Second Notice | | 5/20/2018 | 6/11/2018 | | DONE |
|
|
|
mailed 6-12
|
First Notice | 5/1/2018 | 5/1/2018 | 5/10/2018 | | DONE |
Jim Sly
|
|
|
mailed 5-11-18
|
BLD-Final | 4/30/2018 | 5/1/2018 | 5/1/2018 | A | PASS |
Jim Sly
|
|
|
Hello Jim,
per our conversation let me know if you would like to meet out at the site to review.
thanks Mike Teeter Phone #: ###-#### Inspection requested via web by Mike Teeter
|
DOC - Permit Finaled | 5/1/2018 | 5/1/2018 | 5/1/2018 | P | PASS |
Jim Sly
|
|
|
|
FIRE-Final Inspection | 3/23/2018 | 3/26/2018 | 3/26/2018 | A | PASS |
Troy Cobbley
|
|
|
life safety passed
Mike Phone #: ###-####
|
FIRE-Final Inspection | 2/14/2018 | 2/15/2018 | 2/15/2018 | A | FAIL |
Troy Cobbley
|
|
|
Life safety will be ok to pass when the fire alarm modifications have been made at the flower shop and the bakery
Mike Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 9/22/2017 | 9/22/2017 | 9/22/2017 | P | PASS |
Jim Sly
|
|
|
Tom Phone #: ###-####
|
BLD-Framing/Rough-in | 9/22/2017 | 9/22/2017 | 9/22/2017 | P | PASS |
Jim Sly
|
|
|
Tom Phone #: ###-####
|
BLD-Framing/Rough-in | 9/18/2017 | 9/18/2017 | 9/18/2017 | P | PASS |
Jim Sly
|
|
|
Deli framing// Tom Austin Phone #: ###-####
|
CHANGE STATUS TO (ISS) | | | 9/18/2017 | | DONE |
|
|
|
approved plan mod fees paid
|
Plan assigned to (JAR) | 7/21/2017 | 7/21/2017 | 8/11/2017 | | DONE |
Julie Romig
|
|
|
**07/21 - 08/04 - PLAN MOD - Albertsons Eagle
|
Routing - PLAN CHECK | 7/25/2017 | | 8/11/2017 | | PASS |
Julie Romig
|
|
|
|
Permit Ready to Issue | | | 8/11/2017 | | DONE |
|
|
|
plan mod DO NOT REISSUE; all requirements met, fees due
|
Routing - PLUMBING | 8/10/2017 | | 8/10/2017 | | PASS |
Bill VanDegrift
|
|
|
Per plan and ISPC.
|
Routing - MECHANICAL | 7/25/2017 | | 7/26/2017 | | PASS |
Troy James
|
|
|
|
Route to Impact Fee Review | 7/21/2017 | 7/24/2017 | 7/21/2017 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
Plan Modification Accepted | | | 7/21/2017 | | DONE |
|
|
|
E Plan Plan Mod-add new roof top condenser per refreigeration plans-revised sheets G0.1, A1.1, A2.1, E0.1, E1.1 & E3.1-new sheets A8.2, R1.1, R2.1, R3.1, R4.1 & R5.1-assigned to JAR
|
Issue PAID IN FULL permit | | | 7/12/2017 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 7/12/2017 | | DONE |
|
|
|
|
Plan assigned to (JAR) | 6/6/2017 | 6/6/2017 | 7/5/2017 | | DONE |
Julie Romig
|
|
|
06/19 (07/05) - L2 Eagle Rd Albertsons Remodel
|
Routing - PLAN CHECK | 6/6/2017 | | 7/5/2017 | | PASS |
Julie Romig
|
|
|
|
1st review completed | | | 7/5/2017 | | DONE |
Julie Romig
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/5/2017 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 7/5/2017 | | DONE |
|
|
|
ALL MET Need GC Form and Revised Cert of Value
|
Routing - FIRE | 6/6/2017 | 6/6/2017 | 6/7/2017 | | PASS |
Katie Marron
|
|
|
Separate Fire Permits will be required. No comments attached. Work involves replacing coolers/display cases throughout, creating an online order processing space and a new floral departement area.
|
Routing PW Environmental | 6/6/2017 | | 6/6/2017 | | PASS |
Rick Christenson
|
|
|
|
Routing - MECHANICAL | 6/6/2017 | | 6/6/2017 | | PASS |
Troy James
|
|
|
|
Routing - PLUMBING | 6/6/2017 | | 6/6/2017 | | PASS |
Bill VanDegrift
|
|
|
per plans and ISPC
|
Routing - Addressing | 6/6/2017 | | 6/6/2017 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | 6/6/2017 | | 6/6/2017 | | PASS |
Rachael Beierle
|
|
|
|
Intake Approval | | | 6/6/2017 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
Julie approved pre screen, health department approval uploaded in documents
|
Intake Approval | | | 6/2/2017 | | FAIL |
Julie Romig
|
|
|
Need:
1. Rename A, G, and F sheets with number and brief description per City of Boise naming convention. Sheets have been deleted so they can be re-uploaded.
2. Provide U-factor and SHGC for the new exterior window.
|
Application received | | | 6/1/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Jun 1 2017 9:38AM
|