Print Statement | | | 12/19/2017 | | DONE |
|
|
|
|
Second Notice | | 10/22/2017 | 11/14/2017 | | DONE |
|
|
|
Mailed 11-15-17
|
First Notice | | 9/24/2017 | 10/12/2017 | | DONE |
|
|
|
Mailed 10-13-17
|
Permanent Occupancy | | | 9/14/2017 | | DONE |
|
|
|
|
BLD-Final | 9/6/2017 | 9/7/2017 | 9/7/2017 | A | PASS |
Mike Jordan
|
|
|
Scott Phone #: ###-####. Ok for perm. occ. No electrical work done due to change in scope of work. Existing restrooms were able to remain.
|
FIRE-Final Inspection | 9/5/2017 | 9/5/2017 | 9/5/2017 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
Zoning Approval | 9/5/2017 | 9/5/2017 | 9/5/2017 | | DONE |
Andrea Tuning
|
|
|
|
FIRE-Conference | 8/15/2017 | 8/15/2017 | 8/15/2017 | P | DONE |
Troy Cobbley
|
|
|
We discussed the need for panic hardware on the west exit door, removing the exit sign and blocking the northexit door and providing keyed hardware on the main exit and providing additional emergency lighting.
|
BLD-Conference | 8/14/2017 | 8/14/2017 | 8/14/2017 | P | DONE |
Mike Jordan
|
|
|
Scott Phone #: ###-####. Needs to provide drinking fountain, move toilet and sink in existing bathrooms and add correct grab bars. Needs life/safety final.
|
CHANGE STATUS TO (ISS) | | | 8/14/2017 | | DONE |
|
|
|
|
(F) Reprint permit | | | 8/14/2017 | | DONE |
|
|
|
|
Plan assigned to (CJW) | 8/8/2017 | 8/8/2017 | 8/10/2017 | | PASS |
Carl Westfall
|
|
|
(plan mod)
|
Routing - PLAN CHECK | 8/9/2017 | | 8/10/2017 | | PASS |
Carl Westfall
|
|
|
Plan mod approved
|
Plan Reviewer's activity | | | 8/10/2017 | | PASS |
|
|
|
Plan mod approved
|
Permit Ready to Issue | | | 8/10/2017 | | DONE |
Christina Prado
|
|
|
Need:
Revised Value for Plan Moficiation
Pay all fees due
Do Not RE-ISSUE, change status to ISS once all fees paid in full
|
Plan Modification Accepted | | | 8/8/2017 | | DONE |
|
|
|
e plan plan mod accepted-received plan mod to modify restrooms-received sheets AD1.1 & A1.1-assinged to Carl W
|
BLD-Conference | 8/2/2017 | 8/3/2017 | 8/3/2017 | P | DONE |
Mike Jordan
|
|
|
call when on way // Scott Martin Phone #: ###-####. Architect will need to submit plan mod to modify scope of work to lave existing bathrooms and show that existing restrooms will meet ADA.
|
BLD-Framing/Rough-in | 7/27/2017 | 7/27/2017 | 7/27/2017 | P | PASS |
Mike Jordan
|
|
|
Scott Phone #: ###-####. framing for new overhead door ok.
|
Issue PAID IN FULL permit | | | 7/27/2017 | | DONE |
|
|
|
|
Print Occupancy Form | | | 7/27/2017 | | DONE |
|
|
|
|
Route to Impact Fee Review | 7/24/2017 | 7/27/2017 | 7/26/2017 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
Plan assigned to (CJW) | 5/31/2017 | 5/31/2017 | 7/26/2017 | | PASS |
Carl Westfall
|
|
|
***** (2nd done) (June 20 - 15 days) (12 sheets) Idaho Fitness
|
Routing PW Sewer Rating | 7/25/2017 | | 7/26/2017 | | PASS |
Rachael Beierle
|
|
|
Added drinking fountains and service sink
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/26/2017 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 7/26/2017 | | DONE |
|
|
|
need GC & rev cert of val
|
Plan resubmittals received | | | 7/25/2017 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 7/25/2017 | | 7/25/2017 | | PASS |
Carl Westfall
|
|
|
|
Routing - PLAN CHECK | 5/31/2017 | | 7/24/2017 | | FAIL |
Carl Westfall
|
|
|
Revised drawings required
|
1st review completed | | | 7/24/2017 | | DONE |
|
|
|
|
Plan resubmittals requested | | | 7/24/2017 | | DONE |
|
|
|
|
Routing - FIRE | 5/31/2017 | 5/31/2017 | 6/2/2017 | | PASS |
Scott Arellano
|
|
|
Attached comments to plans.
|
Routing - MECHANICAL | 5/31/2017 | | 6/1/2017 | | PASS |
Troy James
|
|
|
Bath fan required per IMC Table 403.3
|
Routing - Addressing | 5/31/2017 | | 5/31/2017 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | 5/31/2017 | | 5/31/2017 | | PASS |
Morgan Webb
|
|
|
|
Routing - Erosion and Sediment | 5/31/2017 | | 5/31/2017 | | PASS |
Melissa Jannusch
|
|
|
No review needed
|
Routing - Design Review | 5/31/2017 | | 5/31/2017 | | PASS |
Andrea Tuning
|
|
|
|
Intake Approval | | | 5/31/2017 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
pre screen approved by Julie
|
Plan Reviewer's activity | | | 5/31/2017 | | DONE |
Adele J Schaffeld-Griffin
|
|
|
Jeff, Please make sure that you reach out to ACHD for review on this change of use/occupancy. If additional fees are due they will need to be paid or paid when the permit is issued. If no fees are do please submit the documentation from ACDH as such.
Thank you
Adele Schaffeld-Griffin
Assistant Building Official / Plan Review Manager
Planning & Development Services Department
City of Boise - 150 N. Capitol Blvd.
P.O. Box 500
Boise, ID 83701
Office ###-####
Email – aschaffeldgriffin@cityofboise.org
“Building Boise Together.”
|
Intake Approval | | | 5/28/2017 | | FAIL |
|
|
|
Need:
1. Site specific fire flow at hydrants letter - checklist indicates letter, but it has not been uploaded.
2. Provide U-factor and SHGC for new exterior door.
|
Intake Approval | | | 5/16/2017 | | FAIL |
|
|
|
Need 520 Checklist, not 518 due to change of use. Need fire flow.
|
Plan Reviewer's activity | | | 5/16/2017 | | |
|
|
|
Route as 520. Contacted Jeff Likes and let him know that it would be a 520 due to the change in use, not a 518.
|
Application received | | | 5/15/2017 | | DONE |
|
|
|
Application submitted via PDS Online on May 15 2017 10:32AM
|