BLD-Final | 10/31/2017 | 10/31/2017 | 10/31/2017 | P | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Kyle Seick
|
DOC - Permit Finaled | 10/31/2017 | 10/31/2017 | 10/31/2017 | P | PASS |
Brandon Shaw
|
|
|
|
BLD-Final | 10/30/2017 | 10/30/2017 | 10/30/2017 | P | PART |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Kyle Seick
|
BLD-Framing/Rough-in | 9/5/2017 | 9/5/2017 | 9/5/2017 | P | PASS |
Brandon Shaw
|
|
|
Rollo Phone #: ###-####
|
Fees Due Hold | 9/2/2017 | | 9/5/2017 | | DONE |
Christina Prado
|
|
|
|
BLD-Energy code compliance | 9/1/2017 | 9/1/2017 | 9/1/2017 | P | FAIL |
Brandon Shaw
|
|
|
Previous corrections not met, re-inspection fee applies
|
BLD-Energy code compliance | 8/31/2017 | 9/1/2017 | 9/1/2017 | A | CANC |
Brandon Shaw
|
|
|
Phone #: ###-#### >> Inspection requested via web by Kyle Seick Inspection cancelled from web by: Kyle Seick
|
BLD-Energy code compliance | 8/31/2017 | 8/31/2017 | 8/31/2017 | P | FAIL |
Brandon Shaw
|
|
|
Hold downs still need to be installed, no cover
|
BLD-Framing/Rough-in | 8/30/2017 | 8/30/2017 | 8/30/2017 | P | FAIL |
Brandon Shaw
|
|
|
As per walk through, 1 )bracket/hanger for bearing end of beam @ master bathroom 2) bearing stud for 2 ply truss @ master bathroom 3) lateral bracing for trusses @ up stairs bonus room OK to insulate
|
BLD-Wall Bracing | 8/18/2017 | 8/18/2017 | 8/18/2017 | P | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Kyle Seick
|
BLD-Foundation | 6/13/2017 | 6/13/2017 | 6/13/2017 | P | PASS |
Brandon Shaw
|
|
|
As late as possible Phone #: 2084207023 >> Inspection requested via mobile web by Dion Connell
|
BLD-Footing | 6/12/2017 | 6/12/2017 | 6/12/2017 | P | PASS |
Brandon Shaw
|
|
|
As late as possible Phone #: 2084207023 >> Inspection requested via mobile web by Dion Connell
|
OVERRIDE | | | 6/7/2017 | | |
|
|
|
|
Plan assigned to (BJM) | 5/8/2017 | 5/8/2017 | 6/7/2017 | | DONE |
Brian McGowan
|
|
|
sfd 5-19 ePlan
|
1st review completed | | | 6/7/2017 | | DONE |
Brian McGowan
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/7/2017 | | DONE |
Brian McGowan
|
|
|
|
Permit Ready to Issue | | | 6/7/2017 | | DONE |
Christina Prado
|
|
|
All requirements met
|
Issue PAID IN FULL permit | | | 6/7/2017 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 6/7/2017 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 5/8/2017 | | 6/7/2017 | | PASS |
Brian McGowan
|
|
|
|
Routing - MECHANICAL | 5/8/2017 | | 5/10/2017 | | PASS |
Troy James
|
|
|
|
Route to Impact Fee Review | 5/8/2017 | 5/11/2017 | 5/9/2017 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Plan assigned to (AJS) | 5/8/2017 | 5/8/2017 | 5/8/2017 | | DEFR |
Adele J Schaffeld-Griffin
|
|
|
|
Intake Approval | | | 5/8/2017 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 5/8/2017 | | DONE |
|
|
|
|
Routing - PLANNING | 5/8/2017 | | 5/8/2017 | | PASS |
Sue Cummings
|
|
|
|
Routing - Addressing | 5/8/2017 | | 5/8/2017 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | 5/8/2017 | | 5/8/2017 | | PASS |
Morgan Webb
|
|
|
|
Application received | | | 5/5/2017 | | DONE |
|
|
|
Application submitted via PDS Online on May 5 2017 2:14PM
|