Print Statement | | | 7/16/2018 | | DONE |
|
|
|
|
First Notice | | 6/30/2018 | 7/11/2018 | | DONE |
|
|
|
mailed 7-12-18
|
BLD-Final | 6/19/2018 | 6/20/2018 | 6/20/2018 | A | PASS |
Jim Sly
|
|
|
Greg Phone #: ###-#### OK for Perm Occ.
|
Permanent Occupancy | | | 6/20/2018 | | DONE |
|
|
|
|
Zoning Approval | 6/19/2018 | 6/19/2018 | 6/19/2018 | | DONE |
Andrea Tuning
|
|
|
|
FIRE-Final Inspection | 5/2/2018 | 5/2/2018 | 5/2/2018 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed
Greg Phone #: ###-####
|
BLD-Final | 3/2/2018 | 3/2/2018 | 3/2/2018 | P | PART |
Jim Sly
|
|
|
Greg Phone #: ###-#### Phase 1 ......OK.
|
FIRE-Final Inspection | 3/2/2018 | 3/2/2018 | 3/2/2018 | P | PART |
Troy Cobbley
|
|
|
Phase 1 area life safety passed.
Greg Phone #: ###-####
|
FIRE-Conference | 2/23/2018 | 2/23/2018 | 2/23/2018 | P | DONE |
Troy Cobbley
|
|
|
We discussed life safety requirements. I noted that the wrong remote annunciator had been installed for the duct smoke detector and that the exit discharge light was missing at the west exit door.
Greg Phone #: ###-####
|
BLD-Other | 2/13/2018 | 2/13/2018 | 2/13/2018 | P | PASS |
Jim Sly
|
|
|
Tbar grid - Greg Phone #: ###-####
|
BLD-Energy code compliance | 1/22/2018 | 1/22/2018 | 1/22/2018 | P | PASS |
Jim Sly
|
|
|
Greg Phone #: ###-####
|
BLD-Framing/Rough-in | 1/17/2018 | 1/18/2018 | 1/18/2018 | A | PASS |
Jim Sly
|
|
|
Greg Phone #: ###-####
|
BLD-Framing/Rough-in | 1/8/2018 | 1/8/2018 | 1/8/2018 | P | PASS |
Jim Sly
|
|
|
Jeff-Ceiling Rough Framing Phone #: ###-#### Inspection requested via web by Jeff Canning
|
BLD-Other | 12/29/2017 | 1/2/2018 | 1/2/2018 | P | DONE |
Jim Sly
|
|
|
Jeff-CMU inspection Phone #: ###-#### CMU Completed. OK pending all inspections, tests and approval by Geotek.
|
BLD-Other | 12/26/2017 | 12/27/2017 | 12/27/2017 | A | PASS |
Jim Sly
|
|
|
cmu inspection // Jeff Phone #: ###-#### CMU final lift OK pending Geotek special inspection, tests and approvals.
|
CHANGE STATUS TO (ISS) | | | 12/21/2017 | | DONE |
|
|
|
|
OVERRIDE | | | 12/20/2017 | | |
|
|
|
|
Permit Ready to Issue | | | 12/20/2017 | | DONE |
|
|
|
DO NOT REISSUE, plan mod fees due
|
Plan assigned to (CJW) | 11/30/2017 | 11/30/2017 | 12/19/2017 | | PASS |
Carl Westfall
|
|
|
x (1st done) Plan Modification "high school activities"
|
Routing Off Site - STRUCTURAL | 12/19/2017 | | 12/19/2017 | | PASS |
Carl Westfall
|
|
|
On hold until stamped structural calculations were received. Ashley Thompson (KPFF))
|
Routing PW Solid Waste | 12/14/2017 | | 12/19/2017 | | PASS |
Evan Carpenter
|
|
|
The solid waste enclosure is approved for shorter walls.
Note the comment on the site plan (AS1-0) stating the solid waste enclosure must have at least 12 feet of unobstructed clearance between gate posts. The enclosure will need to be in compliance with the below design standards before a container can be delivered.
|
Plan Reviewer's activity | | | 12/19/2017 | | PASS |
|
|
|
Plan modification approved
|
Routing - Design Review | 12/14/2017 | | 12/14/2017 | | PASS |
Andrea Tuning
|
|
|
Approved with redlines to provide a 5-foot clear sidewalk outside of the bicycle parking area and label one compact parking space.
|
Routing - PUBLIC WORKS | 12/14/2017 | | 12/14/2017 | | PASS |
Morgan Webb
|
|
|
Trash enclosure walls being shortened
|
Routing - PLAN CHECK | 12/13/2017 | | 12/14/2017 | | PASS |
Carl Westfall
|
|
|
(12-14-17) Need structural calculations to validate the design.
