BLD-Final | 6/16/2017 | 6/16/2017 | 6/16/2017 | P | PASS |
Jim Storey
|
|
|
Mirceas Phone #: ###-####
|
DOC - Permit Finaled | 6/16/2017 | 6/16/2017 | 6/16/2017 | P | PASS |
Jim Storey
|
|
|
|
Issue PAID IN FULL permit | | | 6/14/2017 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 6/14/2017 | | DONE |
|
|
|
|
Plan assigned to (BJM) | 5/26/2017 | 5/26/2017 | 6/13/2017 | | DONE |
Brian McGowan
|
|
|
1st Review Complete - Fail - Must meet Planning requirements
|
Routing - PLAN CHECK | 6/13/2017 | | 6/13/2017 | | PASS |
Brian McGowan
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/13/2017 | | DONE |
Brian McGowan
|
|
|
ESC no Energy Yes
|
Permit Ready to Issue | | | 6/13/2017 | | DONE |
|
|
|
Need GC form from parcel owner
|
Routing - PLANNING | 6/12/2017 | | 6/12/2017 | | PASS |
Sue Cummings
|
|
|
site plan showing additional parking submitted 6/12/17 O.K. now
|
Routing - PLANNING | 5/26/2017 | | 5/31/2017 | | FAIL |
Sue Cummings
|
|
|
Please see change marks in E-Plan. Two off street parking places are required for each dwelling. Required parking is not allowed in the setbacks. Please provide a new site plan showing a new parking space OR locate the laundry room elsewhere
|
Routing - PLAN CHECK | 5/26/2017 | | 5/31/2017 | | FAIL |
Brian McGowan
|
|
|
Meet Planning requirements
|
1st review completed | | | 5/31/2017 | | FAIL |
Brian McGowan
|
|
|
Meet Planning requirements
|
Intake Approval | | | 5/26/2017 | | PASS |
|
|
|
|
Intake Approval | | | 5/25/2017 | | FAIL |
|
|
|
1. This project is required to be routed to planning and zoning for review. Please provide site plan of overall property showing location of dwelling and driveway dimensions. Provide dimensions of remaining garage space.
2. Provide full floor plan of the entire floor. If multiple floors only required to provide the full floor plan of the level where the remodeling will be taking place (only need dimensions of areas being remodeled). Call out uses of all rooms on floor plan. (call out use of new room)
3. Provide cross section. Show existing slab, sill, anchorage, studs framing, wall covering and insulation (if applicable), ceiling, and ceiling height. If room will be conditioned show compliance with prescriptive energy code or provide RESCheck. Provide details of existing or new steps/stoop if applicable.
|
Application received | | | 4/21/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Apr 21 2017 1:23PM
|