BLD-Final | 1/23/2019 | 1/24/2019 | 1/24/2019 | A | PASS |
Brandon Shaw
|
|
|
Greg Phone #: ###-####
|
DOC - Permit Finaled | 1/24/2019 | 1/24/2019 | 1/24/2019 | P | PASS |
Brandon Shaw
|
|
|
|
PubWorks Occupancy Approval | 1/22/2019 | 1/22/2019 | 1/22/2019 | | DONE |
Melissa Jannusch
|
|
|
A bond for the sites final grading and re-vegetation has been received by Public Works. Occupancy may be approved by the building department. Melissa Jannusch ###-####.
|
BLD-Foundation | 10/3/2018 | 10/4/2018 | 10/4/2018 | A | PASS |
Tony Young
|
|
|
Steve Phone #: ###-####,, pool wall
|
BLD-Other | 8/24/2018 | 8/27/2018 | 8/27/2018 | A | PART |
Tony Young
|
|
|
rebar // concrete at 9am /// Manuel Phone #: ###-####
|
BLD-Footing | 8/20/2018 | 8/20/2018 | 8/20/2018 | P | PASS |
Dave Hannah
|
|
|
Greg Phone #: ###-####
|
PubWorks Subgrade Approval | 8/20/2018 | 8/20/2018 | 8/20/2018 | | DONE |
Melissa Jannusch
|
|
|
FOR THE FOOTING BY THE POOL HOUSE. A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Melissa Jannusch ###-####.
|
BLD-Conference | 8/6/2018 | 8/7/2018 | 8/7/2018 | P | PEND |
Tony Young
|
|
|
As early as possible Phone #: 2084099812 >> Inspection requested via mobile web by Manuel
|
BLD-Foundation | 7/5/2018 | 7/6/2018 | 7/6/2018 | A | PASS |
Jim Storey
|
|
|
As early as possible Phone #: 2088708888 >> Inspection requested via mobile web by Wes
|
BLD-Footing | 6/27/2018 | 6/27/2018 | 6/27/2018 | P | PASS |
Brandon Shaw
|
|
|
Retaining wall and Gazebo
|
CHANGE STATUS TO (ISS) | | | 6/27/2018 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 6/27/2018 | | DONE |
|
|
|
|
OVERRIDE | | | 6/26/2018 | | |
|
|
|
|
Plan assigned to (BJM) | 5/7/2018 | 5/7/2018 | 6/26/2018 | | DONE |
Brian McGowan
|
|
|
!st review complete-need engineering and more drawings.
|
Telephone call | | | 6/26/2018 | | DONE |
|
|
|
called ###-#### to let know plan mod is ready and how much is owed-left message on cell-plans are in the res walk in drawer
|
Routing - PLAN CHECK | 6/26/2018 | | 6/26/2018 | | PASS |
Brian McGowan
|
|
|
|
Case Summary (BLD) | | | 6/26/2018 | | DONE |
Brian McGowan
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/26/2018 | | DONE |
Brian McGowan
|
|
|
|
Permit Ready to Issue | | | 6/26/2018 | | DONE |
|
|
|
plan mod so please do not re issue
|
Plan resubmittals received | | | 6/15/2018 | | DONE |
|
|
|
Two copies of each L0.00, L1.50 and L1.56 stamped and taken to BJM.
|
Routing - PLAN CHECK | 6/14/2018 | | 6/14/2018 | | FAIL |
Brian McGowan
|
|
|
Need floor plan and structure layout for Trellis.
|
Routing PW Grading-Hillside | 6/4/2018 | | 6/13/2018 | | PASS |
Melissa Jannusch
|
|
|
Plan mod ok.
