 | | PASS |
Javier Guzman
|
|
|
|
Application received | | | 4/17/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Apr 17 2017 10:00AM
|
Intake Approval | | | 4/17/2017 | | FAIL |
Julie Romig
|
|
|
Need: 1. Completed Form 304 Registered Design Professional (for engineer) 2. Drawing Index. 3. Code Analysis with information listed on submittal checklist. 4. Vicinity Map. 5. Mechanical COMcheck for new roof top units.
|