BLD-Final | 4/2/2018 | 4/2/2018 | 4/2/2018 | P | DONE |
Mike Jordan
|
|
|
NOT SURE IF BUILDING FINAL IS REQUIRED. Phone #: ###-#### Inspection requested via web by Dana Vance
|
DOC - Permit Finaled | 4/2/2018 | 4/2/2018 | 4/2/2018 | P | PASS |
Mike Jordan
|
|
|
|
Plan assigned to (CDM) | 5/31/2017 | 5/31/2017 | 5/31/2017 | | DONE |
Carl D Madsen
|
|
|
|
Intake Approval | | | 5/31/2017 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 5/31/2017 | | 5/31/2017 | | PASS |
Carl D Madsen
|
|
|
|
1st review completed | | | 5/31/2017 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/31/2017 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 5/31/2017 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 5/31/2017 | | DONE |
|
|
|
|
Application received | | | 5/30/2017 | | DONE |
|
|
|
Application submitted via PDS Online on May 30 2017 2:36PM
|
First Notice | 4/2/2018 | 4/2/2018 | | | |
Mike Jordan
|
|
|
|