Permit Information
Permit NumberBLD17-01548
StatusIssued
Name ZELHAM INC
Site Address 5257 W FAIRVIEW AVE
Project NameZelham Offices - Remodel
Customer Number 
ePlanReviewYes
Description
(ZELHAM OFFICES – 1ST STORY) The fire sprinkler system is used in lieu of rated corridors. A fire sprinkler system will be installed throughout the 1st story in conjunction with this permit. A fire sprinkler system will be installed throughout the 2nd story under a future phase. To remodel the entire 13,988 square foot 1st story of an existing two story building which includes five areas (1) 5,481 square foot office tenant space with 55 OL in the East end of the building, (2) 2,604 square foot office tenant space with 26 OL in the Northwest corner of the building, (3) 1,653 square foot shell tenant space with 17 OL in the Southwest corner of the building, (4) 668 square foot fitness room / break room / server with 25 OL, and (5) 538 square foot shared conference room with 36 OL. To expand the existing Men’s common restroom on the 1st story by 102 square feet to 266 square feet (add 3 toilets) and to expand the existing Women’s common restroom on the 1st story by 102 square feet to 264 square feet (add 3 toilets). A new doorway will be created in an existing masonry wall between the existing restrooms and the restroom expansion areas. Steel headers and steel jambs will be installed. Work is to include interior nonbearing walls, a new toilet / shower room accessible to the disabled, interior doors, interior windows, millwork, and finishes. The work is required to comply with the approved drawings, with the structural details, with the plan review report, and with all applicable codes and ordinances. The fire sprinkler system is required to comply with NFPA 13 and the fire alarm system is required to comply with NFPA 72 as regulated by the Fire Department. A fire sprinkler permit and a fire alarm permit shall be obtained prior to beginning any modification or installation work on such systems. **CJW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
FIRE-Final Inspection5/15/20185/15/20185/15/2018PPASS
DetailsJim Page
Final life fire safety inspection complete.

2nd Floor reception door mag lock replaced with electric strike Phone #: ###-#### Inspection requested via web by Steve Jones
BLD-Final3/19/20183/19/20183/20/2018PPART
DetailsJim Sly
Phone #: ###-#### Inspection requested via web by Steve Jones
OK for Temp. Occ. See previous Fire inspectors notes.
FIRE-Final Inspection3/16/20183/19/20183/19/2018APART
DetailsTroy Cobbley
A temporary for life safety is being given with Assistant Chief Ron's permission until the two pre-action systems/rooms have been addressed. Per the contractor the smoke detectors are active in these rooms. They will need to remain active until the associated pre-action system is functional.
FIRE-Conference2/1/20182/1/20182/1/2018PDONE
DetailsTroy Cobbley
We discussed life safety items such as possible exit discharge lighting and interconnection of the access control egress locks with the new fire alarm system
BLD-Wall cover12/20/201712/20/201712/20/2017PPASS
DetailsJim Sly
Inspection requested via web by Steve Jones
BLD-Framing/Rough-in11/22/201711/22/201711/22/2017PPASS
DetailsMike Jordan
Northeast quadrant offices. Phone #: ###-#### Inspection requested via web by Steve Jones. North west wing interior steel stud framed walls ok. Hard lid in main lobby ok, pending lectrical and fire .
BLD-Framing/Rough-in11/16/201711/16/201711/16/2017PPASS
DetailsJim Sly
1st Floor East of Lobby Phone #: ###-#### Inspection requested via web by Steve Jones
Plan assigned to (CJW)5/22/20175/22/201710/27/2017 PASS
DetailsCarl Westfall
(2nd done) (June 9 - 15 days) (12 sheets) ZELHAM OFFICES
PLANS/APPL TAKEN TO FRONT DESK  10/27/2017 DONE
Permit Ready to Issue  10/27/2017 DONE
Need
GC Form
Revised Cert of Value
Print Occupancy Form  10/27/2017 DONE
Issue PAID IN FULL permit  10/27/2017 DONE
Routing - FIRE10/25/2017 10/26/2017 PASS
DetailsScott Arellano
Attached revised comments to case
Routing PW Sewer Rating10/25/2017 10/26/2017 PASS
DetailsRachael Beierle
Routing - MECHANICAL10/25/2017 10/26/2017 PASS
DetailsTroy James
transfer redlines
Plan resubmittals received  10/25/2017 DONE
Routing - PLAN CHECK10/25/2017 10/25/2017 PASS
DetailsCarl Westfall
Route to Impact Fee Review7/22/20177/25/20177/26/2017 PASS
DetailsEric Bilimoria
Review requested for Commercial Permit
Routing - PLAN CHECK5/22/2017 7/22/2017 FAIL
DetailsCarl Westfall
(7-13-17) Suspended the plan review while it is decided whether to fire sprinkler the building or not.

(7-22-17) Finished plan review though whether to fire sprinkler had not been decided.
1st review completed  7/22/2017 DONE
Plan resubmittals requested  7/22/2017 DONE
Routing - FIRE5/22/20175/22/20175/24/2017 FAIL
DetailsScott Arellano
Emailed plan review report to architect. Attached report to case.
Routing - MECHANICAL5/22/2017 5/23/2017 PASS
DetailsTroy James
Routing - Addressing5/22/2017 5/22/2017 PASS
DetailsLaura Hunter
Routing - PUBLIC WORKS5/22/2017 5/22/2017 PASS
DetailsMorgan Webb
Intake Approval  5/22/2017 PASS
DetailsAdele J Schaffeld-Griffin
Application received  5/18/2017 DONE
Application submitted via PDS Online on May 18 2017 3:34PM