BLD-Final | 6/14/2018 | 6/15/2018 | 6/15/2018 | A | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Clint Wall
|
DOC - Permit Finaled | 6/15/2018 | 6/15/2018 | 6/15/2018 | P | PASS |
Brandon Shaw
|
|
|
|
BLD-Blower Door Test Results | 6/14/2018 | 6/15/2018 | 6/15/2018 | A | DONE |
Brandon Shaw
|
|
|
ACH50- 3.88
|
PubWorks Occupancy Approval | 6/13/2018 | 6/13/2018 | 6/13/2018 | | DONE |
Melissa Jannusch
|
|
|
A letter from the applicant’s civil engineer indicating that the final grading and drainage is acceptable has been received by Public Works. Final occupancy may be approved by the building department. Melissa Jannusch ###-####.
|
BLD-Energy code compliance | 3/27/2018 | 3/29/2018 | 3/29/2018 | A | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Clint Wall
|
BLD-Framing/Rough-in | 3/24/2018 | 3/27/2018 | 3/27/2018 | A | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Clint Wall
|
BLD-Other | 3/2/2018 | 3/2/2018 | 3/2/2018 | P | PASS |
Brandon Shaw
|
|
|
Sofit- Luna Phone #: ###-####
|
BLD-Wall Bracing | 3/2/2018 | 3/2/2018 | 3/2/2018 | P | PASS |
Brandon Shaw
|
|
|
shear- Luna Phone #: ###-####
|
BLD-Foundation | 9/20/2017 | 9/22/2017 | 9/22/2017 | P | NR |
Brandon Shaw
|
|
|
Matt Phone #: ###-####
|
BLD-Foundation | 9/18/2017 | 9/19/2017 | 9/19/2017 | P | NR |
Brandon Shaw
|
|
|
Matt Phone #: ###-####
|
BLD-Footing | 9/14/2017 | 9/15/2017 | 9/15/2017 | A | PASS |
Jim Storey
|
|
|
Matt Phone #: ###-####set backs ok
|
PubWorks Subgrade Approval | 9/14/2017 | 9/14/2017 | 9/14/2017 | | DONE |
Melissa Jannusch
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Melissa Jannusch ###-####.
|
Issue PAID IN FULL permit | | | 7/25/2017 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 7/25/2017 | | DONE |
|
|
|
|
OVERRIDE | | | 7/24/2017 | | |
|
|
|
|
Plan assigned to (BJM) | 6/9/2017 | 6/9/2017 | 7/24/2017 | | DONE |
Brian McGowan
|
|
|
1st review complete- planning failed it - 6/28 sfd Level 2 ePlan
|
Routing - PLAN CHECK | 7/24/2017 | | 7/24/2017 | | PASS |
Brian McGowan
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/24/2017 | | DONE |
Brian McGowan
|
|
|
|
Permit Ready to Issue | | | 7/24/2017 | | DONE |
|
|
|
All met
|
1st review completed | | | 7/21/2017 | | DONE |
Brian McGowan
|
|
|
|
Routing - PLAN CHECK | 6/9/2017 | | 7/21/2017 | | PASS |
Brian McGowan
|
|
|
|
Routing PW Grading-Hillside | 6/9/2017 | | 6/19/2017 | | PASS |
Jason C. Taylor
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Jason Taylor at ###-####
Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Jason Taylor at ###-####.
|
Routing PW Flood Plain | 6/9/2017 | | 6/13/2017 | | PASS |
Jason C. Taylor
|
|
|
Approved LOMR on File. No floodplain review required. JCT
|
Route to Impact Fee Review | 6/9/2017 | 6/12/2017 | 6/12/2017 | | PASS |
Marissa Taylor
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - Addressing | 6/9/2017 | | 6/12/2017 | | PASS |
Laura Hunter
|
|
|
|
Routing - MECHANICAL | 6/9/2017 | | 6/12/2017 | | PASS |
Troy James
|
|
|
|
Routing - FIRE | 6/9/2017 | 6/9/2017 | 6/9/2017 | | PASS |
Katie Marron
|
|
|
Plans were reviewed for FD access, hydrant availability and defensible space. The lot to the rear of the structure is to a common lot to be maintained by the HOA per the final plat.
|
Routing - PUBLIC WORKS | 6/9/2017 | | 6/9/2017 | | PASS |
Rachael Beierle
|
|
|
|
Routing - Erosion and Sediment | 6/9/2017 | | 6/9/2017 | | PASS |
Andy J. Long
|
|
|
ESC plan waiver approved. Valid RP
|
Plans ACCEPTED BY PLAN TECH | | | 6/9/2017 | | DONE |
|
|
|
|
Intake Approval | | | 6/9/2017 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 6/9/2017 | | DONE |
|
|
|
|
Intake Approval | | | 6/2/2017 | | FAIL |
Christina Prado
|
|
|
Need Letter of Reliance from GeoTech Engineer, Structural Engineer, Mechanical Contractor (Manual J) and a new ResCheck for Blackrock Homes because everything still under Tahoe Homes
|
Application received | | | 6/1/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Jun 1 2017 11:02AM
|
Routing - PLANNING | 6/9/2017 | | | | PASS |
|
|
|
Driveway can not exceed 33ft. in width in the front setback
|