Information based on query as of Wednesday, July 17, 2024.
Permit Information
Permit NumberBLD17-01603
StatusFinaled
Name MARSH CREEK LLC
Site Address 9170 W CORY LN
Project NameVerizon Monopole
Customer Number 
ePlanReviewYes
Description
(VERIZON MONOPOLE) **(PLAN MOD FOR CAST-IN-PLACE FOUNDATION. 11/01/17) Permit for a new 35 ft tall monopole cell tower and new ground equipment in 100 sq ft lease area. Work to include: new 30 ft tall monopole with 3 ft tall omni antenna installed on top of pole; new ground level equipment cabinet; new meter panel; new H-frame with (2) RRH units, twin diplexer, GPS antenna, and fiber box mounted to H-frame; and new light fixture. Special inspections required per attached Form 310. Structural engineering and plans provided. **JAR**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Second Notice 3/24/20184/3/2018 DONE
This permit finaled on the web by Kim Anderson
First Notice2/15/20182/15/20183/14/2018 DONE
DetailsJim Sly
Mailed 3-15-18
BLD-Final2/14/20182/15/20182/15/2018APASS
DetailsJim Sly
Phone #: ###-#### Inspection requested via web by Kaleb Checketts
DOC - Permit Finaled2/15/20182/15/20182/15/2018PPASS
DetailsJim Sly
BLD-Final2/12/20182/13/20182/13/2018ANR
DetailsJim Sly
Phone #: ###-#### Inspection requested via web by Kaleb Checketts
Need Electrical final prior to calling for Structural final.
BLD-Concrete11/30/201712/7/201712/7/2017APASS
DetailsJim Sly
Cell Tower...12:00 pour Ryan 208 800 1431
OK pending STRATA special inspection, tests and approvals. 5,000 PSI @ 28 days.
BLD-Footing11/30/201711/30/201711/30/2017PNR
DetailsJim Sly
Ryan Phone #: ###-####
Re-sched......
CHANGE STATUS TO (ISS)  11/30/2017 DONE
(F) Reprint permit  11/30/2017 DONE
OVERRIDE  11/2/2017  
Plan assigned to (JAR)10/24/201710/24/201711/2/2017 DONE
DetailsJulie Romig
**10/24 - Plan Mod Verizon Monopole
Routing Off Site - STRUCTURAL10/26/2017 11/2/2017 PASS
DetailsJulie Romig
Passed per ePlanReview.
Permit Ready to Issue  11/2/2017 DONE
PLEASE DO NOT RE ISSUE
Routing - PLAN CHECK10/26/2017 11/1/2017 PASS
DetailsJulie Romig
Route to Impact Fee Review10/24/201710/27/201710/24/2017 PASS
DetailsEric Bilimoria
Review requested for Commercial Permit
Plan Modification Accepted  10/24/2017 DONE
DetailsChristina Prado
Plan mod to change from pre-cast construction to cast in place, new calcs and drawings uploaded
Issue PAID IN FULL permit  10/4/2017 DONE
Inspection Record Card- Bld  10/4/2017 DONE
OVERRIDE  9/29/2017  
Plan assigned to (JAR)5/25/20175/25/20179/29/2017 DONE
DetailsJulie Romig
**1st Rev Comp - 5th Rec'd 9/27 - 502 Verizon Wireless Monopole
PLANS/APPL TAKEN TO FRONT DESK  9/29/2017 DONE
Permit Ready to Issue  9/29/2017 DONE
DetailsChristina Prado
Need
GC Form
Revised Cert of Value

All met
Routing - PLAN CHECK9/27/2017 9/29/2017 PASS
DetailsJulie Romig
Review #5
Routing Off Site - STRUCTURAL9/27/2017 9/29/2017 PASS
DetailsJulie Romig
Review #5
Routing - PLAN CHECK9/19/2017 9/26/2017 FAIL
DetailsJulie Romig
Review #4 - corrections required per Structural.
Routing Off Site - STRUCTURAL9/19/2017 9/26/2017 FAIL
DetailsJulie Romig
Review #4 - Corrections required per ePlanReview.
Routing - PLAN CHECK8/25/2017 8/31/2017 FAIL
DetailsJulie Romig
Review #3 - Corrections required per Structural.
Routing Off Site - STRUCTURAL8/25/2017 8/31/2017 FAIL
DetailsJulie Romig
Review #3 - Corrections required per ePlanReview
Routing - PLAN CHECK7/13/2017 8/1/2017 FAIL
DetailsJulie Romig
Review #2 - Corrections required per Structural.
Routing Off Site - STRUCTURAL7/13/2017 8/1/2017 FAIL
DetailsJulie Romig
Review #2 - Corrections required per ePlanReview.
Routing Off Site - STRUCTURAL5/25/2017 7/7/2017 FAIL
DetailsJulie Romig
Corrections Required per ePlanReview.
Routing - PLAN CHECK5/25/2017 7/7/2017 FAIL
DetailsJulie Romig
Corrections required per structural review.
1st review completed  7/7/2017 FAIL
DetailsJulie Romig
Routing - Design Review5/25/2017 6/2/2017 PASS
DetailsSarah Schafer
Routing - FIRE5/25/20175/25/20175/26/2017 PASS
DetailsScott Arellano
No comments. No inspection required.
Routing - Erosion and Sediment5/25/2017 5/26/2017 PASS
DetailsAndy J. Long
Routing PW Drainage5/25/2017 5/25/2017 PASS
DetailsBrian Murphy
Routing - PLANNING5/25/2017 5/25/2017 PASS
DetailsCeline Acord
per approval of CUP16-00085
Routing - PLANNING Land Div5/25/2017 5/25/2017 PASS
DetailsTodd Tucker
Routing - PUBLIC WORKS5/25/2017 5/25/2017 PASS
DetailsRachael Beierle
Routing - Addressing5/25/2017 5/25/2017 PASS
DetailsLaura Hunter
Intake Approval  5/24/2017 FAIL
Please see the circled items in the plan intake checklist and resolve each item as noted. CJW
Plan Reviewer's activity  5/24/2017 DONE
DetailsCarl Westfall
Plan intake review approved
Application received  5/23/2017 DONE
Application submitted via PDS Online on May 23 2017 4:18PM