First Notice | | 9/15/2017 | 9/19/2017 | | DONE |
|
|
|
This permit finaled on the web by John Rice
|
BLD-Final | 9/1/2017 | 9/5/2017 | 9/5/2017 | A | PASS |
Brandon Shaw
|
|
|
Abel Phone #: ###-####
|
DOC - Permit Finaled | 9/5/2017 | 9/5/2017 | 9/5/2017 | P | PASS |
Brandon Shaw
|
|
|
|
Permanent Occupancy | | | 9/5/2017 | | DONE |
|
|
|
|
BLD-Final | 8/14/2017 | 8/15/2017 | 8/15/2017 | A | PASS |
Jim Storey
|
|
|
Abel Phone #: ###-#### pending others
|
BLD-Final | 8/14/2017 | 8/14/2017 | 8/14/2017 | P | PART |
Jim Storey
|
|
|
Abel Phone #: ###-#### temp ok pending trades
|
FIRE-Final Inspection | 8/14/2017 | 8/14/2017 | 8/14/2017 | P | PASS |
Jim Page
|
|
|
Fire sprinkler inspection complete, fire alarm inspection complete (Mag locks for tenant space release on general fire alarm), fire extinguishers are in place with current inspection tags. Final life fire safety inspection for area of work passed/complete.
|
Temporary Occupancy | 8/14/2017 | 11/12/2017 | 8/14/2017 | | DONE |
Candy A. Nichols
|
|
|
|
BLD-Final | 8/11/2017 | 8/11/2017 | 8/11/2017 | P | NR |
Jim Storey
|
|
|
Able Phone #: ###-####
|
FIRE-Final Inspection | 8/11/2017 | 8/11/2017 | 8/11/2017 | P | FAIL |
Troy Cobbley
|
|
|
Need the project related fire alarm permit finaled. Need to repair the two exit signs and provide two exit signs in the Break Room. Need panic hardware installed in Break Room. Need additional emergency lighting in the Open Office area. Need fire extinguishers provided.
|
BLD-Ceiling Grid Inspection | 7/21/2017 | 7/21/2017 | 7/21/2017 | P | PASS |
Jim Storey
|
|
|
Abel-would like as late as possible Phone #: ###-####
|
CHANGE STATUS TO (ISS) | | | 7/6/2017 | | DONE |
|
|
|
|
(F) Reprint permit | | | 7/6/2017 | | DONE |
|
|
|
plan mod
|
(F) Reprint permit | | | 7/6/2017 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 6/30/2017 | | DONE |
|
|
|
**DO NOT REISSUE** Plan mod, fees due.
|
Plan assigned to (JAR) | 6/7/2017 | 6/7/2017 | 6/29/2017 | | DONE |
Julie Romig
|
|
|
PLAN MOD - 1st review 06/23/17 - rec'd 06/08/17 - Litster Frost
|
Routing - PLAN CHECK | 6/26/2017 | | 6/29/2017 | | PASS |
Julie Romig
|
|
|
Plan Mod Resubmit
|
Routing - PLAN CHECK | 6/8/2017 | | 6/24/2017 | | FAIL |
Julie Romig
|
|
|
Plan Mod - Need Door, Hardware, and Window schedules.
|
Routing - FIRE | 6/8/2017 | 6/8/2017 | 6/8/2017 | | PASS |
Katie Marron
|
|
|
Reviewed plan modifications. No changes to previous comments required.
|
Routing - PUBLIC WORKS | 6/8/2017 | | 6/8/2017 | | PASS |
Rachael Beierle
|
|
|
|
BLD-Framing/Rough-in | 6/6/2017 | 6/7/2017 | 6/7/2017 | A | PART |
Jim Storey
|
|
|
Abel Phone #: ###-####walls ok except for plm hole in floor firestopping re insp.
|
Plan Modification Accepted | | | 6/7/2017 | | DONE |
Christina Prado
|
|
|
Plan Mod accepted for interior changes to the floor plan
|
BLD-Framing/Rough-in | 5/30/2017 | 5/31/2017 | 5/31/2017 | A | PART |
Brandon Shaw
|
|
|
Able Phone #: ###-#### Phase II A, framing, OK to insulate/cover
|
Issue PAID IN FULL permit | | | 5/30/2017 | | DONE |
|
|
|
|
Print Occupancy Form | | | 5/30/2017 | | DONE |
|
|
|
|
Plan assigned to (JAR) | 5/2/2017 | 5/2/2017 | 5/24/2017 | | DONE |
Julie Romig
|
|
|
1st Review Complete. DUE 05/15 - L2 Litster Frost TI
|
Routing - PLAN CHECK | 5/15/2017 | | 5/24/2017 | | PASS |
Julie Romig
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/24/2017 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 5/24/2017 | | DONE |
|
|
|
Need revised cert of value and GC form
|
Routing - FIRE | 5/15/2017 | 5/15/2017 | 5/17/2017 | | PASS |
Scott Arellano
|
|
|
Revised report attached to case.
|
Route to Impact Fee Review | 5/13/2017 | 5/16/2017 | 5/15/2017 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
Routing - PLAN CHECK | 5/2/2017 | | 5/13/2017 | | FAIL |
Julie Romig
|
|
|
|
1st review completed | | | 5/13/2017 | | FAIL |
Julie Romig
|
|
|
|
Routing - FIRE | 5/2/2017 | 5/2/2017 | 5/3/2017 | | FAIL |
Katie Marron
|
|
|
Report attached to case and emailed to architect.
|
Routing - Addressing | 5/2/2017 | | 5/3/2017 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | 5/2/2017 | | 5/3/2017 | | PASS |
Morgan Webb
|
|
|
|
Intake Approval | | | 5/2/2017 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
Julie completed pre screen, verified fees paid
|
Application received | | | 5/1/2017 | | DONE |
|
|
|
Application submitted via PDS Online on May 1 2017 4:06PM
|