BLD-Final | 5/18/2018 | 5/21/2018 | 5/21/2018 | A | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Clint Wall
|
DOC - Permit Finaled | 5/21/2018 | 5/21/2018 | 5/21/2018 | P | PASS |
Brandon Shaw
|
|
|
|
BLD-Blower Door Test Results | 5/18/2018 | 5/21/2018 | 5/21/2018 | A | DONE |
Brandon Shaw
|
|
|
ACH 50- 4.2
|
PubWorks Occupancy Approval | 5/15/2018 | 5/15/2018 | 5/15/2018 | | DONE |
Melissa Jannusch
|
|
|
A letter from the applicant’s civil engineer indicating that the final grading and drainage is acceptable has been received by Public Works. Final occupancy may be approved by the building department. Melissa Jannusch ###-####.
|
BLD-Energy code compliance | 3/22/2018 | 3/23/2018 | 3/23/2018 | A | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Clint Wall
|
BLD-Framing/Rough-in | 3/19/2018 | 3/21/2018 | 3/21/2018 | A | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Clint Wall
|
BLD-Other | 3/2/2018 | 3/2/2018 | 3/2/2018 | A | PASS |
Brandon Shaw
|
|
|
Soffit
|
BLD-Wall Bracing | 3/1/2018 | 3/2/2018 | 3/2/2018 | A | PASS |
Brandon Shaw
|
|
|
Shear // Guillermo Phone #: ###-####
|
BLD-Aging Inspection | 12/14/2017 | 12/14/2017 | 12/14/2017 | | PEND |
Brandon Shaw
|
|
|
Work in progress
|
BLD-Aging Inspection | 12/13/2017 | 12/13/2017 | 12/13/2017 | | PEND |
Brandon Shaw
|
|
|
Work in progress
|
BLD-Foundation | 7/31/2017 | 8/1/2017 | 8/1/2017 | A | PASS |
Brandon Shaw
|
|
|
Phone #: 2089495359 >> Inspection requested via mobile web by Ricardo
|
BLD-Footing | 7/28/2017 | 7/31/2017 | 7/31/2017 | P | PASS |
Brandon Shaw
|
|
|
Phone #: 2089495359 >> Inspection requested via mobile web by Ricardo
|
BLD-Footing | 7/27/2017 | 7/28/2017 | 7/28/2017 | P | CANC |
Brandon Shaw
|
|
|
Phone #: 2089495359 >> Inspection requested via mobile web by Ricardo
|
PubWorks Subgrade Approval | 7/28/2017 | 7/28/2017 | 7/28/2017 | | DONE |
Melissa Jannusch
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Jason Taylor ###-####.
|
Issue PAID IN FULL permit | | | 6/28/2017 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 6/28/2017 | | DONE |
|
|
|
|
OVERRIDE | | | 6/27/2017 | | |
|
|
|
|
Plan assigned to (LEG) Tisha | 6/13/2017 | | 6/27/2017 | | DONE |
Tisha Gallop
|
|
|
1st review 6/14; eng for two wall lines
|
Plan resubmittals received | | | 6/27/2017 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 6/27/2017 | | 6/27/2017 | | PASS |
Tisha Gallop
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/27/2017 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 6/27/2017 | | DONE |
|
|
|
met
|
1st review completed | | | 6/14/2017 | | FAIL |
|
|
|
need eng for 2 wall bracing lines
|
Routing - PLAN CHECK | 5/25/2017 | | 6/14/2017 | | FAIL |
Brian McGowan
|
|
|
|
Plan assigned to (BJM) | 5/25/2017 | 5/25/2017 | 6/13/2017 | | DEFR |
Brian McGowan
|
|
|
sfd 6-13 - ePlan
|
Routing PW Grading-Hillside | 5/25/2017 | | 6/2/2017 | | PASS |
Jason C. Taylor
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Jason Taylor at ###-####
Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Jason Taylor at ###-####.
|
Route to Impact Fee Review | 5/25/2017 | 5/28/2017 | 5/31/2017 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - MECHANICAL | 5/25/2017 | | 5/30/2017 | | PASS |
Troy James
|
|
|
|
Routing - FIRE | 5/25/2017 | 5/25/2017 | 5/26/2017 | | PASS |
Scott Arellano
|
|
|
Approved for FD vehicle access and proximity to FF water supply.
|
Routing - Erosion and Sediment | 5/25/2017 | | 5/26/2017 | | PASS |
Andy J. Long
|
|
|
East Valley hillside lot. ESC plan waiver approved. Valid RP. Subdivision BMPs installed.
|
Routing - PLANNING | 5/25/2017 | | 5/25/2017 | | PASS |
Sue Cummings
|
|
|
|
Routing - Addressing | 5/25/2017 | | 5/25/2017 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | 5/25/2017 | | 5/25/2017 | | PASS |
Rachael Beierle
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 5/25/2017 | | DONE |
|
|
|
|
Intake Approval | | | 5/25/2017 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 5/25/2017 | | DONE |
|
|
|
|
Application received | | | 4/27/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Apr 27 2017 11:12AM
|