Second Notice | | 3/24/2018 | 4/3/2018 | | DONE |
|
|
|
This permit finaled on the web by Kim Anderson
|
First Notice | 2/15/2018 | 2/15/2018 | 3/14/2018 | | DONE |
Jim Sly
|
|
|
Mailed 3-15-18
|
BLD-Final | 2/14/2018 | 2/15/2018 | 2/15/2018 | A | PASS |
Jim Sly
|
|
|
Phone #: ###-#### Inspection requested via web by Kaleb Checketts
|
DOC - Permit Finaled | 2/15/2018 | 2/15/2018 | 2/15/2018 | P | PASS |
Jim Sly
|
|
|
|
BLD-Final | 2/12/2018 | 2/13/2018 | 2/13/2018 | A | NR |
Jim Sly
|
|
|
Phone #: ###-#### Inspection requested via web by Kaleb Checketts Need Electrical final prior to calling for Structural final.
|
BLD-Concrete | 11/30/2017 | 12/7/2017 | 12/7/2017 | A | PASS |
Jim Sly
|
|
|
Cell Tower...12:00 pour Ryan 208 800 1431 OK pending STRATA special inspection, tests and approvals. 5,000 PSI @ 28 days.
|
BLD-Footing | 11/30/2017 | 11/30/2017 | 11/30/2017 | P | NR |
Jim Sly
|
|
|
Ryan Phone #: ###-#### Re-sched......
|
CHANGE STATUS TO (ISS) | | | 11/30/2017 | | DONE |
|
|
|
|
(F) Reprint permit | | | 11/30/2017 | | DONE |
|
|
|
|
OVERRIDE | | | 11/2/2017 | | |
|
|
|
|
Plan assigned to (JAR) | 10/24/2017 | 10/24/2017 | 11/2/2017 | | DONE |
Julie Romig
|
|
|
**10/24 - Plan Mod Verizon Monopole
|
Routing Off Site - STRUCTURAL | 10/26/2017 | | 11/2/2017 | | PASS |
Julie Romig
|
|
|
Passed per ePlanReview.
|
Permit Ready to Issue | | | 11/2/2017 | | DONE |
|
|
|
PLEASE DO NOT RE ISSUE
|
Routing - PLAN CHECK | 10/26/2017 | | 11/1/2017 | | PASS |
Julie Romig
|
|
|
|
Route to Impact Fee Review | 10/24/2017 | 10/27/2017 | 10/24/2017 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
Plan Modification Accepted | | | 10/24/2017 | | DONE |
Christina Prado
|
|
|
Plan mod to change from pre-cast construction to cast in place, new calcs and drawings uploaded
|
Issue PAID IN FULL permit | | | 10/4/2017 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 10/4/2017 | | DONE |
|
|
|
|
OVERRIDE | | | 9/29/2017 | | |
|
|
|
|
Plan assigned to (JAR) | 5/25/2017 | 5/25/2017 | 9/29/2017 | | DONE |
Julie Romig
|
|
|
**1st Rev Comp - 5th Rec'd 9/27 - 502 Verizon Wireless Monopole
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/29/2017 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 9/29/2017 | | DONE |
Christina Prado
|
|
|
Need
GC Form
Revised Cert of Value
All met
|
Routing - PLAN CHECK | 9/27/2017 | | 9/29/2017 | | PASS |
Julie Romig
|
|
|
Review #5
|
Routing Off Site - STRUCTURAL | 9/27/2017 | | 9/29/2017 | | PASS |
Julie Romig
|
|
|
Review #5
|
Routing - PLAN CHECK | 9/19/2017 | | 9/26/2017 | | FAIL |
Julie Romig
|
|
|
Review #4 - corrections required per Structural.
|
Routing Off Site - STRUCTURAL | 9/19/2017 | | 9/26/2017 | | FAIL |
Julie Romig
|
|
|
Review #4 - Corrections required per ePlanReview.
|
Routing - PLAN CHECK | 8/25/2017 | | 8/31/2017 | | FAIL |
Julie Romig
|
|
|
Review #3 - Corrections required per Structural.
|
Routing Off Site - STRUCTURAL | 8/25/2017 | | 8/31/2017 | | FAIL |
Julie Romig
|
|
|
Review #3 - Corrections required per ePlanReview
|
Routing - PLAN CHECK | 7/13/2017 | | 8/1/2017 | | FAIL |
Julie Romig
|
|
|
Review #2 - Corrections required per Structural.
|
Routing Off Site - STRUCTURAL | 7/13/2017 | | 8/1/2017 | | FAIL |
Julie Romig
|
|
|
Review #2 - Corrections required per ePlanReview.
|
Routing Off Site - STRUCTURAL | 5/25/2017 | | 7/7/2017 | | FAIL |
Julie Romig
|
|
|
Corrections Required per ePlanReview.
|
Routing - PLAN CHECK | 5/25/2017 | | 7/7/2017 | | FAIL |
Julie Romig
|
|
|
Corrections required per structural review.
|
1st review completed | | | 7/7/2017 | | FAIL |
Julie Romig
|
|
|
|
Routing - Design Review | 5/25/2017 | | 6/2/2017 | | PASS |
Sarah Schafer
|
|
|
|
Routing - FIRE | 5/25/2017 | 5/25/2017 | 5/26/2017 | | PASS |
Scott Arellano
|
|
|
No comments. No inspection required.
|
Routing - Erosion and Sediment | 5/25/2017 | | 5/26/2017 | | PASS |
Andy J. Long
|
|
|
|
Routing PW Drainage | 5/25/2017 | | 5/25/2017 | | PASS |
Brian Murphy
|
|
|
|
Routing - PLANNING | 5/25/2017 | | 5/25/2017 | | PASS |
Celine Acord
|
|
|
per approval of CUP16-00085
|
Routing - PLANNING Land Div | 5/25/2017 | | 5/25/2017 | | PASS |
Todd Tucker
|
|
|
|
Routing - PUBLIC WORKS | 5/25/2017 | | 5/25/2017 | | PASS |
Rachael Beierle
|
|
|
|
Routing - Addressing | 5/25/2017 | | 5/25/2017 | | PASS |
Laura Hunter
|
|
|
|
Intake Approval | | | 5/24/2017 | | FAIL |
|
|
|
Please see the circled items in the plan intake checklist and resolve each item as noted. CJW
|
Plan Reviewer's activity | | | 5/24/2017 | | DONE |
Carl Westfall
|
|
|
Plan intake review approved
|
Application received | | | 5/23/2017 | | DONE |
|
|
|
Application submitted via PDS Online on May 23 2017 4:18PM
|