BLD-Final | 10/5/2017 | 10/5/2017 | 10/5/2017 | A | PASS |
Dave Hannah
|
|
|
Phone #: ###-#### Inspection requested via web by kevin debelloy
|
DOC - Permit Finaled | 10/5/2017 | 10/5/2017 | 10/5/2017 | P | PASS |
Dave Hannah
|
|
|
|
Zoning Approval | 10/4/2017 | 10/4/2017 | 10/4/2017 | | PASS |
Katelyn Menuge
|
|
|
Historic Okay
|
BLD-Final | 10/3/2017 | 10/3/2017 | 10/3/2017 | A | NR |
Dave Hannah
|
|
|
Phone #: ###-#### Inspection requested via web by kevin debelloy needs zoning sign off
|
BLD-Framing/Rough-in | 8/14/2017 | 8/15/2017 | 8/15/2017 | A | PASS |
Dave Hannah
|
|
|
Please call with any questions Phone #: ###-#### Inspection requested via web by kevin debelloy
|
BLD-Footing | 7/7/2017 | 7/10/2017 | 7/10/2017 | A | PART |
Tony Young
|
|
|
Concrete pour is scheduled for 1;00 Phone #: ###-#### Inspection requested via web by kevin debelloy,, see notes,, ok
|
BLD-Footing | 7/6/2017 | 7/7/2017 | 7/7/2017 | A | CANC |
Tony Young
|
|
|
Footings are schedule to pour at 1:00 Phone #: ###-#### >> Inspection requested via web by kevin debelloy Inspection cancelled from web by: kevin debelloy
|
Issue PAID IN FULL permit | | | 6/14/2017 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 6/14/2017 | | DONE |
|
|
|
|
OVERRIDE | | | 5/17/2017 | | |
|
|
|
|
OVERRIDE | | | 5/17/2017 | | |
|
|
|
|
Plan assigned to (BJM) | 5/1/2017 | 5/1/2017 | 5/17/2017 | | DONE |
Brian McGowan
|
|
|
Fail- Planning needs more info and I need to know how it is being heated.
|
Routing - PLANNING | 5/17/2017 | | 5/17/2017 | | PASS |
Katelyn Menuge
|
|
|
|
Routing - PLAN CHECK | 5/17/2017 | | 5/17/2017 | | PASS |
Brian McGowan
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/17/2017 | | DONE |
Brian McGowan
|
|
|
|
Permit Ready to Issue | | | 5/17/2017 | | DONE |
|
|
|
need GC and RP
|
Routing - PLAN CHECK | 5/1/2017 | | 5/7/2017 | | FAIL |
Brian McGowan
|
|
|
|
1st review completed | | | 5/7/2017 | | FAIL |
Brian McGowan
|
|
|
How is the structure to be heated.
|
Routing - PLANNING | 5/1/2017 | | 5/4/2017 | | FAIL |
Katelyn Menuge
|
|
|
Need to submit approval letter from Idaho Power.
|
Application received | | | 5/1/2017 | | DONE |
|
|
|
Application submitted via PDS Online on May 1 2017 9:39AM
|
Plans ACCEPTED BY PLAN TECH | | | 5/1/2017 | | DONE |
|
|
|
|
Intake Approval | | | 5/1/2017 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 5/1/2017 | | DONE |
|
|
|
|