BLD-Final | 2/5/2018 | 2/5/2018 | 2/5/2018 | P | PASS |
Brandon Shaw
|
|
|
Rollo Phone #: ###-####
|
DOC - Permit Finaled | 2/5/2018 | 2/5/2018 | 2/5/2018 | P | PASS |
Brandon Shaw
|
|
|
|
PubWorks Occupancy Approval | 1/26/2018 | 1/26/2018 | 1/26/2018 | | DONE |
Melissa Jannusch
|
|
|
A bond for the sites final grading and re-vegetation has been received by Public Works. Occupancy may be approved by the building department. Melissa Jannusch ###-####.
|
BLD-Other | 10/9/2017 | 10/9/2017 | 10/10/2017 | P | PASS |
Brandon Shaw
|
|
|
soffits - Rollo Phone #: ###-####
|
BLD-Energy code compliance | 9/22/2017 | 9/25/2017 | 9/25/2017 | A | PASS |
Brandon Shaw
|
|
|
Rollo Phone #: ###-####
|
BLD-Framing/Rough-in | 9/21/2017 | 9/21/2017 | 9/21/2017 | P | FAIL |
Brandon Shaw
|
|
|
See correction notice
OK to insulate
|
BLD-Wall Bracing | 9/7/2017 | 9/7/2017 | 9/7/2017 | P | PASS |
Brandon Shaw
|
|
|
Rollo Phone #: ###-####
|
BLD-Foundation | 8/22/2017 | 8/22/2017 | 8/22/2017 | P | CANC |
Brandon Shaw
|
|
|
Dion Phone #: ###-####
|
BLD-Foundation | 7/21/2017 | 7/21/2017 | 7/21/2017 | A | PASS |
Brandon Shaw
|
|
|
As early as possible Phone #: 2084207023 >> Inspection requested via mobile web by Dion Connell
|
BLD-Footing | 7/5/2017 | 7/6/2017 | 7/6/2017 | A | PASS |
Brandon Shaw
|
|
|
As early as possible Phone #: 2084207023 >> Inspection requested via mobile web by Dion Connell
|
Issue PAID IN FULL permit | | | 7/5/2017 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 7/5/2017 | | DONE |
|
|
|
|
PubWorks Subgrade Approval | 6/19/2017 | 6/19/2017 | 6/19/2017 | | DONE |
Jason C. Taylor
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Jason Taylor ###-####.
|
OVERRIDE | | | 5/8/2017 | | |
|
|
|
|
Plan assigned to (CDM) | 5/2/2017 | 5/2/2017 | 5/8/2017 | | PASS |
Carl D Madsen
|
|
|
5/12 SFD
|
1st review completed | | | 5/8/2017 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/8/2017 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 5/8/2017 | | |
|
|
|
all met
|
Routing PW Grading-Hillside | 5/1/2017 | | 5/8/2017 | | PASS |
Jason C. Taylor
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Jason Taylor at ###-####
Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Jason Taylor at ###-####.
|
Routing - PLAN CHECK | 5/1/2017 | | 5/6/2017 | | PASS |
Carl D Madsen
|
|
|
|
Routing - MECHANICAL | 5/1/2017 | | 5/3/2017 | | PASS |
Troy James
|
|
|
|
Route to Impact Fee Review | 5/1/2017 | 5/4/2017 | 5/2/2017 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Pending Assignment by AJS | 5/1/2017 | | 5/2/2017 | | DONE |
Adele J Schaffeld-Griffin
|
|
|
|
Routing - Erosion and Sediment | 5/1/2017 | | 5/2/2017 | | PASS |
Melissa Jannusch
|
|
|
|
Routing - FIRE | 5/1/2017 | 5/1/2017 | 5/1/2017 | | PASS |
Scott Arellano
|
|
|
Plans were reviewed for FD Access, hydrant availability and defensible space.
|
Plans ACCEPTED BY PLAN TECH | | | 5/1/2017 | | DONE |
|
|
|
|
Intake Approval | | | 5/1/2017 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 5/1/2017 | | DONE |
|
|
|
|
Routing - PLANNING | 5/1/2017 | | 5/1/2017 | | PASS |
Sue Cummings
|
|
|
|
Routing - Addressing | 5/1/2017 | | 5/1/2017 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | 5/1/2017 | | 5/1/2017 | | PASS |
Rachael Beierle
|
|
|
|
Application received | | | 4/28/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Apr 28 2017 4:04PM
|