(12-19-17) Structural calculations received and uploaded. Workflow routed to consultant structural engineer. Passed pending the structural review.
|
Plan Modification Accepted | | | 12/13/2017 | | DONE |
|
|
|
Workflow in ePlanReview received
|
Plan Modification Accepted | | | 11/30/2017 | | DONE |
Christina Prado
|
|
|
Plan Mod to reduce trash enclosure height and update misc. cmu walls
|
BLD-Footing | 11/20/2017 | 11/20/2017 | 11/20/2017 | P | PASS |
Jim Sly
|
|
|
Jeff Phone #: ###-#### OK pending Geotek special inspection, tests and approvals.
|
OVERRIDE | | | 10/11/2017 | | |
|
|
|
|
Print Occupancy Form | | | 10/11/2017 | | DONE |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 10/11/2017 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 10/11/2017 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 10/11/2017 | | DONE |
|
|
|
|
Print Occupancy Form | | | 10/11/2017 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 10/11/2017 | | DONE |
|
|
|
WAITING FOR ACHD DO NOT REISSUE. SENT AN EMAIL TO JEFF WITH CANNING CONSTRUCTION
|
OVERRIDE | | | 10/9/2017 | | |
|
|
|
|
Plan assigned to (CJW) | 6/20/2017 | | 10/9/2017 | | PASS |
Carl Westfall
|
|
|
(2nd done) (July 24 - 25 days) (44 sheets) Idaho High School Activities - remodel
|
Routing Off Site - STRUCTURAL | 10/6/2017 | | 10/9/2017 | | PASS |
Carl Westfall
|
|
|
Ashley Thompson (KPFF)
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/9/2017 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 10/9/2017 | | DONE |
|
|
|
MET
Need
RP - MET
GC Form - MET
Revised Cert of Value - MET
ACHD
**DO NOT ISSUE WITHOUT BLD17-01956**
|
Plan resubmittals received | | | 10/6/2017 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 10/6/2017 | | 10/6/2017 | | PASS |
Carl Westfall
|
|
|
Pending approval by structural - routed drawings
|
Plan resubmittals requested | | | 10/4/2017 | | DONE |
|
|
|
|
Routing Off Site - STRUCTURAL | 9/27/2017 | | 10/4/2017 | | FAIL |
Carl Westfall
|
|
|
Ashley Thompson (KPFF)
|
Routing - FIRE | 9/27/2017 | | 10/2/2017 | | PASS |
Katie Marron
|
|
|
Comments attached to case
|
Routing - Design Review | 9/29/2017 | | 9/29/2017 | | PASS |
Andrea Tuning
|
|
|
Approved with redlines to provide a 5-foot clear sidewalk outside of the bicycle parking area and label one compact parking space.
|
Routing - MECHANICAL | 9/27/2017 | | 9/28/2017 | | PASS |
Troy James
|
|
|
|
Routing - PLAN CHECK | 9/26/2017 | | 9/27/2017 | | PASS |
Carl Westfall
|
|
|
Pending approval by structural
|
Routing PW Sewer Rating | 9/27/2017 | | 9/27/2017 | | PASS |
Morgan Webb
|
|
|
Drinking fountains added. WEST BOISE SEWER DISTRICT.
|
Routing PW Drainage | 9/27/2017 | | 9/27/2017 | | PASS |
Brian Murphy
|
|
|
less than 1000ft2
|
Routing - Design Review | 9/27/2017 | | 9/27/2017 | | FAIL |
Andrea Tuning
|
|
|
Sidewalk adjacent to the bicycle parking shall be 5-feet in width and the parking space adjacent to the new termial planter should be labeled as compact.