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Please allow 24 hours for subgrade approval processing. Call Melissa Jannusch at ###-####
Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Melissa Jannusch at ###-####.
|
Routing - PUBLIC WORKS | 6/13/2018 | | 6/13/2018 | | PASS |
Morgan Webb
|
|
|
|
Plan resubmittals received | | | 6/4/2018 | | DONE |
|
|
|
received two copies of structural calcs and plan sheets L0.00, L0.01, L0.02, L0.03, L1.00, L1.10, L1.50, L1.51, L1.52, L1.53, L1.54, L1.55; taken to Brian McGowan
|
Plan Reviewer's activity | | | 6/4/2018 | | |
Brian McGowan
|
|
|
Took plans to Public Works for routing
|
Routing - PLAN CHECK | 5/11/2018 | | 5/15/2018 | | FAIL |
Brian McGowan
|
|
|
Engineering required
|
Routing - PUBLIC WORKS | | | 5/11/2018 | | FAIL |
Morgan Webb
|
|
|
|
Routing PW Grading-Hillside | 5/8/2018 | | 5/11/2018 | | FAIL |
Melissa Jannusch
|
|
|
The proposed retaining wall is over 4’ and will need engineering
|
Routing - PUBLIC WORKS | 5/11/2018 | | 5/11/2018 | | FAIL |
Morgan Webb
|
|
|
SEE HILLSIDE FOR FAIL
|
Routing - Addressing | 5/8/2018 | | 5/8/2018 | | PASS |
Doug Chausow
|
|
|
|
Routing - PLANNING | 5/7/2018 | | 5/8/2018 | | PASS |
Sue Cummings
|
|
|
|
Plan Modification Accepted | | | 5/7/2018 | | DONE |
|
|
|
Plan mod accepted-turned in 2 of each sheet-L0.00L1.50 & L1.51 took to Brian McGowan-retaining wall between pool & equip/ vault
|
BLD-Energy code compliance | 4/2/2018 | 4/3/2018 | 4/3/2018 | A | PASS |
Tony Young
|
|
|
Greg Phone #: ###-####,, work in progress,, ok
|
BLD-Energy code compliance | 3/12/2018 | 3/13/2018 | 3/13/2018 | A | PART |
Brandon Shaw
|
|
|
Air seal-
|
BLD-Framing/Rough-in | 2/8/2018 | 2/9/2018 | 2/9/2018 | A | PASS |
Brandon Shaw
|
|
|
Air seal to be completed with spray foam installation
|
BLD-Other | 12/7/2017 | 12/7/2017 | 12/7/2017 | P | CANC |
Brandon Shaw
|
|
|
Work in progress Fire caulk all seams at firebox/hats in soffit
|
BLD-Wall cover | 11/29/2017 | 11/30/2017 | 11/30/2017 | P | PART |
Tony Young
|
|
|
Soffit work in progress,, needs electrical approval
|
BLD-Wall cover | 11/29/2017 | 11/29/2017 | 11/29/2017 | P | PART |
Brandon Shaw
|
|
|
North garage, clockwise, to south side
Work in Progress
|
BLD-Framing/Rough-in | 11/28/2017 | 11/29/2017 | 11/29/2017 | A | NR |
Tony Young
|
|
|
Greg Phone #: ###-####,, needs soffits,, resceduled for pm
|
Plan Modification Accepted | | | 11/16/2017 | | DONE |
|
|
|
new manual j report
|
Routing - MECHANICAL | 11/16/2017 | | 11/16/2017 | | PASS |
Troy James
|
|
|
resubmitted manual j report
|
BLD-Wall Bracing | 10/25/2017 | 10/26/2017 | 10/26/2017 | A | PASS |
Tony Young
|
|
|
Mike Phone #: ###-####,, exterior ok
|
BLD-Wall Bracing | 10/19/2017 | 10/20/2017 | 10/20/2017 | A | PART |
Tony Young
|
|
|
Greg Phone #: ###-#### would like late AM if possible,, will need fixes on missing hold downs,, see paint marks for missed nails,, then ok,, BMC prebuilt wall panels
|
BLD-Conference | 9/6/2017 | 9/6/2017 | 9/7/2017 | P | PASS |
Tony Young
|
|
|
Call 20 mintues // Greg Phone #: ###-#### WUI ?s
|
BLD-Foundation | 8/8/2017 | 8/9/2017 | 8/9/2017 | A | PASS |
Brandon Shaw
|
|
|
Greg Phone #: ###-####
|
BLD-Footing | 8/2/2017 | 8/3/2017 | 8/3/2017 | P | PART |
Brandon Shaw
|
|
|
Interior footings, home owner had special inspection on interior footing rebar, nrrd report submitted before final.
