Print Statement | | | 8/17/2017 | | DONE |
|
|
|
|
First Notice | | 7/24/2017 | 8/10/2017 | | DONE |
|
|
|
Mailed 8-11-17
|
BLD-Final | 7/13/2017 | 7/14/2017 | 7/14/2017 | A | PASS |
Dave Hannah
|
|
|
Call prior to going Phone #: 2088415809 >> Inspection requested via mobile web by Mike
|
Permanent Occupancy | | | 7/14/2017 | | DONE |
|
|
|
|
BLD-Final | 7/13/2017 | 7/14/2017 | 7/13/2017 | P | CANC |
Dave Hannah
|
|
|
Call prior to going Phone #: 2088415809 >> Inspection requested via mobile web by Mike Inspection cancelled via mobile web on Thursday, July 13, 2017.
|
FIRE-Final Inspection | 7/11/2017 | 7/13/2017 | 7/13/2017 | A | PASS |
Jim Page
|
|
|
Fire sprinkler inspection complete, fire alarm inspection complete, fire extinguishers have current inspection tags and will be mounted in discussed locations. Final life fire safety inspection passed/complete.
|
BLD-Framing/Rough-in | 6/28/2017 | 6/29/2017 | 6/29/2017 | A | PASS |
Dave Hannah
|
|
|
Call prior to going Phone #: 2088415809 >> Inspection requested via mobile web by Mike
|
BLD-Framing/Rough-in | 6/26/2017 | 6/27/2017 | 6/26/2017 | A | CANC |
Dave Hannah
|
|
|
Call prior to going Phone #: 2088415809 >> Inspection requested via mobile web by Mike Inspection cancelled via mobile web on Monday, June 26, 2017.
|
Permit Ready to Issue | | | 6/23/2017 | | DONE |
|
|
|
Need GC Form and Revised Cert of Value
|
Telephone call | | | 6/23/2017 | | DONE |
|
|
|
Spoke with sam informing him this permit is ready and that we just need the GC to fill out a 302 and a 306 form and once we have those we can add in the final fees for issuance
|
Print Occupancy Form | | | 6/23/2017 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 6/23/2017 | | DONE |
|
|
|
|
Route to Impact Fee Review | 6/20/2017 | 6/23/2017 | 6/22/2017 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
Plan assigned to (JAR) | 5/18/2017 | 5/18/2017 | 6/21/2017 | | DONE |
Julie Romig
|
|
|
06/02 (06/16) - PAPER - L2 Banner Bank TI
|
Case Summary (BLD) | | | 6/21/2017 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/21/2017 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 5/23/2017 | | 6/20/2017 | | PASS |
Julie Romig
|
|
|
|
Routing - FIRE | 6/20/2017 | | 6/20/2017 | | PASS |
Katie Marron
|
|
|
Separate Fire Permits will be required. No comments required.
|
1st review completed | | | 6/20/2017 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS | | | 5/23/2017 | | PASS |
|
|
|
|
Routing - Addressing | 5/19/2017 | | 5/22/2017 | | PASS |
Laura Hunter
|
|
|
|
Intake Approval | | | 5/19/2017 | | PASS |
Julie Romig
|
|
|
per JAR
|
Application received | | 5/18/2017 | | | |
|
|
|
|