BLD-Final | 5/1/2019 | 5/2/2019 | 5/2/2019 | P | PASS |
Jim Sly
|
|
|
Mike Phone #: ###-####
|
DOC - Permit Finaled | 5/2/2019 | 5/2/2019 | 5/2/2019 | P | PASS |
Jim Sly
|
|
|
|
BLD-Conference | 8/16/2018 | 8/16/2018 | 8/17/2018 | P | DONE |
Jim Sly
|
|
|
Mike Phone #: ###-####
|
BLD-Conference | 7/9/2018 | 7/10/2018 | 7/10/2018 | A | DONE |
Jim Sly
|
|
|
Mike Phone #: ###-####
|
BLD-Framing/Rough-in | 1/8/2018 | 1/8/2018 | 1/8/2018 | P | PASS |
Jim Sly
|
|
|
Mike Phone #: ###-####
|
Routing - MECHANICAL | 11/28/2017 | | 11/28/2017 | | PASS |
Troy James
|
|
|
Manual j report
|
OVERRIDE | | | 9/27/2017 | | |
|
|
|
|
Routing Walk-In (BLD) | 9/27/2017 | 9/27/2017 | 9/27/2017 | A | DONE |
Josh Bogle
|
|
|
|
Plan assigned to (JAB) Josh | 6/6/2017 | 6/6/2017 | 9/27/2017 | | PASS |
Josh Bogle
|
|
|
1st comp - need more info
|
Routing - PLAN CHECK | 9/27/2017 | | 9/27/2017 | | PASS |
Josh Bogle
|
|
|
|
Inspection Record Card- Bld | | | 9/27/2017 | | DONE |
Josh Bogle
|
|
|
|
Case Summary (BLD) | | | 9/27/2017 | | DONE |
Josh Bogle
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/27/2017 | | DONE |
Josh Bogle
|
|
|
ESC yes - Energy yes
|
Permit Ready to Issue | | | 9/27/2017 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 9/27/2017 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 9/20/2017 | | 9/20/2017 | | FAIL |
Josh Bogle
|
|
|
plans still incomplete JAB
|
Plan resubmittals received | | | 8/31/2017 | | DONE |
|
|
|
resubmittals received 2 sets of sheets 1-4, S1, S2, 1 struc calcs & 1 checklist-took to JAB
|
Plan assigned to (BJM) | 5/26/2017 | 5/26/2017 | 6/6/2017 | | DEFR |
Brian McGowan
|
|
|
addition
|
1st review completed | | | 6/6/2017 | | FAIL |
Josh Bogle
|
|
|
|
Routing - PLAN CHECK | 6/6/2017 | | 6/6/2017 | | FAIL |
Josh Bogle
|
|
|
|
Routing - MECHANICAL | 5/30/2017 | | 6/5/2017 | | PASS |
Troy James
|
|
|
No manual j report submitted. If a new furnace or a/c is installed with this building permit a manual j report is required to be submitted for review before any mechanical work is performed.
|
Routing - PLANNING | 5/30/2017 | | 5/30/2017 | | PASS |
Jeff Lowe
|
|
|
intall hard surface driveway minimum 9-feet wide
|
Routing - PUBLIC WORKS | | | 5/30/2017 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 5/26/2017 | | DONE |
|
|
|
|
Intake Approval | | | 5/26/2017 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 5/26/2017 | | DONE |
|
|
|
no fees taken at intake
|
Routing - Addressing | 5/26/2017 | | 5/26/2017 | | PASS |
Laura Hunter
|
|
|
|
Application received | | 5/26/2017 | | | |
|
|
|
|