Information based on query as of Sunday, June 30, 2024.
Permit Information
Permit NumberBLD17-01073
StatusFinaled
Name ARMADA HOMES
Site Address 2728 N JEREMY AVE
Project NameChaucer 2-7
Customer Number 
ePlanReviewYes
Description
Permit for the construction of a new 1812 sq. ft., one story single family dwelling with 3 bedrooms, 2 bathrooms, approximately 27 sq. ft. of covered patio/porch and a 596 sq. ft. attached garage per the approved plans. Prescriptive Energy Code is proposed. R-1C zoning and setbacks per planning. **BJM**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Routing - PLANNING9/8/2017 9/8/2017 PASS
DetailsCeline Acord
Revised site plan to reflect actual driveway location; xref BLD17-03197
Plan Reviewer's activity  9/8/2017 DONE
DetailsBrian McGowan
Uploaded revised Site plan for driveway location
Plan Reviewer's activity  9/8/2017 DONE
revised and ok per CYA
BLD-Final8/23/20178/24/20178/24/2017PPASS
DetailsJim Sly
Kelly Phone #: ###-####
DOC - Permit Finaled8/24/20178/24/20178/24/2017PPASS
DetailsJim Sly
DOC - Permit Finaled8/24/20178/24/20178/24/2017PPASS
DetailsJim Sly
BLD-Energy code compliance6/27/20176/27/20176/27/2017PPASS
DetailsBrandon Shaw
Phone #: ###-#### Inspection requested via web by Kelly Stover
BLD-Framing/Rough-in6/22/20176/23/20176/23/2017PPASS
DetailsJim Sly
Inspection requested via web by Kelly Stover
BLD-Wall Bracing6/14/20176/15/20176/15/2017APASS
DetailsJim Sly
Phone #: ###-#### Inspection requested via web by Kelly Stover
BLD-Wall Bracing6/14/20176/16/20176/14/2017ACANC
DetailsJim Sly
Phone #: ###-#### >> Inspection requested via web by Kelly Stover Inspection cancelled from web by: Kelly Stover
BLD-Footing5/10/20175/10/20175/11/2017PPASS
DetailsJim Sly
Matt Phone #: ###-####
OVERRIDE  5/9/2017  
Issue PAID IN FULL permit  5/9/2017 DONE
Permit Ready to Issue  5/9/2017 DONE
DetailsChristina Prado
All requirements met
Routing Walk-In (BLD)5/1/20175/1/20175/8/2017PDONE
DetailsBrian McGowan
emailed drawings to me to upload.
Plan assigned to (BJM)4/17/20174/17/20175/8/2017 DONE
DetailsBrian McGowan
Due 4-28 ePlan - FAIL - Several sheets were not legible.
PLANS/APPL TAKEN TO FRONT DESK  5/8/2017 DONE
DetailsBrian McGowan
Routing - PLAN CHECK5/7/2017 5/7/2017 PASS
DetailsBrian McGowan
1st review completed  4/27/2017 FAIL
DetailsBrian McGowan
Several sheets were not legible.
Routing - PLAN CHECK4/17/2017 4/27/2017 FAIL
DetailsBrian McGowan
Several sheets were not legible.
Routing - MECHANICAL4/17/2017 4/26/2017 PASS
DetailsTroy James
Routing - PLANNING4/17/2017 4/19/2017 PASS
DetailsJeff Lowe
Route to Impact Fee Review4/17/20174/20/20174/18/2017 PASS
DetailsTonya Wallace
Initial residential review of new SFD permits requested for now.
Routing - Addressing4/17/2017 4/18/2017 PASS
DetailsLaura Hunter
Routing - PUBLIC WORKS4/17/2017 4/18/2017 PASS
DetailsMorgan Webb
Application received  4/17/2017 DONE
Application submitted via PDS Online on Apr 17 2017 1:32PM
Plan assigned to (AJS)4/17/20174/17/20174/17/2017 DEFR
DetailsAdele J Schaffeld-Griffin
Plans ACCEPTED BY PLAN TECH  4/17/2017 DONE
Intake Approval  4/17/2017 PASS
Recd Pcfee & Taken To Pln CK  4/17/2017 DONE