BLD-Final | 1/5/2018 | 1/5/2018 | 1/5/2018 | P | PASS |
Jim Storey
|
|
|
Phil Phone #: ###-####
|
DOC - Permit Finaled | 1/5/2018 | 1/5/2018 | 1/5/2018 | P | PASS |
Jim Storey
|
|
|
|
PubWorks Occupancy Approval | 12/21/2017 | 12/21/2017 | 12/21/2017 | | DONE |
Mike Sheppard
|
|
|
A bond for the sites final grading and re-vegetation has been received by Public Works. Occupancy may be approved by the building department. Jason Taylor ###-####.
|
BLD-Energy code compliance | 9/13/2017 | 9/14/2017 | 9/14/2017 | A | PASS |
Jim Sly
|
|
|
Phil Phone #: ###-####
|
BLD-Framing/Rough-in | 9/11/2017 | 9/12/2017 | 9/12/2017 | A | PASS |
Tony Young
|
|
|
phil Phone #: ###-#### (or Don ###-####)
|
BLD-Other | 8/29/2017 | 8/30/2017 | 8/30/2017 | A | PASS |
Tony Young
|
|
|
Phil-soffit Phone #: ###-####
|
BLD-Wall Bracing | 8/15/2017 | 8/15/2017 | 8/15/2017 | P | PASS |
Brandon Shaw
|
|
|
Phil Phone #: ###-####
|
BLD-Foundation | 7/13/2017 | 7/13/2017 | 7/13/2017 | P | PASS |
Tony Young
|
|
|
pour time 12:30 // foundation wall insp// Bill Phone #: ###-####
|
BLD-Footing | 7/11/2017 | 7/11/2017 | 7/11/2017 | P | PEND |
Tony Young
|
|
|
pour at 2 // Bill Phone #: ###-####,, ok pending soils report approval
|
Routing - PUBLIC WORKS GRADING | 7/11/2017 | | 7/11/2017 | | PASS |
Jim Wyllie
|
|
|
Letter from MTI approving footing subgrade received. Okay to schedule a footing inspection.
Jim Wyllie / ###-####
|
Issue PAID IN FULL permit | | | 7/3/2017 | | DONE |
|
|
|
|
OVERRIDE | | | 6/15/2017 | | |
|
|
|
|
Plan assigned to (JG) | 6/7/2017 | 6/7/2017 | 6/15/2017 | | PASS |
Javier Guzman
|
|
|
6/15 L2 SFD paper
|
1st review completed | | | 6/15/2017 | | DONE |
Javier Guzman
|
|
|
|
Case Summary (BLD) | | | 6/15/2017 | | DONE |
Javier Guzman
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/15/2017 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 6/15/2017 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 6/15/2017 | | DONE |
|
|
|
met
|
Routing - PLAN CHECK | | | 6/15/2017 | | PASS |
Javier Guzman
|
|
|
|
Telephone call | | | 6/15/2017 | | DONE |
Christina Prado
|
|
|
Called John to advise permit is ready for pick up and gave fees due
|
Routing - FIRE | 6/8/2017 | 6/2/2017 | 6/12/2017 | | PASS |
Scott Arellano
|
|
|
|
Routing - Erosion and Sediment | 6/8/2017 | | 6/8/2017 | | PASS |
Andy J. Long
|
|
|
ESC plan with site map and narrative approved. Valid RP and PD designated. Site preparation inspection required.
|
Routing - MECHANICAL | 6/7/2017 | | 6/8/2017 | | PASS |
Troy James
|
|
|
|
Plan assigned to (BJM) | 6/2/2017 | 6/2/2017 | 6/7/2017 | | DEFR |
Brian McGowan
|
|
|
sfd- 6-21 Level 2 paper
|
Routing - PLANNING | 6/7/2017 | | 6/7/2017 | | PASS |
David Moser
|
|
|
|
Routing - PUBLIC WORKS | 6/7/2017 | | 6/7/2017 | | PASS |
Rachael Beierle
|
|
|
|
Routing PW Grading-Hillside | | | 6/7/2017 | | PASS |
Jason C. Taylor
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Jason Taylor at ###-####
Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Jason Taylor at ###-####.
|
Route to Impact Fee Review | 6/2/2017 | 6/5/2017 | 6/5/2017 | | PASS |
Marissa Taylor
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing PW Sewer Rating | 6/2/2017 | | 6/2/2017 | | PASS |
Morgan Webb
|
|
|
|
Routing - Addressing | 6/2/2017 | | 6/2/2017 | | PASS |
Laura Hunter
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 6/2/2017 | | DONE |
|
|
|
|
Intake Approval | | | 6/2/2017 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 6/2/2017 | | DONE |
|
|
|
|
Application received | | 6/1/2017 | | | |
|
|
|
|