BLD-Final | 9/5/2017 | 9/6/2017 | 9/6/2017 | A | PASS |
Mike Jordan
|
|
|
MIke Phone #: ###-####
|
DOC - Permit Finaled | 9/6/2017 | 9/6/2017 | 9/6/2017 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Framing/Rough-in | 7/20/2017 | 7/24/2017 | 7/24/2017 | A | PEND |
Brandon Shaw
|
|
|
Pend electrical rough in, all electrical to be surface mounted
|
Routing Walk-In (Zoning) | 7/3/2017 | 7/3/2017 | 7/3/2017 | A | PASS |
Katelyn Menuge
|
|
|
Addition roof change okay
|
Routing Walk-In (BLD) | 7/3/2017 | 7/3/2017 | 7/3/2017 | A | DONE |
Josh Bogle
|
|
|
|
1st review completed | | | 7/3/2017 | | DONE |
Josh Bogle
|
|
|
|
Routing - PLAN CHECK | 7/3/2017 | | 7/3/2017 | | PASS |
Josh Bogle
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/3/2017 | | DONE |
Josh Bogle
|
|
|
No fee for El Queso Grande
|
Permit Ready to Issue | | | 7/3/2017 | | DONE |
Christina Prado
|
|
|
|
CHANGE STATUS TO (ISS) | | | 7/3/2017 | | DONE |
Christina Prado
|
|
|
|
BLD-Foundation | 5/15/2017 | 5/16/2017 | 5/16/2017 | A | PART |
Tony Young
|
|
|
Mike Phone #: ###-####
|
BLD-Footing | 5/11/2017 | 5/15/2017 | 5/15/2017 | A | PART |
Tony Young
|
|
|
Mike Phone #: ###-####,, work in progress
|
Routing Walk-In (Zoning) | 5/5/2017 | 5/5/2017 | 5/5/2017 | A | PASS |
Jeff Lowe
|
|
|
|
Routing Walk-In (BLD) | 5/5/2017 | 5/5/2017 | 5/5/2017 | A | DONE |
Josh Bogle
|
|
|
|
1st review completed | | | 5/5/2017 | | DONE |
Josh Bogle
|
|
|
|
Routing - PLAN CHECK | 5/5/2017 | | 5/5/2017 | | PASS |
Josh Bogle
|
|
|
|
Case Summary (BLD) | | | 5/5/2017 | | DONE |
Josh Bogle
|
|
|
|
Inspection Record Card- Bld | | | 5/5/2017 | | DONE |
Josh Bogle
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/5/2017 | | DONE |
Josh Bogle
|
|
|
|
Permit Ready to Issue | | | 5/5/2017 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 5/5/2017 | | DONE |
|
|
|
|
Application received | | 5/5/2017 | | | |
|
|
|
|