|
BLD-Footing | 7/26/2017 | 7/27/2017 | 7/27/2017 | A | PASS |
Tony Young
|
|
|
greg Phone #: ###-####,, house footings ok
|
PubWorks Subgrade Approval | 7/27/2017 | 7/27/2017 | 7/27/2017 | | DONE |
Jason C. Taylor
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Jason Taylor ###-####.
|
Telephone call | | | 7/21/2017 | | DONE |
|
|
|
Left a messge for Mike informing that this permit is ready and the fee amount due for issuance
|
Issue PAID IN FULL permit | | | 7/21/2017 | | DONE |
|
|
|
|
OVERRIDE | | | 7/20/2017 | | |
|
|
|
|
Plan assigned to (BJM) | | 5/18/2017 | 7/20/2017 | | DONE |
Brian McGowan
|
|
|
1st review complete - FAIL- 6-06 sfd paper- STRUCTURAL OUTSOURCED
|
Inspection Record Card- Bld | | | 7/20/2017 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 7/19/2017 | | 7/20/2017 | | PASS |
Brian McGowan
|
|
|
|
Case Summary (BLD) | | | 7/20/2017 | | DONE |
Brian McGowan
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/20/2017 | | DONE |
Brian McGowan
|
|
|
|
Permit Ready to Issue | | | 7/20/2017 | | DONE |
|
|
|
met
|
Routing PW Grading-Hillside | 7/10/2017 | | 7/19/2017 | | PASS |
Jason C. Taylor
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Jason Taylor at ###-####
Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Jason Taylor at ###-####.
|
Routing - PUBLIC WORKS | 7/19/2017 | | 7/19/2017 | | PASS |
Rachael Beierle
|
|
|
|
Plan resubmittals received | | | 7/13/2017 | | DONE |
|
|
|
recieved three copies of plan sheet 12, and two copies of plan sheets 2, 7, and 8; taken to Brian McGowan
|
Plan resubmittals received | | | 6/28/2017 | | DONE |
|
|
|
resubmittals received 2 sets of sheet 2, 7, 8, 12 of 14 and 1 email from Wolfe Engineering-took to Brian McGowan
|
Routing - PLAN CHECK | 5/23/2017 | | 6/20/2017 | | FAIL |
Brian McGowan
|
|
|
Structural alterations and verification needed.
|
1st review completed | | | 6/20/2017 | | FAIL |
Brian McGowan
|
|
|
Structural alterations and verification needed.
|
Routing Off Site - STRUCTURAL | 6/6/2017 | | 6/16/2017 | | FAIL |
Brian McGowan
|
|
|
|
Routing - FIRE | 5/23/2017 | 5/18/2017 | 5/23/2017 | | PASS |
Scott Arellano
|
|
|
This home is required to be fire sprinklered in accordance with NFPA 13D. A separate permit will be required. Refer to SUB04-00056 Fire Code Approval Conditions.
|
Routing - Erosion and Sediment | 5/23/2017 | | 5/23/2017 | | PASS |
Andy J. Long
|
|
|
ESC site map and narrative approved. Valid PD, RP to be designated at time of permit issue. Site preparation inspection required.
|
Routing - MECHANICAL | 5/19/2017 | | 5/23/2017 | | PASS |
Troy James
|
|
|
|
Route to Impact Fee Review | 5/18/2017 | 5/21/2017 | 5/19/2017 | | PASS |
Marissa Taylor
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - PLANNING | 5/19/2017 | | 5/19/2017 | | PASS |
Sue Cummings
|
|
|
|
Routing PW Grading-Hillside | 5/18/2017 | | 5/19/2017 | | FAIL |
Jason C. Taylor
|
|
|
Need geotech addendum for site setback determination. See email dated 5/19/2017. JCT
|
Routing - PUBLIC WORKS | 5/19/2017 | | 5/19/2017 | | FAIL |
Morgan Webb
|
|
|
SEE JASON TAYLOR FOR FAIL
|
Routing PW Sewer Rating | 5/18/2017 | | 5/18/2017 | | PASS |
Morgan Webb
|
|
|
|
Routing - Addressing | 5/18/2017 | | 5/18/2017 | | PASS |
Laura Hunter
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 5/18/2017 | | DONE |
|
|
|
|
Intake Approval | | | 5/18/2017 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 5/18/2017 | | DONE |
|
|
|
|
Application received | | 5/17/2017 | | | |
|
|
|
|