BLD-Final | 10/17/2017 | 10/18/2017 | 10/18/2017 | P | PASS |
Dave Hannah
|
|
|
Phone #: ###-#### Inspection requested via web by zane everman
|
DOC - Permit Finaled | 10/18/2017 | 10/18/2017 | 10/18/2017 | P | PASS |
Dave Hannah
|
|
|
|
BLD-Final | 10/13/2017 | 10/16/2017 | 10/16/2017 | P | FAIL |
Dave Hannah
|
|
|
i have electrical and hvac re inspections set up for Monday AM. Please stop by even if they aren''t marked off in the computer system yet. Correction notices have been addressed.
Zane Phone #: ###-#### Inspection requested via web by zane everman needs final on fireplace and egress window for upstairs bedroom is 48 inchs above floor
|
BLD-Energy code compliance | 8/9/2017 | 8/9/2017 | 8/9/2017 | P | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by zane everman
|
BLD-Framing/Rough-in | 8/3/2017 | 8/4/2017 | 8/5/2017 | P | PASS |
Dave Hannah
|
|
|
Phone #: ###-#### Inspection requested via web by zane everman
|
BLD-Framing/Rough-in | 8/2/2017 | 8/3/2017 | 8/4/2017 | P | NR |
Dave Hannah
|
|
|
Phone #: ###-#### Inspection requested via web by zane everman
|
Plan Modification Accepted | | | 8/4/2017 | | DONE |
|
|
|
new manual j report
|
Routing - MECHANICAL | 8/4/2017 | | 8/4/2017 | | PASS |
Troy James
|
|
|
resubmitted manaual j report
|
BLD-Framing/Rough-in | 8/2/2017 | 8/3/2017 | 8/2/2017 | A | CANC |
Dave Hannah
|
|
|
Phone #: ###-#### >> Inspection requested via web by zane everman Inspection cancelled from web by: zane everman
|
BLD-Framing/Rough-in | 8/1/2017 | 8/2/2017 | 8/2/2017 | P | CANC |
Dave Hannah
|
|
|
>> Inspection requested via web by zane everman Inspection cancelled from web by: zane everman
|
BLD-Wall Bracing | 7/18/2017 | 7/19/2017 | 7/19/2017 | A | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by zane everman
|
BLD-Foundation | 6/12/2017 | 6/13/2017 | 6/13/2017 | A | PASS |
Dave Hannah
|
|
|
Phone #: 2089495359 >> Inspection requested via mobile web by Ricardo
|
BLD-Conference | 6/9/2017 | 6/12/2017 | 6/12/2017 | P | DONE |
Dave Hannah
|
|
|
Phone #: 2089495359 >> Inspection requested via mobile web by Ricardo
|
BLD-Footing | 6/12/2017 | 6/12/2017 | 6/12/2017 | P | PASS |
Dave Hannah
|
|
|
|
Issue PAID IN FULL permit | | | 6/5/2017 | | |
|
|
|
|
OVERRIDE | | | 5/30/2017 | | |
|
|
|
|
Plan assigned to (JG) | 5/19/2017 | 5/19/2017 | 5/30/2017 | | PASS |
Javier Guzman
|
|
|
5/30 L1 SFD ePlan
|
1st review completed | | | 5/30/2017 | | DONE |
Javier Guzman
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/30/2017 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 5/30/2017 | | DONE |
|
|
|
met
|
Routing - PLAN CHECK | 5/17/2017 | | 5/30/2017 | | PASS |
Javier Guzman
|
|
|
|
Plan assigned to (BJM) | 5/17/2017 | 5/17/2017 | 5/19/2017 | | DEFR |
Brian McGowan
|
|
|
|
Route to Impact Fee Review | 5/17/2017 | 5/20/2017 | 5/18/2017 | | PASS |
Marissa Taylor
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - MECHANICAL | 5/17/2017 | | 5/18/2017 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | 5/17/2017 | | 5/17/2017 | | PASS |
Sue Cummings
|
|
|
|
Routing - Addressing | 5/17/2017 | | 5/17/2017 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | 5/17/2017 | | 5/17/2017 | | PASS |
Morgan Webb
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 5/17/2017 | | DONE |
|
|
|
|
Intake Approval | | | 5/17/2017 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 5/17/2017 | | DONE |
|
|
|
|
Application received | | | 5/12/2017 | | DONE |
|
|
|
Application submitted via PDS Online on May 12 2017 6:56AM
|