Third Notice | | 9/24/2017 | 10/12/2017 | | DONE |
|
|
|
Mailed 10-13-17
|
Second Notice | | 8/20/2017 | 9/19/2017 | | DONE |
|
|
|
Mailed 9-20-17
|
First Notice | | 7/31/2017 | 8/10/2017 | | DONE |
|
|
|
Mailed 8-11-17
|
BLD-Final | 7/20/2017 | 7/21/2017 | 7/21/2017 | P | PASS |
Mike Jordan
|
|
|
please call for access Phone #: ###-#### Inspection requested via web by matthew greenman. Ok for perm oc.
|
FIRE-Final Inspection | 7/20/2017 | 7/21/2017 | 7/21/2017 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed. Per discussion with the contractor the thumbturn dead bolt on the Stockroom door to be removed prior to a building inspection. ADA single action hardware can be installed as per discussion
|
Permanent Occupancy | | | 7/21/2017 | | DONE |
|
|
|
|
FIRE-Final Inspection | 7/19/2017 | 7/20/2017 | 7/20/2017 | A | FAIL |
Troy Cobbley
|
|
|
I stopped at the job site after making two non-answered phone calls to the contact. I spoke to an employee and the ceiling tile installer. There were no approved plans available, ceiling tile was not installed, sprinkler permit not finaled, smoke evac not ready for testing...ect.
Eric Murphy Phone #: ###-####
|
CHANGE STATUS TO (ISS) | | | 7/19/2017 | | DONE |
|
|
|
|
Plan assigned to (JAR) | 7/10/2017 | 7/10/2017 | 7/14/2017 | | DONE |
Julie Romig
|
|
|
00 - PLAN MOD - All ABout Games BTS #1188 (07/14)
|
Routing - PLAN CHECK | 7/12/2017 | | 7/14/2017 | | PASS |
Julie Romig
|
|
|
|
Permit Ready to Issue | | | 7/14/2017 | | DONE |
Christina Prado
|
|
|
Plan Mod approved, all requirements met
Change status to ISS after hourly fees paid in full **DO NOT RE-ISSUE PERMIT**
|
Plan Modification Accepted | | | 7/10/2017 | | DONE |
Christina Prado
|
|
|
Plan Mod to change to a roll up security shutter, and changes to a temp. steel post
|
BLD-Framing/Rough-in | 7/6/2017 | 7/7/2017 | 7/7/2017 | P | PART |
Mike Jordan
|
|
|
call for access please Phone #: ###-#### Inspection requested via web by matthew greenman. Needs to resubmit for roll up door and framing around door and engineering.
|
BLD-Ceiling Grid Inspection | 6/20/2017 | 6/21/2017 | 6/21/2017 | A | PART |
Mike Jordan
|
|
|
Please call for access Thanks, Phone #: ###-#### Inspection requested via web by matthew greenman. pending ele. and fire sprinkler.
|
Issue PAID IN FULL permit | | | 6/6/2017 | | DONE |
|
|
|
|
Print Occupancy Form | | | 6/6/2017 | | DONE |
|
|
|
|
Route to Impact Fee Review | 6/1/2017 | 6/4/2017 | 6/5/2017 | | PASS |
Marissa Taylor
|
|
|
Review requested for Commercial Permit
|
Permit Ready to Issue | | | 6/2/2017 | | DONE |
Christina Prado
|
|
|
Need GC form & Revised certificate of value for issuance
|
Plan assigned to (JAR) | 5/17/2017 | 5/17/2017 | 6/1/2017 | | DONE |
Julie Romig
|
|
|
05/31 - L2. Mall TI - All About Games
|
Routing - PLAN CHECK | 5/17/2017 | | 6/1/2017 | | PASS |
Julie Romig
|
|
|
|
1st review completed | | | 6/1/2017 | | DONE |
Julie Romig
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/1/2017 | | DONE |
|
|
|
|
Routing - FIRE | 5/17/2017 | 5/17/2017 | 5/19/2017 | | PASS |
Katie Marron
|
|
|
Comments attached to case.
|
Routing - PUBLIC WORKS | 5/17/2017 | | 5/18/2017 | | PASS |
Rachael Beierle
|
|
|
|
Routing - Addressing | 5/17/2017 | | 5/17/2017 | | PASS |
Laura Hunter
|
|
|
|
Intake Approval | | | 5/17/2017 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
Application received | | | 5/12/2017 | | DONE |
|
|
|
Application submitted via PDS Online on May 12 2017 8:33AM
|