BLD-Final | 10/26/2017 | 10/27/2017 | 10/27/2017 | A | PASS |
Jim Storey
|
|
|
Ryan Phone #: ###-####
|
DOC - Permit Finaled | 10/27/2017 | 10/27/2017 | 10/27/2017 | P | PASS |
Jim Storey
|
|
|
|
BLD-Energy code compliance | 8/16/2017 | 8/17/2017 | 8/17/2017 | A | PASS |
Jim Storey
|
|
|
|
BLD-Energy code compliance | 8/15/2017 | 8/16/2017 | 8/17/2017 | P | DEFR |
Jim Storey
|
|
|
Air seal is done and all items are corrected and ready to go. Phone #: ###-#### Inspection requested via web by Ryan Sullivan
|
BLD-Framing/Rough-in | 8/15/2017 | 8/16/2017 | 8/16/2017 | A | PASS |
Jim Storey
|
|
|
Air seal is done and all items are corrected and ready to go. Phone #: ###-#### Inspection requested via web by Ryan Sullivan
|
BLD-Framing/Rough-in | 8/14/2017 | 8/14/2017 | 8/14/2017 | P | PART |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by Ryan Sullivan need ele passed/ blk floor joist at girders./airseal and insulate ok
|
Plan Modification Accepted | | | 8/9/2017 | | DONE |
|
|
|
new manual j report
|
Routing - MECHANICAL | 8/9/2017 | | 8/9/2017 | | PASS |
Troy James
|
|
|
resubmitted manual j report
|
BLD-Wall Bracing | 6/26/2017 | 6/27/2017 | 6/27/2017 | P | PASS |
Jim Storey
|
|
|
Ryan Phone #: ###-####
|
BLD-Foundation | 5/15/2017 | 5/16/2017 | 5/16/2017 | P | PASS |
Jim Storey
|
|
|
Dane Phone #: ###-####
|
BLD-Footing | 5/15/2017 | 5/15/2017 | 5/15/2017 | P | PASS |
Jim Storey
|
|
|
|
BLD-Footing | 5/12/2017 | 5/15/2017 | 5/15/2017 | A | NR |
Jim Storey
|
|
|
Dane Phone #: ###-####
|
BLD-Footing | 5/10/2017 | 5/11/2017 | 5/11/2017 | P | NR |
Jim Storey
|
|
|
Dane Phone #: ###-####
|
Issue PAID IN FULL permit | | | 5/4/2017 | | DONE |
|
|
|
|
OVERRIDE | | | 5/3/2017 | | |
|
|
|
|
Plan assigned to (JG) | 4/20/2017 | 4/20/2017 | 5/3/2017 | | PASS |
Javier Guzman
|
|
|
1st rev comp, 5/02 L1 SFD ePlan
|
Routing - PLAN CHECK | 5/3/2017 | | 5/3/2017 | | PASS |
Javier Guzman
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/3/2017 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 5/3/2017 | | DONE |
|
|
|
all requirements met
|
1st review completed | | | 5/2/2017 | | FAIL |
Javier Guzman
|
|
|
|
Routing - PLAN CHECK | 4/19/2017 | | 5/2/2017 | | FAIL |
Javier Guzman
|
|
|
|
Routing - Addressing | 4/19/2017 | | 5/2/2017 | | PASS |
Laura Hunter
|
|
|
signed off in ePlan by Public Works Addressing Laura Hunter
|
Routing - MECHANICAL | 4/19/2017 | | 4/26/2017 | | FAIL |
Troy James
|
|
|
emailed corrections to dustin mori
|
Routing - MECHANICAL | 4/26/2017 | | 4/26/2017 | | PASS |
Troy James
|
|
|
|
Route to Impact Fee Review | 4/19/2017 | 4/22/2017 | 4/24/2017 | | PASS |
Tonya Wallace
|
|
|
Initial residential review of new SFD permits requested for now.
|
Plan assigned to (AJS) | 4/19/2017 | 4/19/2017 | 4/20/2017 | | DEFR |
Adele J Schaffeld-Griffin
|
|
|
|
Routing - PLANNING | 4/19/2017 | | 4/20/2017 | | PASS |
Jeff Lowe
|
|
|
|
Routing - PUBLIC WORKS | 4/19/2017 | | 4/20/2017 | | PASS |
Morgan Webb
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 4/19/2017 | | DONE |
|
|
|
|
Intake Approval | | | 4/19/2017 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 4/19/2017 | | DONE |
|
|
|
|
Application received | | | 4/17/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Apr 17 2017 12:44PM
|
Intake Approval | | | 4/17/2017 | | FAIL |
|
|
|
***for res-check see precriptive on sheet A-8*** is on Missing Manual and Rescheck
|
Routing - PLAN CHECK | 5/3/2017 | | | | |
Javier Guzman
|
|
|
|