Permit Information
Permit NumberBLD17-01277
StatusFinaled
Name K2 CONSTRUCTION
Site Address 2777 S ORCHARD ST
Project NameDennis Dillion GMC Service
Customer NumberBLD17-03694 EARLY START
ePlanReviewYes
Description
(DENNIS DILLION GMC – SERVICE CENTER) 04/27/18 PLAN MODIFICATION FOR NEWLY CONSTRUCTED 2X6 METAL STUD WALL IN DRIVE THRU SERVICE AREA. **JAR**. 01/26/18 PLAN MODIFICATION TO RECONFIGURE INTERIOR PARITIONS AND CABINETRY ON 1ST AND 2ND FLOOR; NEW STRUCTURAL WORK AT CASHIERS DESK WITH STRUCTURAL DRAWINGS AND CALCULATIONS PROVIDED. **JAR** Permit to remodel a 16,629 sq ft portion of a vehicle service building. This portion of the building includes a 2,853 sq ft second floor storage platform that was never permitted and is now accounted for in the building square footage. A structural analysis has been completed on the platform, which the requires additional reinforcement; see attached letter and special inspection form. Other work to include: demolition of non-structural interior walls, expanding 2nd floor bathrooms into existing storage area, upgrade existing restrooms to comply with current accessibility standards, installation of new accessible doors/hardware, new lighting, and new interior finishes in accordance with Ch. 8 of the 2012 IBC. This building is fully Fire Sprinklered with an approved Fire Alarm system. Any alterations or modifications to the buildings Fire Sprinkler or Fire Alarm system WILL REQUIRE A SEPARATE PERMIT and shall be installed per NFPA 13 & NFPA 72 as regulated by the Boise Fire Department. Approval is contingent on the contractor adhering to the approved drawings and engineering on site. **JAR**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Print Statement  9/12/2018 DONE
Print Statement  9/12/2018 DONE
Second Notice 8/17/20189/6/2018 DONE
mailed 9-10-18
First Notice 7/27/20188/7/2018 DONE
Mailed 8-10-18
BLD-Final7/13/20187/17/20187/17/2018APASS
DetailsDave Hannah
Herb ###-####
Permanent Occupancy  7/17/2018 DONE
FIRE-Final Inspection7/13/20187/16/20187/16/2018PPASS
DetailsTroy Cobbley
life safetyu passed

Herb ###-####
BLD-Final5/16/20185/16/20185/16/2018PCANC
DetailsJim Sly
Julio Phone #: ###-####
BLD-Final5/10/20185/11/20185/16/2018APART
DetailsJim Sly
Julio Phone #: ###-####
OK for Temp Occ.
FIRE-Final Inspection5/16/20185/16/20185/16/2018PPART
DetailsJim Page
Fire sprinkler inspection complete, no fire alarm modifications, fire extinguishers are in place with current inspection tags, work is still to be completed on level 2, final life fire safety inspection for level 1 complete, level 2 will be scheduled for a later date.

Juloe Phone #: ###-####
FIRE-Final Inspection5/1/20185/2/20185/2/2018AFAIL
DetailsTroy Cobbley
For a life safety final I need the sprinkler coverage and door hardware issues corrected on the ground floor as noted on the plans.

Julio Phone #: ###-####
CHANGE STATUS TO (ISS)  5/1/2018 DONE
Plan Mod
Print Occupancy Form  5/1/2018 DONE
Plan assigned to (JAR)4/20/20184/20/20184/27/2018 DONE
DetailsJulie Romig
**Plan Mod #2 - 04/26 - Dennis Dillion GMC - egress openings created to seperate the two auto bays
Routing - PLAN CHECK4/20/2018 4/27/2018 PASS
DetailsJulie Romig
Permit Ready to Issue  4/27/2018 DONE
Plan mod DO NOT REISSUE
Print Occupancy Form  4/27/2018 DONE
BLD-Final4/17/20184/20/20184/20/2018APART
DetailsJim Sly
For temp // Julio Phone #: ###-####
See Fire inspectors Previous notes.
FIRE-Final Inspection4/17/20184/20/20184/20/2018APART
DetailsTroy Cobbley
The Point of Sale area life safety is passed. There is a issue with exiting, as per plans, from this area. The two exit signs have not been installed but if they end up being installed one of the two doors has a manual roll down security gate in front of it. Also as per the previous inspection the wall that was shown to be demolished in the Service Bay was actually rebuilt with framed openings and newly added exit signs. This does not match plans. Other corrections are adding sprinkler protection in the east office area and removing all of the (5 doors) keyed dead bolts. An exit discharge needs to be repaired at the east exit door and one added at the south exit door.

