First Notice | | 8/21/2017 | 9/26/2017 | | DONE |
|
|
|
Faxed in 9-26-17
|
BLD-Final | 8/10/2017 | 8/11/2017 | 8/11/2017 | P | PASS |
Jim Storey
|
|
|
tyler Phone #: ###-####
|
FIRE-Final Inspection | 8/10/2017 | 8/11/2017 | 8/11/2017 | P | PASS |
Jim Page
|
|
|
Fire sprinkler inspection complete, no fire alarm modifications, fire extinguishers are in place with current inspection tags. Final lfie fire safety inspection for area of work passed/complete.
|
Permanent Occupancy | | | 8/11/2017 | | DONE |
|
|
|
|
BLD-Ceiling Grid Inspection | 8/9/2017 | 8/10/2017 | 8/10/2017 | P | PASS |
Jim Storey
|
|
|
Tyler Phone #: ###-####
|
FIRE-Final Inspection | 8/8/2017 | 8/9/2017 | 8/9/2017 | P | CANC |
Jim Page
|
|
|
Inspection request cancelled, space not ready for final life fire safety inspection, office spaces are missing the ceiling tile, ceiling tile provides heat collection for fire sprinkler head operation. Inspection request will be made when ceiling tile is installed and complete.
|
BLD-Energy code compliance | 7/20/2017 | 7/20/2017 | 7/20/2017 | P | PASS |
Jim Storey
|
|
|
Brent Phone #: ###-####
|
BLD-Framing/Rough-in | 7/17/2017 | 7/17/2017 | 7/17/2017 | P | PASS |
Jim Storey
|
|
|
Brent Phone #: ###-####
|
Plan assigned to (CJW) | 5/25/2017 | 5/25/2017 | 7/14/2017 | | PASS |
Carl Westfall
|
|
|
(6g) (June 14 - 15 days) (23 sheets) Burgin Relocation, Inc.
|
Routing - PLAN CHECK | 5/25/2017 | | 7/14/2017 | | PASS |
Carl Westfall
|
|
|
|
1st review completed | | | 7/14/2017 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/14/2017 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 7/14/2017 | | DONE |
|
|
|
need GC and rev cert of val
|
Issue PAID IN FULL permit | | | 7/14/2017 | | DONE |
|
|
|
|
Print Occupancy Form | | | 7/14/2017 | | DONE |
|
|
|
|
Routing - MECHANICAL | 5/25/2017 | | 6/1/2017 | | PASS |
Chad Schwendiman
|
|
|
|
Routing - FIRE | 5/25/2017 | 5/25/2017 | 5/30/2017 | | PASS |
Scott Arellano
|
|
|
Attached review comments to plans.
|
Intake Approval | | | 5/25/2017 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
Julie completed pre screen.
|
Routing - PLUMBING | 5/25/2017 | | 5/25/2017 | | PASS |
Daryl Spivey
|
|
|
Per plan and ISPC.
|
Routing - Addressing | 5/25/2017 | | 5/25/2017 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | 5/25/2017 | | 5/25/2017 | | PASS |
Morgan Webb
|
|
|
|
Application received | | | 5/18/2017 | | DONE |
|
|
|
Application submitted via PDS Online on May 18 2017 2:40PM
|