Third Notice | | 3/5/2018 | 4/6/2018 | | DONE |
|
|
|
This permit finaled on the web by kevin debelloy
|
Third Notice | | 1/17/2018 | 2/12/2018 | | DONE |
Christina Prado
|
|
|
|
Third Notice | | 12/17/2017 | 1/12/2018 | | DONE |
|
|
|
Mailed 1-12-18
|
Third Notice | | 11/19/2017 | 12/12/2017 | | DONE |
|
|
|
Mailed 12-13-17
|
Second Notice | | 10/22/2017 | 11/14/2017 | | DONE |
|
|
|
Mailed 11-15-17
|
First Notice | | 9/25/2017 | 10/12/2017 | | DONE |
|
|
|
Mailed 10-13-17
|
BLD-Final | 9/14/2017 | 9/14/2017 | 9/15/2017 | P | PASS |
Jim Storey
|
|
|
Josh Phone #: ###-#### final ok no card on site
|
Print Occupancy Form | | | 9/15/2017 | | DONE |
|
|
|
|
Permanent Occupancy | | | 9/15/2017 | | DONE |
|
|
|
|
BLD-Final | 7/20/2017 | 7/20/2017 | 7/20/2017 | P | FAIL |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by kevin debelloy need racking permit/ door hardware 2 nd floor/ back handrail if on plan set
|
FIRE-Final Inspection | 7/17/2017 | 7/17/2017 | 7/17/2017 | P | PASS |
Jim Page
|
|
|
Fire sprinkler inspection complete, final life fire safety inspection passed/complete
|
FIRE-Final Inspection | 6/19/2017 | 6/19/2017 | 6/19/2017 | A | FAIL |
Jim Page
|
|
|
Modifications need to be made to the fire sprinkler system to accomodate newly added equipment and roll up overhead door along the north wall. Storage racks exceed 8 feet in height, a racking permit is required for storage that exceeds 8 feet or the storage and racking needs to be lowered below 8 feet to the top of storage.
|
CHANGE STATUS TO (ISS) | | | 6/16/2017 | | DONE |
|
|
|
|
(F) Reprint permit | | | 6/16/2017 | | DONE |
|
|
|
|
Plan assigned to (JAR) | 5/11/2017 | 5/11/2017 | 5/31/2017 | | DONE |
Julie Romig
|
|
|
Plan Mod - Resubmit rec'd on 05/24 - Sealmaster TI ePlan
|
Permit Ready to Issue | | | 5/31/2017 | | DONE |
|
|
|
DO NOT REISSUE; need revised value from GC
|
Routing - PLAN CHECK | 5/26/2017 | | 5/26/2017 | | PASS |
Julie Romig
|
|
|
Plan Modification for new overhead door and relocated drinking fountain.
|
Routing Off Site - STRUCTURAL | 5/24/2017 | | 5/25/2017 | | PASS |
Julie Romig
|
|
|
Plan Modification approved per ePlanReview
|
Routing - PLAN CHECK | 5/24/2017 | | 5/25/2017 | | FAIL |
Julie Romig
|
|
|
Applicant had additional information to include in plan modification. Failed in ePlanReview so applicant could upload new sheet.
|
Routing Off Site - STRUCTURAL | 5/11/2017 | | 5/23/2017 | | FAIL |
Julie Romig
|
|
|
Plan Mod - Corrections required in ePlanReview
|
Routing - Design Review | 5/11/2017 | | 5/17/2017 | | PASS |
Sarah Schafer
|
|
|
Approved by Sarah Schafer per ePlanReview.
|
Routing - Erosion and Sediment | 5/11/2017 | | 5/15/2017 | | PASS |
Andy J. Long
|
|
|
No ESC permit needed
|
Routing - PLAN CHECK | 5/11/2017 | | 5/11/2017 | | FAIL |
Julie Romig
|
|
|
Plan Mod - Need overhead door R-value for IECC compliance.
|
Routing - PLANNING | 5/11/2017 | | 5/11/2017 | | PASS |
Cody Riddle
|
|
|
|
Plan Modification Accepted | | | 5/11/2017 | | DONE |
|
|
|
plan mod accepted in e plan
|
BLD-Framing/Rough-in | 5/8/2017 | 5/9/2017 | 5/9/2017 | A | PASS |
Jim Storey
|
|
|
please call Shay at ###-#### 30 minutes before arrival to gain access if you could . Phone #: ###-#### Inspection requested via web by kevin debelloy
|
Route to Impact Fee Review | 5/3/2017 | 5/6/2017 | 5/4/2017 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
Issue PAID IN FULL permit | | | 5/4/2017 | | DONE |
Christina Prado
|
|
|
|
Print Occupancy Form | | | 5/4/2017 | | DONE |
Christina Prado
|
|
|
|
Plan assigned to (JAR) | 4/27/2017 | 4/27/2017 | 5/3/2017 | | DONE |
Julie Romig
|
|
|
1st Review Complete. DUE 05/10 - L2 Sealmaster TI
|
Routing - PLAN CHECK | 4/27/2017 | | 5/3/2017 | | FAIL |
Julie Romig
|
|
|
|
1st review completed | | | 5/3/2017 | | FAIL |
Julie Romig
|
|
|
|
Routing - PLAN CHECK | 5/3/2017 | | 5/3/2017 | | PASS |
Julie Romig
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/3/2017 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 5/3/2017 | | DONE |
|
|
|
Need GC Form, Revised Cert of Value and **waiting for impact review to be completed as of 5-3-17**
|
Routing - FIRE | 5/2/2017 | 5/2/2017 | 5/2/2017 | | PASS |
Scott Arellano
|
|
|
Modifications to the sprinkler system MAY be required. PDS Fire Inspector to verify.
|
Routing - Addressing | 4/27/2017 | | 4/28/2017 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | 4/27/2017 | | 4/28/2017 | | PASS |
Morgan Webb
|
|
|
|
Intake Approval | | | 4/27/2017 | | PASS |
Javier Guzman
|
|
|
|
Intake Approval | | | 4/25/2017 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
Please see submittal standards for required stamping areas.
http://pds.cityofboise.org/media/105041/electronicstandards.pdf
|
Application received | | | 4/20/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Apr 20 2017 4:55PM
|