(PAGE ONE POWER) **Permit is to remodel two existing office spaces into one 1,660 sq ft office. This permit is approved contingent upon adhering to the approved plans on file. Work to include: demo existing nonbearing interior walls, new light fixtures, new office walls, new interior doors, and new corridor wall constructed to maintain existing 1-hour rating. Interior finishes must be in compliance with Ch. 8 of the 2012 IBC. This building is fully Fire Sprinklered. Any alterations or modifications to the buildings Fire Sprinkler or Fire Alarm system WILL REQUIRE A SEPARATE PERMIT and shall be installed per NFPA 13 & NFPA 72 as regulated by the Boise Fire Department. **JAR*
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Second Notice 6/21/20186/20/2018 DONE
This permit finaled on the web by Braven Allen
First Notice 6/2/20186/11/2018 DONE
mailed 6-12
Print Occupancy Form  5/23/2018 DONE
Permanent Occupancy  5/23/2018 DONE
BLD-Final5/17/20185/18/20185/18/2018ADONE
DetailsTony Young
BLD-Aging Inspection5/11/20185/11/20185/17/2018 PEND
DetailsTony Young
BLD-Final5/15/20185/15/20185/16/2018PDONE
DetailsTony Young
BLD-Aging Inspection5/10/20185/10/20185/15/2018 PEND
DetailsTony Young
BLD-Final12/26/201712/27/201712/27/2017APASS
DetailsMike Jordan
Braven Phone #: ###-####. Ok for perm occ.
FIRE-Final Inspection12/22/201712/26/201712/26/2017APASS
DetailsJim Page
Fire sprinkler inspection complete, no fire alarm modifications, fire extinguishers are in place with current inspection tags. Final life fire safety inspection passed/complete.
FIRE-Final Inspection12/13/201712/14/201712/14/2017AFAIL
DetailsTroy Cobbley
Provide correct suite number, provide permit for sprinkler modifications (one pendant is too close to wall/contractor states Phoenix pulled permit for work), provide missing canopies, provide fire alarm permit for additional devices or demo, mount the fire extinguishers.

Braven Phone #: ###-####
BLD-Final12/13/201712/15/201712/14/2017ACANC
DetailsTony Young
Braven Phone #: ###-#### // cancelled per phone call from Braven 12/14/17 leg
BLD-Ceiling Grid Inspection12/7/201712/8/201712/8/2017PPASS
DetailsDave Hannah
late afternoon- Braven Phone #: ###-####
BLD-Wall cover11/21/201711/22/201711/22/2017PPART
DetailsTony Young
Braven Phone #: ###-####,, walls ok to cover
BLD-Framing/Rough-in11/16/201711/17/201711/17/2017APART
DetailsTony Young
after 10am please -Braven Phone #: ###-####,, main wall framing ok,, steel studs ok .vs wood,, needs more opposing top braces,, ok to start electrical work
Issue PAID IN FULL permit  11/8/2017 DONE
Print Occupancy Form  11/8/2017 DONE
Override - Parcel Holds  11/1/2017  
Extend Review Timeline  11/1/2017 DONE
1st approved 180 day extension per Adele. See documents
Expiration Notice10/11/201711/1/201710/11/2017 DONE
DetailsBrittany Hill
Plan assigned to (JAR)5/17/20175/17/20176/16/2017 DONE
DetailsJulie Romig
1st Review Complete - L2 Page One Power at Lake Harbor. Carl Westfall is familiar with building.
Routing - PLAN CHECK5/17/2017 6/16/2017 FAIL
DetailsJulie Romig
1st review completed  6/16/2017 FAIL
DetailsJulie Romig
Routing - PLAN CHECK6/16/2017 6/16/2017 PASS
DetailsJulie Romig
PLANS/APPL TAKEN TO FRONT DESK  6/16/2017 DONE
Override - Parcel Holds  6/16/2017  
Permit Ready to Issue  6/16/2017 DONE
Need GC Form - Met
and
Revised Cert of Value - Met
Routing - FIRE5/17/20175/17/20175/18/2017 PASS
DetailsKatie Marron
Separate fire permits will be required. Work is to combine two office spaces in an existing office building. Verify life safety items. No comments attached.
Routing - Addressing5/17/2017 5/18/2017 PASS
DetailsLaura Hunter
Ste 175
Routing - PUBLIC WORKS5/17/2017 5/18/2017 PASS
DetailsRachael Beierle
Intake Approval  5/17/2017 PASS
DetailsAdele J Schaffeld-Griffin
Intake Approval  5/16/2017 FAIL
Need:
1. Lighting compliance COMcheck for new interior lighting.
2. Lighting plan and lighting fixture schedule for new interior lighting.
Application received  5/11/2017 DONE
Application submitted via PDS Online on May 11 2017 10:34AM