BLD-Final | 2/7/2018 | 2/8/2018 | 2/9/2018 | A | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Clint Wall
|
DOC - Permit Finaled | 2/9/2018 | 2/9/2018 | 2/9/2018 | P | PASS |
Brandon Shaw
|
|
|
|
BLD-Final | 2/6/2018 | 2/7/2018 | 2/7/2018 | A | CANC |
Brandon Shaw
|
|
|
Need Mech final
|
PubWorks Occupancy Approval | 1/29/2018 | 1/29/2018 | 1/29/2018 | | DONE |
Melissa Jannusch
|
|
|
A bond for the sites final grading and re-vegetation has been received by Public Works. Occupancy may be approved by the building department. Melissa Jannusch ###-####.
|
BLD-Energy code compliance | 12/6/2017 | 12/8/2017 | 12/8/2017 | A | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Clint Wall
|
BLD-Framing/Rough-in | 12/4/2017 | 12/6/2017 | 12/6/2017 | A | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Clint Wall
|
BLD-Other | 11/24/2017 | 11/24/2017 | 11/24/2017 | P | PASS |
Brandon Shaw
|
|
|
soffit insp // Luna Phone #: ###-####
|
BLD-Wall Bracing | 11/24/2017 | 11/24/2017 | 11/24/2017 | P | PASS |
Brandon Shaw
|
|
|
Luna Phone #: ###-####
|
BLD-Foundation | 8/7/2017 | 8/8/2017 | 8/8/2017 | A | PASS |
Brandon Shaw
|
|
|
Jared Phone #: ###-####
|
BLD-Footing | 8/7/2017 | 8/7/2017 | 8/7/2017 | P | PASS |
Brandon Shaw
|
|
|
Jared Phone #: ###-####
|
PubWorks Subgrade Approval | 8/3/2017 | 8/3/2017 | 8/3/2017 | | DONE |
Melissa Jannusch
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Jason Taylor ###-####.
|
OVERRIDE | | | 7/11/2017 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 7/11/2017 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 7/11/2017 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 7/11/2017 | | DONE |
Christina Prado
|
|
|
All requirements met
|
Plan assigned to (JAB) Josh | 6/29/2017 | 6/29/2017 | 7/10/2017 | | PASS |
Josh Bogle
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/10/2017 | | DONE |
Josh Bogle
|
|
|
ESC yes - Energy yes
|
Routing - PLAN CHECK | 6/9/2017 | | 7/10/2017 | | PASS |
Josh Bogle
|
|
|
|
1st review completed | | | 7/3/2017 | | DONE |
Josh Bogle
|
|
|
sent to BHM to verify - JAB
|
Plan assigned to (BJM) | 6/9/2017 | 6/9/2017 | 6/29/2017 | | DEFR |
Brian McGowan
|
|
|
6/28 sfd Level 2 ePlan
|
Routing PW Grading-Hillside | 6/9/2017 | | 6/14/2017 | | PASS |
Jason C. Taylor
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Jason Taylor at ###-####
Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Jason Taylor at ###-####.
|
Route to Impact Fee Review | 6/9/2017 | 6/12/2017 | 6/12/2017 | | PASS |
Marissa Taylor
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - FIRE | 6/9/2017 | 6/9/2017 | 6/9/2017 | | PASS |
Katie Marron
|
|
|
Plans were reviewed for FD access, hydrant availability and defensible space. The lot to the rear of the structure is a common lot to be maintained by the HOA per the final plat.
|
Routing - MECHANICAL | 6/9/2017 | | 6/9/2017 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | 6/9/2017 | | 6/9/2017 | | PASS |
Jeff Lowe
|
|
|
|
Routing - Addressing | 6/9/2017 | | 6/9/2017 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | 6/9/2017 | | 6/9/2017 | | PASS |
Rachael Beierle
|
|
|
|
Routing - Erosion and Sediment | 6/9/2017 | | 6/9/2017 | | PASS |
Melissa Jannusch
|
|
|
Special waiver approved
|
Plans ACCEPTED BY PLAN TECH | | | 6/9/2017 | | DONE |
Christina Prado
|
|
|
|
Intake Approval | | | 6/9/2017 | | PASS |
Christina Prado
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 6/9/2017 | | DONE |
Christina Prado
|
|
|
|
Intake Approval | | | 6/2/2017 | | FAIL |
Christina Prado
|
|
|
Need Letter of Reliance from GeoTech Engineer, Structural Engineer, Mechanical Contractor (Manual J) and a new ResCheck for Blackrock Homes because everything still under Tahoe Homes
|
Application received | | | 6/1/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Jun 1 2017 7:40AM
|