BLD-Final | 8/8/2018 | 8/10/2018 | 8/10/2018 | A | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Clint Wall
|
DOC - Permit Finaled | 8/10/2018 | 8/10/2018 | 8/10/2018 | P | PASS |
Brandon Shaw
|
|
|
|
BLD-Blower Door Test Results | 8/8/2018 | 8/10/2018 | 8/10/2018 | A | DONE |
Brandon Shaw
|
|
|
ACH50- 4.6
|
PubWorks Occupancy Approval | 8/10/2018 | 8/10/2018 | 8/10/2018 | | DONE |
Melissa Jannusch
|
|
|
A letter from the applicant’s civil engineer indicating that the final grading and drainage is acceptable has been received by Public Works. Final occupancy may be approved by the building department. Melissa Jannusch ###-####.
|
BLD-Energy code compliance | 5/29/2018 | 5/31/2018 | 5/31/2018 | A | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Clint Wall
|
BLD-Framing/Rough-in | 5/29/2018 | 5/29/2018 | 5/29/2018 | P | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Clint Wall
|
BLD-Framing/Rough-in | 5/25/2018 | 5/29/2018 | 5/29/2018 | A | CANC |
Brandon Shaw
|
|
|
Phone #: ###-#### >> Inspection requested via web by Clint Wall Inspection cancelled from web by: Clint Wall
|
BLD-Wall Bracing | 5/8/2018 | 5/8/2018 | 5/8/2018 | P | PASS |
Brandon Shaw
|
|
|
Work in progress
|
BLD-Aging Inspection | 12/26/2017 | 12/26/2017 | 12/26/2017 | | DONE |
Brandon Shaw
|
|
|
Work in progress
|
BLD-Footing | 8/11/2017 | 8/11/2017 | 8/14/2017 | P | PASS |
Brandon Shaw
|
|
|
Pat Phone #: ###-####
|
PubWorks Subgrade Approval | 8/10/2017 | 8/10/2017 | 8/10/2017 | | DONE |
Melissa Jannusch
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Melissa Jannusch ###-####.
|
OVERRIDE | | | 6/20/2017 | | |
|
|
|
|
Plan assigned to (JG) | 6/1/2017 | 6/1/2017 | 6/20/2017 | | PASS |
Javier Guzman
|
|
|
1st rev comp, 6/16 L2 SFD ePlan pend flood
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/20/2017 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 6/20/2017 | | DONE |
|
|
|
all met
|
Issue PAID IN FULL permit | | | 6/20/2017 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 6/20/2017 | | DONE |
|
|
|
|
Routing PW Flood Plain | 6/15/2017 | | 6/19/2017 | | PASS |
Jason C. Taylor
|
|
|
Approved LOMR on File. No floodplain review required. JCT
|
Routing - PLAN CHECK | 6/15/2017 | | 6/17/2017 | | PASS |
Javier Guzman
|
|
|
|
1st review completed | | | 6/14/2017 | | FAIL |
Javier Guzman
|
|
|
|
Routing - PLAN CHECK | 6/1/2017 | | 6/14/2017 | | PASS |
Javier Guzman
|
|
|
|
Routing PW Grading-Hillside | 6/1/2017 | | 6/9/2017 | | PASS |
Jason C. Taylor
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Jason Taylor at ###-####
Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Jason Taylor at ###-####.
|
Routing PW Flood Plain | 6/1/2017 | | 6/7/2017 | | FAIL |
Jason C. Taylor
|
|
|
See Changemarks in ePlan. JCT
|
Route to Impact Fee Review | 6/1/2017 | 6/4/2017 | 6/5/2017 | | PASS |
Marissa Taylor
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - FIRE | 6/1/2017 | 6/1/2017 | 6/5/2017 | | PASS |
Katie Marron
|
|
|
Plans were reviewed for FD Access, hydrant availability and defensible space.
|
Plan assigned to (BJM) | 6/1/2017 | 6/1/2017 | 6/1/2017 | | DEFR |
Brian McGowan
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 6/1/2017 | | DONE |
Christina Prado
|
|
|
|
Intake Approval | | | 6/1/2017 | | PASS |
Christina Prado
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 6/1/2017 | | DONE |
Christina Prado
|
|
|
|
Routing - MECHANICAL | 6/1/2017 | | 6/1/2017 | | PASS |
Chad Schwendiman
|
|
|
|
Routing - PLANNING | 6/1/2017 | | 6/1/2017 | | PASS |
Sue Cummings
|
|
|
|
Routing - Addressing | 6/1/2017 | | 6/1/2017 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | 6/1/2017 | | 6/1/2017 | | PASS |
Rachael Beierle
|
|
|
|
Routing - Erosion and Sediment | 6/1/2017 | | 6/1/2017 | | PASS |
Melissa Jannusch
|
|
|
Special waiver approved.
|
Application received | | | 5/24/2017 | | DONE |
|
|
|
Application submitted via PDS Online on May 24 2017 9:46AM
|