BLD-Final | 4/30/2018 | 5/1/2018 | 5/1/2018 | A | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Clint Wall
|
DOC - Permit Finaled | 5/1/2018 | 5/1/2018 | 5/1/2018 | P | PASS |
Brandon Shaw
|
|
|
|
PubWorks Occupancy Approval | 4/30/2018 | 4/30/2018 | 4/30/2018 | | DONE |
Melissa Jannusch
|
|
|
A letter from the applicant’s civil engineer indicating that the final grading and drainage is acceptable has been received by Public Works. Final occupancy may be approved by the building department. Melissa Jannusch ###-####.
|
BLD-Energy code compliance | 1/26/2018 | 1/30/2018 | 1/30/2018 | A | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Clint Wall
|
BLD-Framing/Rough-in | 1/22/2018 | 1/26/2018 | 1/26/2018 | A | PASS |
Brandon Shaw
|
|
|
OK to insulate
|
BLD-Wall Bracing | 1/4/2018 | 1/4/2018 | 1/4/2018 | P | PASS |
Brandon Shaw
|
|
|
Soffit OK OK to cover exterior
|
BLD-Foundation | 9/5/2017 | 9/5/2017 | 9/5/2017 | P | PASS |
Brandon Shaw
|
|
|
Derek Phone #: ###-####
|
BLD-Footing | 8/30/2017 | 8/31/2017 | 8/31/2017 | P | PASS |
Brandon Shaw
|
|
|
Derek Phone #: ###-####
|
PubWorks Subgrade Approval | 8/31/2017 | 8/31/2017 | 8/31/2017 | | DONE |
Melissa Jannusch
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Melissa Jannusch ###-####.
|
OVERRIDE | | | 7/18/2017 | | |
|
|
|
|
Plan assigned to (BJM) | 6/9/2017 | 6/9/2017 | 7/18/2017 | | DONE |
Brian McGowan
|
|
|
6/28 sfd Level 2 ePlan
|
Routing - PLAN CHECK | 6/9/2017 | | 7/18/2017 | | PASS |
Brian McGowan
|
|
|
|
Issue PAID IN FULL permit | | | 7/18/2017 | | DONE |
|
|
|
|
1st review completed | | | 7/18/2017 | | DONE |
Brian McGowan
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/18/2017 | | DONE |
Brian McGowan
|
|
|
|
Permit Ready to Issue | | | 7/18/2017 | | |
|
|
|
met
|
Routing PW Grading-Hillside | 6/9/2017 | | 6/14/2017 | | PASS |
Jason C. Taylor
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Jason Taylor at ###-####
Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Jason Taylor at ###-####.
|
Route to Impact Fee Review | 6/9/2017 | 6/12/2017 | 6/12/2017 | | PASS |
Marissa Taylor
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - MECHANICAL | 6/9/2017 | | 6/12/2017 | | PASS |
Troy James
|
|
|
|
Routing - FIRE | 6/9/2017 | 6/9/2017 | 6/9/2017 | | PASS |
Katie Marron
|
|
|
Plans were reviewed for FD access, hydrant availability and defensible space.
|
Routing - PLANNING | 6/9/2017 | | 6/9/2017 | | PASS |
Colleen T Carroll
|
|
|
|
Routing - Addressing | 6/9/2017 | | 6/9/2017 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | 6/9/2017 | | 6/9/2017 | | PASS |
Rachael Beierle
|
|
|
|
Routing - Erosion and Sediment | 6/9/2017 | | 6/9/2017 | | PASS |
Melissa Jannusch
|
|
|
Special waiver approved
|
Plans ACCEPTED BY PLAN TECH | | | 6/9/2017 | | DONE |
Christina Prado
|
|
|
|
Intake Approval | | | 6/9/2017 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 6/9/2017 | | DONE |
|
|
|
|
Intake Approval | | | 6/2/2017 | | FAIL |
Christina Prado
|
|
|
Need Letter of Reliance from GeoTech Engineer, Structural Engineer, Mechanical Contractor (Manual J) and a new ResCheck for Blackrock Homes because everything still under Tahoe Homes
|
Application received | | | 6/1/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Jun 1 2017 9:37AM
|