BLD-Final | 10/8/2017 | 10/9/2017 | 10/9/2017 | A | PASS |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by Nathan Taylor
|
DOC - Permit Finaled | 10/9/2017 | 10/9/2017 | 10/9/2017 | P | PASS |
Jim Storey
|
|
|
|
BLD-Energy code compliance | 8/13/2017 | 8/14/2017 | 8/14/2017 | A | PASS |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by Nathan Taylor
|
BLD-Framing/Rough-in | 8/7/2017 | 8/8/2017 | 8/8/2017 | A | PASS |
Jim Storey
|
|
|
Later AM if possible. Thanks. Phone #: ###-#### Inspection requested via web by Nathan Taylor
|
BLD-Wall Bracing | 7/18/2017 | 7/19/2017 | 7/19/2017 | A | PASS |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by Nathan Taylor
|
BLD-Foundation | 6/20/2017 | 6/21/2017 | 6/21/2017 | A | PART |
Jim Storey
|
|
|
Derik Phone #: ###-#### ft elvation high need aproval from planreview to raise sides and back for frost and drainage. wall ok
|
BLD-Footing | 6/19/2017 | 6/20/2017 | 6/20/2017 | P | PASS |
Dave Hannah
|
|
|
Derek Phone #: ###-####
|
BLD-Footing | 6/19/2017 | 6/20/2017 | 6/20/2017 | A | NR |
Jim Storey
|
|
|
Chris Phone #: ###-#### grade looks to short
|
Issue PAID IN FULL permit | | | 6/14/2017 | | DONE |
|
|
|
|
OVERRIDE | | | 6/13/2017 | | |
|
|
|
|
Route to Impact Fee Review | 6/13/2017 | 6/16/2017 | 6/13/2017 | | PASS |
Marissa Taylor
|
|
|
|
Plan assigned to (JG) | 5/12/2017 | 5/12/2017 | 6/13/2017 | | PASS |
Javier Guzman
|
|
|
1st rev comp, 5/24 L1 SFD paper
|
Inspection Record Card- Bld | | | 6/13/2017 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 6/13/2017 | | 6/13/2017 | | PASS |
Javier Guzman
|
|
|
|
Case Summary (BLD) | | | 6/13/2017 | | DONE |
Javier Guzman
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/13/2017 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 6/13/2017 | | DONE |
|
|
|
Need RP for issuance. Demo was over ten years so there are fees with SWR
|
Telephone call | | | 6/13/2017 | | DONE |
Christina Prado
|
|
|
Called Nate to advise permit is aready pending RP and gave fees due
|
Plan resubmittals received | | | 6/12/2017 | | DONE |
|
|
|
received two copies of plan sheets S1, S2, S3, and lateral calcs; taken to JG
|
1st review completed | | | 5/23/2017 | | FAIL |
Javier Guzman
|
|
|
|
Routing - PLAN CHECK | | | 5/17/2017 | | FAIL |
Javier Guzman
|
|
|
|
Routing - MECHANICAL | 5/12/2017 | | 5/17/2017 | | PASS |
Troy James
|
|
|
|
Plan assigned to (BJM) | 5/11/2017 | 5/11/2017 | 5/16/2017 | | DEFR |
Brian McGowan
|
|
|
|
Route to Impact Fee Review | 5/11/2017 | 5/14/2017 | 5/15/2017 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - PLANNING | 5/11/2017 | | 5/12/2017 | | PASS |
Jeff Lowe
|
|
|
|
Routing - Addressing | 5/11/2017 | | 5/11/2017 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | | | 5/11/2017 | | PASS |
|
|
|
|
Meeting | | | 5/11/2017 | | DONE |
|
|
|
as per Eric in PRK impact dept-no fees will be assessed-as per Sewer dept-talked to Racheal-yes fees will be assessed-also sent emailo to Austin with ACHD-waiting for a reply about the fees for them
|
Plans ACCEPTED BY PLAN TECH | | | 5/11/2017 | | DONE |
|
|
|
|
Intake Approval | | | 5/11/2017 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 5/11/2017 | | DONE |
|
|
|
|
Application received | | 5/11/2017 | | | |
|
|
|
|