Julio Phone #: ###-####
Plan Modification Accepted  4/20/2018 DONE
DetailsChristina Prado
Plan Mod #2 - egress openings created to seperate the two auto bays
FIRE-Conference3/16/20183/16/20183/16/2018PDONE
DetailsTroy Cobbley
The contractor and I discussed the wall in the "Drive Thru" that is shown to be demo'd. If this wall is to remain it appears that it may cause exiting issues from the Cashier area. There is a life safety plan that shows exit signs in the Cashier area that direct people to this Drive Thru. If people go into the Drive Thru this wall will block access to the exterior exit doors on the other side of the wall. At a minimum wall layout needs to match what is being built.
BLD-Framing/Rough-in2/6/20182/7/20182/7/2018APASS
DetailsJim Sly
Julio Phone #: ###-####
BLD-Ceiling Grid Inspection2/6/20182/7/20182/7/2018APASS
DetailsJim Sly
Julio Phone #: ###-####
Permit Ready to Issue  1/29/2018 DONE
DO NOT REISSUE PLAN MOD
CHANGE STATUS TO (ISS)  1/29/2018 DONE
(F) Reprint permit  1/29/2018 DONE
Print Occupancy Form  1/29/2018 DONE
Plan assigned to (JAR)1/9/20181/9/20181/26/2018 DONE
DetailsJulie Romig
**1st Rev Comp - 2nd Rec'd 01/24 - Plan Mod - Dennis Dillion GMC
Routing - PLAN CHECK1/24/2018 1/26/2018 PASS
DetailsJulie Romig
Plan Mod 2nd Review
Routing Off Site - STRUCTURAL1/10/2018 1/22/2018 PASS
DetailsJulie Romig
Plan Mod
Routing - PLAN CHECK1/10/2018 1/22/2018 FAIL
DetailsJulie Romig
Plan Mod
Routing - FIRE1/10/20181/10/20181/16/2018 PASS
DetailsScott Arellano
Plan Mod; previous comments apply
FIRE-Conference1/11/20181/12/20181/12/2018ADONE
DetailsTroy Cobbley
We discussed possible exiting options but without the latest city approved plans not much could be finalized


Julio Phone #: ###-####
BLD-Framing/Rough-in1/10/20181/10/20181/10/2018PPART
DetailsJim Sly
Julio-wall inspection on 2nd upstairs, 1st floor cashier area - Julio said this inspection is not in any area of the plan mod that''s in for review Phone #: ###-####
Plan Modification Accepted  1/9/2018 DONE
DetailsChristina Prado
Plan Mod - modifications to the 1st & 2nd floor for new desk arrangement, fireplace addition and related structural calculations
Permit Ready to Issue  12/21/2017 DONE
DetailsChristina Prado
Need
GC - met
Revised Cert of Value - met
Issue PAID IN FULL permit  12/21/2017 DONE
Print Occupancy Form  12/21/2017 DONE
Inspection Record Card- Bld  12/21/2017 DONE
Plan assigned to (JAR)5/15/20175/15/201712/20/2017 DONE
DetailsJulie Romig
1st Rev Comp - 4th Comp - L2 DD GMC Office Remodel ePlan
Routing - PLAN CHECK12/20/2017 12/20/2017 PASS
DetailsJulie Romig
PLANS/APPL TAKEN TO FRONT DESK  12/20/2017 DONE
Routing - PLAN CHECK12/16/2017 12/19/2017 FAIL
DetailsJulie Romig
4th Review
Routing - PLAN CHECK11/27/2017 12/15/2017 FAIL
DetailsJulie Romig
3rd Review
Extend Review Timeline  11/17/2017 DONE
1st Approved 180 day extension per Adele. See documents
Routing - PLAN CHECK10/3/2017 10/17/2017 FAIL
DetailsJulie Romig
Route to Impact Fee Review6/13/20176/16/20176/14/2017 PASS
DetailsMarissa Taylor
Review requested for Commercial Permit
Routing - FIRE6/13/20176/13/20176/13/2017 PASS
DetailsScott Arellano
Pending approved IBC plan review correction items. Fire review attached.
1st review completed  6/13/2017 FAIL
DetailsJulie Romig
Routing - PLAN CHECK5/15/2017 6/13/2017 FAIL
DetailsJulie Romig
Routing - Addressing5/15/2017 5/15/2017 PASS
DetailsLaura Hunter
Routing - PUBLIC WORKS5/15/2017 5/15/2017 PASS
DetailsRachael Beierle
Intake Approval  5/15/2017 PASS
DetailsJavier Guzman
Intake Approval  5/9/2017 FAIL
DetailsJulie Romig
Need lighting comcheck or information showiing compliance with C101.4.3 Exception 7.
Application received  5/1/2017 DONE
Application submitted via PDS Online on May 1 2017 3:47PM