Print Statement | | | 12/14/2017 | | DONE |
|
|
|
|
Third Notice | | 11/19/2017 | 12/12/2017 | | DONE |
|
|
|
Mailed 12-13-17
|
Second Notice | | 10/22/2017 | 11/14/2017 | | DONE |
|
|
|
Mailed 11-15-17
|
First Notice | | 9/24/2017 | 10/12/2017 | | DONE |
|
|
|
Mailed 10-13-17
|
BLD-Final | 9/14/2017 | 9/14/2017 | 9/14/2017 | P | PASS |
Jim Storey
|
|
|
Bill-please go early as possible as the fire final is done. Phone #: ###-#### need sign off from health dept.
|
FIRE-Final Inspection | 9/14/2017 | 9/14/2017 | 9/14/2017 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed.
Bill Phone #: ###-####
|
Letter of compliance/Occupancy | | | 9/14/2017 | | DONE |
|
|
|
|
Letter of compliance/Occupancy | | | 9/14/2017 | | DONE |
|
|
|
|
DOC - Permit Finaled | | | 9/14/2017 | | DONE |
|
|
|
|
FIRE-Final Inspection | 9/13/2017 | 9/13/2017 | 9/13/2017 | P | CANC |
Jim Page
|
|
|
Inspection not ready, point of contact Bill Phone #: ###-#### will reschedule inspection request for a later date. This inspection request is cancelled.
|
BLD-Ceiling Grid Inspection | 9/12/2017 | 9/13/2017 | 9/13/2017 | A | PASS |
Mike Jordan
|
|
|
Bill Phone #: ###-####
|
Permit Ready to Issue | | | 9/12/2017 | | DONE |
|
|
|
plan mod ready-PLEASE DO NOT RE ISSUE
|
(F) Reprint permit | | | 9/12/2017 | | DONE |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 9/12/2017 | | DONE |
|
|
|
|
Plan assigned to (CDM) | 9/5/2017 | 9/5/2017 | 9/11/2017 | | PASS |
Carl D Madsen
|
|
|
|
Routing - PLAN CHECK | 9/5/2017 | | 9/11/2017 | | PASS |
Carl D Madsen
|
|
|
|
Case Summary (BLD) | | | 9/11/2017 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 9/11/2017 | | DONE |
|
|
|
|
Plan resubmittals received | | | 9/5/2017 | | DONE |
|
|
|
Two copies of sheets A101, taken to Carl M
|
Issue PAID IN FULL permit | | | 7/12/2017 | | DONE |
|
|
|
|
Route to Impact Fee Review | 6/20/2017 | 6/23/2017 | 6/27/2017 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
Permit Ready to Issue | | | 6/27/2017 | | DONE |
|
|
|
need GC & Rev Cert of Val
|
Telephone call | | | 6/27/2017 | | DONE |
|
|
|
Left a message for William informing him that this permit is ready and that we just need the 302 and 306 forms filled out by the GC
|
Inspection Record Card- Bld | | | 6/26/2017 | | DONE |
|
|
|
|
Plan assigned to (CDM) | 6/2/2017 | 6/2/2017 | 6/24/2017 | | PASS |
Carl D Madsen
|
|
|
|
Routing - PLAN CHECK | 6/20/2017 | | 6/24/2017 | | PASS |
Carl D Madsen
|
|
|
|
Case Summary (BLD) | | | 6/24/2017 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/24/2017 | | DONE |
|
|
|
|
Routing - FIRE | 6/19/2017 | 6/17/2017 | 6/20/2017 | | PASS |
Scott Arellano
|
|
|
A cooking hood suppression system permit will be required along with any work to tie it into the existing fire alarm system. Inspector to verify a type K extinguisher is in the permit area.
|
1st review completed | | | 6/20/2017 | | PASS |
|
|
|
|
Routing - Addressing | 6/17/2017 | | 6/19/2017 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | 6/17/2017 | | 6/19/2017 | | PASS |
Rachael Beierle
|
|
|
NO PRETREATMENT REVIEW PER TERRY A
|
Routing - MECHANICAL | 6/19/2017 | | 6/19/2017 | | PASS |
Troy James
|
|
|
|
Routing - PLAN CHECK | 6/2/2017 | | 6/17/2017 | | PASS |
Carl D Madsen
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 6/2/2017 | | DONE |
|
|
|
|
Intake Approval | | | 6/2/2017 | | PASS |
Carl D Madsen
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 6/1/2017 | | DONE |
|
|
|
|
Application received | | 6/1/2017 | | | |
|
|
|
|