|
Plan resubmittals received | | | 9/26/2017 | | DONE |
|
|
|
|
Route to Impact Fee Review | 8/10/2017 | 8/13/2017 | 8/11/2017 | | PASS |
Marissa Taylor
|
|
|
Review requested for Commercial Permit
|
1st review completed | | | 8/10/2017 | | DONE |
|
|
|
|
Plan resubmittals requested | | | 8/10/2017 | | DONE |
|
|
|
Emailed plan review report to Architect. Will route workflow in ePlanReview back to the Architect when the garage review is completed
|
Routing - PLAN CHECK | 6/20/2017 | | 8/10/2017 | | FAIL |
Carl Westfall
|
|
|
Revised drawings required
|
Routing PW Drainage | 6/20/2017 | | 6/29/2017 | | PASS |
Brian Murphy
|
|
|
Engineer letter less than 1000
|
Routing Off Site - STRUCTURAL | 6/20/2017 | | 6/27/2017 | | FAIL |
Carl Westfall
|
|
|
Ashley Thompson (KPFF)
|
Routing - PLANNING Land Div | 6/20/2017 | | 6/21/2017 | | PASS |
Todd Tucker
|
|
|
|
Routing - Erosion and Sediment | 6/20/2017 | | 6/21/2017 | | PASS |
Melissa Jannusch
|
|
|
General ESC permit issued.
|
Routing - MECHANICAL | 6/20/2017 | | 6/21/2017 | | FAIL |
Troy James
|
|
|
|
Routing - FIRE | 6/20/2017 | 6/20/2017 | 6/20/2017 | | FAIL |
Katie Marron
|
|
|
Report attached to case and emailed to architect.
|
Intake Approval | | | 6/20/2017 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
Julie approved pre screen and notified applicant this is a 502 application not a 520
|
Plan Reviewer's activity | | | 6/20/2017 | | DONE |
Adele J Schaffeld-Griffin
|
|
|
email sent to applicant Jeff, Please make sure that you reach out to ACHD for review on this change of use/occupancy. If additional fees are due they will need to be paid or paid when the permit is issued. If no fees are do please submit the documentation from ACDH as such.
Thank you
|
Routing - Design Review | 6/20/2017 | | 6/20/2017 | | FAIL |
Andrea Tuning
|
|
|
a. Install four (4) bicycle parking spaces on an approved surfacing that is convenient and visible to individuals using alternative modes of transportation.
b. Install a vertical curb line at the terminus of the pavement to prohibit individuals from driving or parking in the undeveloped area.
c. Provide a total of eight (8) Class I street trees along Ustick Road.
d. Widen the terminal planter at the west end of the parking lot to be a minimum of 8-feet in width (measured inside of curb to inside of curb) and include a Class II tree with shrubs or groundcover.
|
Routing - Addressing | 6/20/2017 | | 6/20/2017 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | 6/20/2017 | | 6/20/2017 | | PASS |
Rachael Beierle
|
|
|
|
Intake Approval | | | 6/14/2017 | | FAIL |
Julie Romig
|
|
|
Neeed 2 applications uploaded:
- (1) application for the Addition and Remodel with revised square footage, occupant load, and valuation specific to the Addition/Remodel.
- (1) application for the new Garage Building with square footage, occupant load, and valuation specific to the Garage.
|
Intake Approval | | | 6/7/2017 | | FAIL |
Julie Romig
|
|
|
Since the project has 2 different buildings, a second building permit will be issued for the garage building. There will only be one ePlanReview case, but you need to upload (2) PDFs of the 502 Building Applications:
- (1) for the Addition and Remodel with revised square footage, occupant load, and valuation specific to the Addition.
- (1) for the new Garage Building with square footage, occupant load, and valuation specific to the Garage.
Also upload the following:
- Provide calcs showing existing roof structure can support additional load of new RTU.
- Mechanical COMcheck uses 90.1 (2013) Standard, Building and Electrical COMchecks use 2012 IECC. All three must use the same energy code path. Submit Mechanical COMcheck for 2012 IECC or submit new Building and Electrical COMcheck using 90.1 (2013) Standard.
- Missing stamp/signature on the following sheets: G1.1, AS1.0, A1.1, A4.2, A5.1, A6.1, A8.1, A8.2, A8.3, A9.1
|
Intake Approval | | | 5/16/2017 | | FAIL |
|
|
|
Applicant submitted drawings/docs for a different project. Deleted and sent application back after discussing with Jeff Likes.
|
Plan Reviewer's activity | | | 5/16/2017 | | |
|
|
|
Route as 502 Addition. Called Jeff Likes and let him know that the project will be routed as a 502 and not a 520.
|
Application received | | | 5/15/2017 | | DONE |
|
|
|
Application submitted via PDS Online on May 15 2017 8:57AM
|