Information based on query as of Sunday, June 30, 2024.
Permit Information
Permit NumberBLD17-01711
StatusFinaled
Name BLACKROCK HOMES LLC
Site Address 5033 S TABOO PL
Project Name37-7 EV3 Jensen RV
Customer Number 
ePlanReviewYes
Description
HILLSIDE, WUI ZONE "A", FLOODPLAIN, CLASS "A" ROOF REQUIRED. Permit for the construction of a new 2529 sq. ft., two story (first story 1108 sq. ft., second story 1421 sq. ft.) single family dwelling with 4 bedrooms, 2.5 bathrooms, approximately 132 sq. ft. of covered patio/porch and a 943 sq. ft. attached garage per the approved plans and any notations. R-1C/DA zoning and setbacks per planning. ***BJM*** A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Jason Taylor at 608-7168

Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Jason Taylor at 608-7168.
Contact Information
See Activities list for contact information
Color Key
Current location of plans being reviewed:  
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final6/14/20186/15/20186/15/2018APASS
DetailsBrandon Shaw
Phone #: ###-#### Inspection requested via web by Clint Wall
DOC - Permit Finaled6/15/20186/15/20186/15/2018PPASS
DetailsBrandon Shaw
BLD-Blower Door Test Results6/14/20186/15/20186/15/2018ADONE
DetailsBrandon Shaw
ACH50- 3.88
PubWorks Occupancy Approval6/13/20186/13/20186/13/2018 DONE
DetailsMelissa Jannusch
A letter from the applicant’s civil engineer indicating that the final grading and drainage is acceptable has been received by Public Works. Final occupancy may be approved by the building department. Melissa Jannusch ###-####.
BLD-Energy code compliance3/27/20183/29/20183/29/2018APASS
DetailsBrandon Shaw
Phone #: ###-#### Inspection requested via web by Clint Wall
BLD-Framing/Rough-in3/24/20183/27/20183/27/2018APASS
DetailsBrandon Shaw
Phone #: ###-#### Inspection requested via web by Clint Wall
BLD-Other3/2/20183/2/20183/2/2018PPASS
DetailsBrandon Shaw
Sofit- Luna Phone #: ###-####
BLD-Wall Bracing3/2/20183/2/20183/2/2018PPASS
DetailsBrandon Shaw
shear- Luna Phone #: ###-####
BLD-Foundation9/20/20179/22/20179/22/2017PNR
DetailsBrandon Shaw
Matt Phone #: ###-####
BLD-Foundation9/18/20179/19/20179/19/2017PNR
DetailsBrandon Shaw
Matt Phone #: ###-####
BLD-Footing9/14/20179/15/20179/15/2017APASS
DetailsJim Storey
Matt Phone #: ###-####set backs ok
PubWorks Subgrade Approval9/14/20179/14/20179/14/2017 DONE
DetailsMelissa Jannusch
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Melissa Jannusch ###-####.

Issue PAID IN FULL permit  7/25/2017 DONE
Inspection Record Card- Bld  7/25/2017 DONE
OVERRIDE  7/24/2017  
Plan assigned to (BJM)6/9/20176/9/20177/24/2017 DONE
DetailsBrian McGowan
1st review complete- planning failed it - 6/28 sfd Level 2 ePlan
Routing - PLAN CHECK7/24/2017 7/24/2017 PASS
DetailsBrian McGowan
PLANS/APPL TAKEN TO FRONT DESK  7/24/2017 DONE
DetailsBrian McGowan
Permit Ready to Issue  7/24/2017 DONE
All met
1st review completed  7/21/2017 DONE
DetailsBrian McGowan
Routing - PLAN CHECK6/9/2017 7/21/2017 PASS
DetailsBrian McGowan
Routing PW Grading-Hillside6/9/2017 6/19/2017 PASS
DetailsJason C. Taylor
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Jason Taylor at ###-####

Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Jason Taylor at ###-####.
Routing PW Flood Plain6/9/2017 6/13/2017 PASS
DetailsJason C. Taylor
Approved LOMR on File. No floodplain review required. JCT
Route to Impact Fee Review6/9/20176/12/20176/12/2017 PASS
DetailsMarissa Taylor
Initial residential review of new SFD permits requested for now.
Routing - Addressing6/9/2017 6/12/2017 PASS
DetailsLaura Hunter
Routing - MECHANICAL6/9/2017 6/12/2017 PASS
DetailsTroy James
Routing - FIRE6/9/20176/9/20176/9/2017 PASS
DetailsKatie Marron
Plans were reviewed for FD access, hydrant availability and defensible space. The lot to the rear of the structure is to a common lot to be maintained by the HOA per the final plat.
Routing - PUBLIC WORKS6/9/2017 6/9/2017 PASS
DetailsRachael Beierle
Routing - Erosion and Sediment6/9/2017 6/9/2017 PASS
DetailsAndy J. Long
ESC plan waiver approved. Valid RP
Plans ACCEPTED BY PLAN TECH  6/9/2017 DONE
Intake Approval  6/9/2017 PASS
Recd Pcfee & Taken To Pln CK  6/9/2017 DONE
Intake Approval  6/2/2017 FAIL
DetailsChristina Prado
Need Letter of Reliance from GeoTech Engineer, Structural Engineer, Mechanical Contractor (Manual J) and a new ResCheck for Blackrock Homes because everything still under Tahoe Homes
Application received  6/1/2017 DONE
Application submitted via PDS Online on Jun 1 2017 11:02AM
Routing - PLANNING6/9/2017   PASS
Driveway can not exceed 33ft. in width in the front setback