BLD-Final | 2/14/2018 | 2/14/2018 | 2/14/2018 | P | PASS |
Jim Storey
|
|
|
Rollo Phone #: ###-####
|
DOC - Permit Finaled | 2/14/2018 | 2/14/2018 | 2/14/2018 | P | PASS |
Jim Storey
|
|
|
|
BLD-Final | 2/12/2018 | 2/13/2018 | 2/13/2018 | A | NH |
Mike Jordan
|
|
|
Rolo Phone #: ###-####. No access.
|
PubWorks Occupancy Approval | 2/9/2018 | 2/9/2018 | 2/9/2018 | | DONE |
Melissa Jannusch
|
|
|
A letter from the applicant’s civil engineer indicating that the final grading and drainage is acceptable has been received by Public Works. Final occupancy may be approved by the building department. Melissa Jannusch ###-####.
|
BLD-Final | 2/7/2018 | 2/7/2018 | 2/7/2018 | P | CANC |
Brandon Shaw
|
|
|
rollo Phone #: ###-####
|
BLD-Aging Inspection | 12/21/2017 | 12/21/2017 | 12/26/2017 | | DONE |
Brandon Shaw
|
|
|
Work in progress
|
BLD-Aging Inspection | 12/20/2017 | 12/20/2017 | 12/20/2017 | | DONE |
Brandon Shaw
|
|
|
|
BLD-Final | 12/13/2017 | 12/13/2017 | 12/13/2017 | P | CANC |
Brandon Shaw
|
|
|
Per Brad
|
BLD-Conference | 9/21/2017 | 9/22/2017 | 9/22/2017 | A | PART |
Brandon Shaw
|
|
|
81-1 HN sofit inspection Phone #: ###-#### Inspection requested via web by Brad McJunkin
|
BLD-Other | 9/20/2017 | 9/20/2017 | 9/20/2017 | P | PASS |
Brandon Shaw
|
|
|
WUI soffit // Rollo Phone #: ###-####
|
BLD-Energy code compliance | 8/7/2017 | 8/8/2017 | 8/8/2017 | A | PASS |
Brandon Shaw
|
|
|
Rollo Phone #: ###-####
|
BLD-Framing/Rough-in | 8/4/2017 | 8/4/2017 | 8/4/2017 | P | PASS |
Brandon Shaw
|
|
|
Rolo Phone #: ###-####
|
Plan Modification Accepted | | | 7/25/2017 | | DONE |
|
|
|
new manual j report
|
Routing - MECHANICAL | 7/25/2017 | | 7/25/2017 | | PASS |
Troy James
|
|
|
resubmitted manual j report
|
BLD-Wall Bracing | 7/19/2017 | 7/19/2017 | 7/19/2017 | P | PASS |
Brandon Shaw
|
|
|
Rollo Phone #: ###-####
|
BLD-Foundation | 6/1/2017 | 6/2/2017 | 6/5/2017 | P | PART |
Brandon Shaw
|
|
|
As late as possible Phone #: 2084207023 >> Inspection requested via mobile web by Dion Connell
|
BLD-Footing | 6/1/2017 | 6/1/2017 | 6/1/2017 | P | PASS |
Brandon Shaw
|
|
|
|
PubWorks Subgrade Approval | 5/26/2017 | 5/26/2017 | 5/26/2017 | | DONE |
Jason C. Taylor
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Jason Taylor ###-####.
|
Issue PAID IN FULL permit | | | 5/17/2017 | | DONE |
Christina Prado
|
|
|
|
Inspection Record Card- Bld | | | 5/17/2017 | | DONE |
Christina Prado
|
|
|
|
OVERRIDE | | | 5/9/2017 | | |
|
|
|
|
Plan assigned to (CDM) | 5/3/2017 | 5/3/2017 | 5/9/2017 | | PASS |
Carl D Madsen
|
|
|
|
1st review completed | | | 5/9/2017 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/9/2017 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 5/9/2017 | | DONE |
|
|
|
met
|
Routing - MECHANICAL | 5/3/2017 | | 5/9/2017 | | PASS |
Troy James
|
|
|
|
Routing PW Grading-Hillside | 5/3/2017 | | 5/8/2017 | | PASS |
Jason C. Taylor
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Jason Taylor at ###-####
Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Jason Taylor at ###-####.
|
Routing - PLAN CHECK | 5/3/2017 | | 5/6/2017 | | PASS |
Carl D Madsen
|
|
|
|
Route to Impact Fee Review | 5/3/2017 | 5/6/2017 | 5/4/2017 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - Erosion and Sediment | 5/3/2017 | | 5/4/2017 | | PASS |
Andy J. Long
|
|
|
ESC narrative with site map approved. Valid RP and PD. Site preparation inspection required.
|
Routing - FIRE | 5/3/2017 | 5/3/2017 | 5/3/2017 | | PASS |
Scott Arellano
|
|
|
plans were reviewed for FD access, hydrant availability and defensible space.
|
Routing - PLANNING | 5/3/2017 | | 5/3/2017 | | PASS |
Sue Cummings
|
|
|
|
Routing - Addressing | 5/3/2017 | | 5/3/2017 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | 5/3/2017 | | 5/3/2017 | | PASS |
Rachael Beierle
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 5/3/2017 | | DONE |
|
|
|
|
Intake Approval | | | 5/3/2017 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 5/3/2017 | | DONE |
|
|
|
|
Pending Assignment by AJS | 5/3/2017 | | 5/3/2017 | | DONE |
Adele J Schaffeld-Griffin
|
|
|
|
Application received | | | 5/2/2017 | | DONE |
|
|
|
Application submitted via PDS Online on May 2 2017 10:56AM
|