First Notice | 9/1/2017 | 9/1/2017 | 9/6/2017 | | DONE |
Dave Hannah
|
|
|
received the final values threw email
|
BLD-Final | 8/30/2017 | 8/31/2017 | 9/1/2017 | P | DONE |
Dave Hannah
|
|
|
Shawn Phone #: ###-####-please call 1 hour prior to meet
|
BLD-Final | 8/31/2017 | 9/1/2017 | 9/1/2017 | A | PASS |
Dave Hannah
|
|
|
Sean Phone #: ###-####
|
DOC - Permit Finaled | 9/1/2017 | 9/1/2017 | 9/1/2017 | P | PASS |
Dave Hannah
|
|
|
|
FIRE-Final Inspection | 8/30/2017 | 8/31/2017 | 8/31/2017 | A | PASS |
Jim Page
|
|
|
Fire sprinkler inspection complete, fire alarm inspection complete, fire extinguisher is in place with a current inspection tag. Final life fire safety inspection for area of work passed/complete.
|
BLD-Framing/Rough-in | 6/30/2017 | 7/6/2017 | 7/7/2017 | P | PASS |
Dave Hannah
|
|
|
Shawn-please call 30 mintues prior to meet Phone #: ###-####
|
BLD-Wall Bracing | 6/30/2017 | 7/6/2017 | 7/6/2017 | P | PASS |
Dave Hannah
|
|
|
Shawn-please call 30 mintues prior to meet Phone #: ###-####
|
Inspection Record Card- Bld | | | 6/23/2017 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 6/23/2017 | | DONE |
|
|
|
|
Route to Impact Fee Review | 5/13/2017 | 5/16/2017 | 5/15/2017 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
Permit Ready to Issue | | | 5/15/2017 | | DONE |
Christina Prado
|
|
|
Need GC form & revised certificate of value for issuance
|
Plan assigned to (JG) | 5/9/2017 | 5/9/2017 | 5/13/2017 | | PASS |
Javier Guzman
|
|
|
5/15 L1 Ada County Public Defender TI ePlan
|
Routing - PLAN CHECK | 5/9/2017 | | 5/13/2017 | | PASS |
Javier Guzman
|
|
|
|
1st review completed | | | 5/13/2017 | | DONE |
Javier Guzman
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/13/2017 | | DONE |
|
|
|
|
Routing - MECHANICAL | 5/9/2017 | | 5/12/2017 | | PASS |
Troy James
|
|
|
|
Intake Approval | | | 5/9/2017 | | PASS |
Javier Guzman
|
|
|
|
Intake Approval | | | 5/8/2017 | | FAIL |
Julie Romig
|
|
|
Need:
1. Form 304 Registered Design Professional Form.
2. Show location of portable fire extinguisher.
3. Mechanical heating and cooling load calculations for new mechanical unit.
|
Application received | | | 5/5/2017 | | DONE |
|
|
|
Application submitted via PDS Online on May 5 2017 2:56PM
|