Second Notice | | 10/22/2017 | 10/18/2017 | | DONE |
|
|
|
This permit finaled on the web by Paul Saucerman
|
First Notice | | 10/6/2017 | 10/12/2017 | | DONE |
|
|
|
Mailed 10-13-17
|
Permanent Occupancy | | | 9/26/2017 | | DONE |
|
|
|
|
Temporary Occupancy | 9/19/2017 | 12/18/2017 | 9/19/2017 | | DONE |
Candy A. Nichols
|
|
|
|
BLD-Final | 9/15/2017 | 9/18/2017 | 9/18/2017 | P | PART |
Jim Storey
|
|
|
Requested by Shane Treasure Phone #: ###-#### Inspection requested via web by Shane Treasure final ok pending plm sign off-CAN changed results to Part because all sub permits were not finaled
|
FIRE-Final Inspection | 9/15/2017 | 9/18/2017 | 9/18/2017 | A | PASS |
Jim Page
|
|
|
No fire sprinklers, no fire alarms, fire extinguisher is in place with a current inspection tag. Final life fire safety inspection passed/complete.
|
BLD-Ceiling Grid Inspection | 9/11/2017 | 9/12/2017 | 9/12/2017 | P | PASS |
Jim Storey
|
|
|
Remainder of Ceiling grid inspection Phone #: ###-#### Inspection requested via web by Shane Treasure
|
BLD-Ceiling Grid Inspection | 9/7/2017 | 9/8/2017 | 9/8/2017 | P | PASS |
Jim Sly
|
|
|
Ceiling grid inspection for workout west (111) and workout east (110) Phone #: ###-#### Inspection requested via web by Shane Treasure
|
BLD-Framing/Rough-in | 8/10/2017 | 8/11/2017 | 8/11/2017 | A | PASS |
Jim Storey
|
|
|
Framing inspection requested by Shane Treasure Phone #: ###-#### Inspection requested via web by Shane Treasure pending ele aproval framing ok
|
BLD-Framing/Rough-in | 8/3/2017 | 8/4/2017 | 8/4/2017 | A | PART |
Brandon Shaw
|
|
|
Sound wall, OK to cover
|
Issue PAID IN FULL permit | | | 7/25/2017 | | DONE |
|
|
|
|
Print Occupancy Form | | | 7/25/2017 | | DONE |
|
|
|
|
Plan assigned to (CJW) | 5/17/2017 | 5/17/2017 | 7/21/2017 | | PASS |
Carl Westfall
|
|
|
(1st done) (June 6 - 15 days) (30 sheets) Orange Theory Fitness
|
Routing - PLAN CHECK | 7/20/2017 | | 7/21/2017 | | PASS |
Carl Westfall
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/21/2017 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 7/21/2017 | | DONE |
Christina Prado
|
|
|
Need GC Form & Revised Certificate of Value for issuance
|
Plan resubmittals received | | | 7/20/2017 | | DONE |
|
|
|
|
Route to Impact Fee Review | 7/6/2017 | 7/9/2017 | 7/10/2017 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
1st review completed | | | 7/6/2017 | | DONE |
|
|
|
|
Plan resubmittals requested | | | 7/6/2017 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 5/17/2017 | | 7/6/2017 | | FAIL |
Carl Westfall
|
|
|
Revised drawings required
|
Routing - MECHANICAL | 6/8/2017 | | 6/8/2017 | | PASS |
Troy James
|
|
|
|
Routing - MECHANICAL | 5/17/2017 | | 5/18/2017 | | FAIL |
Troy James
|
|
|
|
Routing - FIRE | 5/17/2017 | 5/17/2017 | 5/17/2017 | | PASS |
Katie Marron
|
|
|
No comments required, basic life safety.
|
Plan Reviewer's activity | | | 5/17/2017 | | DONE |
Adele J Schaffeld-Griffin
|
|
|
Mary, Please make sure that you reach out to ACHD for review on this change of use/occupancy. If additional fees are due they will need to be paid or paid when the permit is issued. If no fees are do please submit the documentation from ACDH as such.
Thank you
|
Intake Approval | | | 5/17/2017 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
pre screen approved by Julie
|
Routing - PLUMBING | 5/17/2017 | | 5/17/2017 | | PASS |
Bill VanDegrift
|
|
|
per plans and ISPC
|
Routing - Addressing | 5/17/2017 | | 5/17/2017 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | 5/17/2017 | | 5/17/2017 | | PASS |
Rachael Beierle
|
|
|
|
Routing - Erosion and Sediment | 5/17/2017 | | 5/17/2017 | | PASS |
Melissa Jannusch
|
|
|
No review needed. Interior only.
|
Application received | | | 5/16/2017 | | DONE |
|
|
|
Application submitted via PDS Online on May 16 2017 10:13AM
|