Permit Information
Permit NumberBLD17-01371
StatusFinaled
Name HC COMPANY INC
Site Address 11311 W CHINDEN BLVD
Project NameSykes Remodel
Customer Number 
ePlanReviewYes
Description
(SYKES - HP CAMPUS B8) (08/10/2017 PLAN MODIFICATION FOR REVISED DOOR SCHEDULE TO REFLECT ACTUAL CONDITIONS FOR NEW AND EXISTING EGRESS DOORS). **Permit is to remodel 32,517 sq ft of the existing 58,656 sq ft third floor tenant space in Building B8 on the HP Campus. This permit is approved contingent upon adhering to the approved plans on file. Work to include: demo of existing non-bearing interior walls; electrical, mechanical and plumbing modifications; new kitchenette and locker room; new doors, interior windows, and new finishes in compliance with Ch. 8 of the 2012 IBC. This building is fully Fire Sprinklered. Any alterations or modifications to the buildings Fire Sprinkler or Fire Alarm system WILL REQUIRE A SEPARATE PERMIT and shall be installed per NFPA 13 & NFPA 72 as regulated by the Boise Fire Department. **JAR*
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Second Notice 11/24/201711/20/2017 DONE
This permit finaled on the web by Jeff Tonkin
First Notice 10/29/201711/14/2017 DONE
Mailed 11-15-17
Print Occupancy Form  10/19/2017 DONE
DetailsChristina Prado
Permanent Occupancy  10/19/2017 DONE
DetailsChristina Prado
BLD-Final10/17/201710/18/201710/18/2017APASS
DetailsJim Sly
Jason Phone #: ###-####
OK for Perm Occ.
FIRE-Final Inspection10/17/201710/17/201710/17/2017PPASS
DetailsTroy Cobbley
Life safety passed

Jason Phone #: ###-####
BLD-Framing/Rough-in8/30/20178/31/20178/31/2017APASS
DetailsJim Sly
Jason Phone #: ###-####
BLD-Final8/10/20178/11/20178/11/2017APART
DetailsJim Sly
temp occ // Jason Phone #: ###-####
OK for Temp. Occ. under the conditions per Julie Romig and Jason Blais.
BLD-Final8/10/20178/10/20178/11/2017ACANC
DetailsJim Sly
FIRE-Final Inspection8/10/20178/11/20178/11/2017APART
DetailsTroy Cobbley
Phase B (North East Quadrant) life safety is passed. Will need the door mag request to exit buttons modified

temp occ // Jason Phone #: ###-####
Routing - FIRE8/4/20178/8/20178/10/2017 PASS
DetailsScott Arellano
Attached revised comments to plans.
Plan assigned to (JAR)8/1/20178/1/20178/10/2017 DONE
DetailsJulie Romig
**08/01 - Plan Mod (SYKES - HP CAMPUS B8)
Routing - PLAN CHECK8/1/2017 8/10/2017 PASS
DetailsJulie Romig
Permit Ready to Issue  8/10/2017 DONE
DO NOT RE ISSUE
CHANGE STATUS TO (ISS)  8/10/2017 DONE
Plan Modification Accepted  8/1/2017 DONE
Plan mod workflow started for door hardware clarification
BLD-Conference7/27/20177/28/20177/27/2017APART
DetailsJim Sly
Jason Phone #: ###-####
See fire inspectors previous notes.
FIRE-Final Inspection7/26/20177/27/20177/27/2017APART
DetailsTroy Cobbley
Phase 1 (northwest quadrant) life safety passed. Plans need to be resubmitted for the door hardware as discussed.
FIRE-Final Inspection7/25/20177/26/20177/26/2017AFAIL
DetailsTroy Cobbley
Todays inspection was for Phase 1 (north west quadrant). The project related fire alarm permit failed. Also I noted that the marked and unmarked egress doors from this area all have door magnets did not release on activation of the fire alarm system and are missing the rex (sensors) and per the review notes there is a 2016 BLD that did not allow the use of mags on the doors. So I'm requesting that the applicant provide a plan modification that gives approval to the requested locking arrangement. Also the egress plan has not been approved by the building code official and I noted that exiting will be going through construction areas from both required exits.

Jason Phone #: ###-####
BLD-Framing/Rough-in6/19/20176/20/20176/20/2017APASS
DetailsJim Sly
Jason Phone #: ###-####
BLD-Framing/Rough-in6/19/20176/19/20176/19/2017PCANC
DetailsDave Hannah
Jason Phone #: ###-####
Plan assigned to (JAR)5/11/20175/11/20176/15/2017 DONE
DetailsJulie Romig
06/09 Resubmitted. 1st Review Complete. L2 - Sykes 3rd Floor Remodel ePlan
Routing - PLAN CHECK6/10/2017 6/15/2017 PASS
DetailsJulie Romig
Resubmit 06/09/17
PLANS/APPL TAKEN TO FRONT DESK  6/15/2017 DONE
Permit Ready to Issue  6/15/2017 DONE
DetailsChristina Prado
All requirements met for issuance
PLANS/APPL TAKEN TO FRONT DESK  6/15/2017 DONE
Permit Ready to Issue  6/15/2017 DONE
DetailsChristina Prado
Issue PAID IN FULL permit  6/15/2017 DONE
DetailsChristina Prado
Print Occupancy Form  6/15/2017 DONE
DetailsChristina Prado
Routing - FIRE6/10/20176/10/20176/13/2017 PASS
DetailsKatie Marron
Revised report attached to case.
Route to Impact Fee Review6/7/20176/10/20176/8/2017 PASS
DetailsMarissa Taylor
Review requested for Commercial Permit
Routing - PLAN CHECK5/11/2017 6/7/2017 FAIL
DetailsJulie Romig
1st review completed  6/7/2017 FAIL
DetailsJulie Romig
Routing - FIRE5/11/20175/11/20175/16/2017 FAIL
DetailsKatie Marron
Report attached to case and emailed to architect.
Routing - MECHANICAL5/11/2017 5/12/2017 PASS
DetailsTroy James
Routing - PLUMBING5/11/2017 5/11/2017 PASS
DetailsBill VanDegrift
per plans and ISPC
Routing - Addressing5/11/2017 5/11/2017 PASS
DetailsLaura Hunter
Routing - PUBLIC WORKS5/11/2017 5/11/2017 PASS
DetailsRachael Beierle
Intake Approval  5/11/2017 PASS
DetailsJavier Guzman
Application received  5/8/2017 DONE
Application submitted via PDS Online on May 8 2017 9:42AM