BLD-Footing | 8/7/2017 | 8/7/2017 | 8/7/2017 | P | PEND |
Tony Young
|
|
|
Inspection can be done later in the AM. Jimmy will be doing the installation and his cell number is ###-####. We will have the MTI subgrade report with us. Thanks. Phone #: ###-#### Inspection requested via web by rich prasch
|
BLD-Footing | 8/4/2017 | 8/7/2017 | 8/7/2017 | A | PEND |
Tony Young
|
|
|
Inspection can be done later in the AM. Jimmy will be doing the installation and his cell number is ###-####. We will have the MTI subgrade report with us. Thanks. Phone #: ###-#### Inspection requested via web by rich prasch
|
BLD-Footing | 8/3/2017 | 8/4/2017 | 8/4/2017 | A | PEND |
Tony Young
|
|
|
Inspection can be done later in the AM. Jimmy will be doing the installation and his cell number is ###-####. We will have the MTI subgrade report with us. Thanks. Phone #: ###-#### Inspection requested via web by rich prasch,, needs soils 1st
|
BLD-Footing | 8/2/2017 | 8/3/2017 | 8/3/2017 | A | PEND |
Tony Young
|
|
|
Inspection can be done later in the AM. Jimmy will be doing the installation and his cell number is ###-####. We will have the MTI subgrade report with us. Thanks. Phone #: ###-#### Inspection requested via web by rich prasch// pending soils approval
|
BLD-Footing | 8/1/2017 | 8/2/2017 | 8/2/2017 | A | CANC |
Tony Young
|
|
|
Footing inspection can be done in the late AM. Tony should probably be the one on the inspection as he has been there before. MTI has approved the subgrade and we have the forms. Jimmy will be doing the installation and his cell number is ###-####. Thanks. Phone #: ###-#### >> Inspection requested via web by rich prasch Inspection cancelled from web by: rich prasch
|
BLD-Footing | 7/28/2017 | 7/28/2017 | 7/28/2017 | P | PEND |
Tony Young
|
|
|
This footing inspection can be done later in the AM tomorrow. MTI has been there and report should be on file. Jimmy will be doing the installation and his cell number is ###-####. Thanks. Phone #: ###-#### Inspection requested via web by rich prasch,, pending soils report
|
BLD-Footing | 7/26/2017 | 7/28/2017 | 7/28/2017 | A | PEND |
Tony Young
|
|
|
This footing inspection can be done later in the AM tomorrow. MTI has been there and report should be on file. Jimmy will be doing the installation and his cell number is ###-####. Thanks. Phone #: ###-#### Inspection requested via web by rich prasch,, need soils approval
|
BLD-Footing | 7/25/2017 | 7/26/2017 | 7/26/2017 | A | PEND |
Tony Young
|
|
|
This footing inspection can be done later in the AM tomorrow. MTI has been there and report should be on file. Jimmy will be doing the installation and his cell number is ###-####. Thanks. Phone #: ###-#### Inspection requested via web by rich prasch/// need soils report approval
|
Routing Walk-In (BLD) | 5/12/2017 | 5/12/2017 | 5/16/2017 | P | DONE |
Josh Bogle
|
|
|
|
Plan assigned to (JAB) Josh | 5/12/2017 | 5/12/2017 | 5/16/2017 | | PASS |
Josh Bogle
|
|
|
routed to JCT & AJL
|
1st review completed | | | 5/16/2017 | | DONE |
Josh Bogle
|
|
|
|
Routing - PLAN CHECK | 5/16/2017 | | 5/16/2017 | | PASS |
Josh Bogle
|
|
|
|
Inspection Record Card- Bld | | | 5/16/2017 | | DONE |
Josh Bogle
|
|
|
|
Case Summary (BLD) | | | 5/16/2017 | | DONE |
Josh Bogle
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/16/2017 | | DONE |
Josh Bogle
|
|
|
|
Permit Ready to Issue | | | 5/16/2017 | | DONE |
|
|
|
|
Telephone call | | | 5/16/2017 | | DONE |
|
|
|
Spoke with Rich informing him that this permit is ready to be picked up
|
Issue PAID IN FULL permit | | | 5/16/2017 | | DONE |
|
|
|
|
Routing - Erosion and Sediment | 5/15/2017 | | 5/16/2017 | | CANC |
Andy J. Long
|
|
|
No ESC permit required. Small excavation within vegetated yard and existing patio area.
|
Routing PW Grading-Hillside | 5/12/2017 | | 5/15/2017 | | PASS |
Jason C. Taylor
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Jason Taylor at ###-####
|
Routing Walk-In (Zoning) | 5/12/2017 | 5/12/2017 | 5/12/2017 | P | PASS |
Colleen T Carroll
|
|
|
|
Application received | | 5/12/2017 | | | |
|
|
|
|
Routing - PLAN CHECK | 5/12/2017 | | | | |
Josh Bogle
|
|
|
|