BLD-Final | 3/12/2018 | 3/15/2018 | 3/15/2018 | A | PASS |
Tony Young
|
|
|
Heidi Phone #: ###-####
|
DOC - Permit Finaled | 3/15/2018 | 3/15/2018 | 3/15/2018 | P | PASS |
Tony Young
|
|
|
|
BLD-Final | 3/9/2018 | 3/12/2018 | 3/12/2018 | A | PEND |
Tony Young
|
|
|
Heidi Phone #: ###-####
|
BLD-Final | 3/7/2018 | 3/9/2018 | 3/9/2018 | P | PASS |
Tony Young
|
|
|
Heidi Phone #: ###-####,, all ok,, just needs to finish some siding on exterior
|
Zoning Approval | 3/2/2018 | 3/2/2018 | 3/2/2018 | | DONE |
Ted Vanegas
|
|
|
|
BLD-Energy code compliance | 1/25/2018 | 1/26/2018 | 1/26/2018 | A | PASS |
Jim Sly
|
|
|
scott Phone #: ###-####
|
BLD-Energy code compliance | 1/24/2018 | 1/25/2018 | 1/25/2018 | P | NR |
Dave Hannah
|
|
|
Scott Phone #: ###-#### no one on site
|
BLD-Energy code compliance | 1/23/2018 | 1/23/2018 | 1/23/2018 | P | PART |
Tony Young
|
|
|
Scott Phone #: ###-####,, foam base layer okay
|
BLD-Framing/Rough-in | 1/17/2018 | 1/18/2018 | 1/18/2018 | A | PASS |
Dave Hannah
|
|
|
Scott Phone #: ###-####ok to spry ceiling and air seal
|
BLD-Wall Bracing | 12/29/2017 | 12/29/2017 | 12/29/2017 | P | PASS |
Tony Young
|
|
|
Scott Phone #: ###-####
|
BLD-Foundation | 11/14/2017 | 11/14/2017 | 11/14/2017 | P | PASS |
Tony Young
|
|
|
Mana Phone #: ###-####
|
BLD-Footing | 11/9/2017 | 11/13/2017 | 11/13/2017 | A | PASS |
Brandon Shaw
|
|
|
Mana Phone #: ###-####
|
Issue PAID IN FULL permit | | | 10/20/2017 | | DONE |
|
|
|
|
OVERRIDE | | | 10/19/2017 | | |
|
|
|
|
Plan assigned to (BJM) | 6/8/2017 | 6/8/2017 | 10/19/2017 | | DONE |
Brian McGowan
|
|
|
1st review complete - FAIL- ADU 6/19 paper 9-25 - Planning failed it.
|
Inspection Record Card- Bld | | | 10/19/2017 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 10/19/2017 | | 10/19/2017 | | PASS |
Brian McGowan
|
|
|
|
Case Summary (BLD) | | | 10/19/2017 | | DONE |
Brian McGowan
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/19/2017 | | DONE |
Brian McGowan
|
|
|
|
Permit Ready to Issue | | | 10/19/2017 | | DONE |
|
|
|
need
GC form
RP - met
|
Routing - PLANNING | 10/17/2017 | | 10/17/2017 | | PASS |
Nicolette Womack
|
|
|
|
Plan resubmittals received | | | 10/12/2017 | | DONE |
|
|
|
Resubmittals received 2 sets of sheets Cs, A-1, A-2, A-3, S-1.0 & D-1-took to Brian McGowan
|
Routing - PLANNING | 10/11/2017 | | 10/11/2017 | | PASS |
Nicolette Womack
|
|
|
According to plans emailed 10-11-17. Proposal meets the square footage requirements.
|
Routing - PLANNING | 9/25/2017 | | 9/25/2017 | | FAIL |
Nicolette Womack
|
|
|
Significant Redesign Proposed since Historic Approval. Requires DRH modification. Storage Area included in the square footage of ADU exceeds 600 square feet approved through ADU application.
|
Plan resubmittals received | | | 9/11/2017 | | DONE |
|
|
|
Resumittals received 2 sets of each Eng calcs, res check, C1, A-1, A-2, A-3, D-1, S1.0-Took to Brian McGowan
|
Plan resubmittals received | | | 6/30/2017 | | DONE |
|
|
|
received two copies of plan sheets CS, A1, A2, A3, D1; taken to Brian McGowan
|
Routing - PLAN CHECK | 7/11/2017 | | 6/30/2017 | | FAIL |
Brian McGowan
|
|
|
Need ICC-ES Report for the spray foam insulation.
|
1st review completed | | | 6/22/2017 | | FAIL |
Brian McGowan
|
|
|
Failed to meet energy code, no wall bracing noted,
|
Routing - PLAN CHECK | 6/8/2017 | | 6/22/2017 | | FAIL |
Brian McGowan
|
|
|
Failed to meet energy code, no wall bracing noted,
|
Routing - PLANNING | 6/20/2017 | | 6/20/2017 | | PASS |
Nicolette Womack
|
|
|
Only one entrance is allowed on the front elevations. Future Carport does not comply with the required setbacks. This is not approved and requires a variance and historic approval.
|
Route to Impact Fee Review | 6/6/2017 | 6/9/2017 | 6/9/2017 | | PASS |
Marissa Taylor
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - MECHANICAL | | | 6/8/2017 | | PASS |
|
|
|
owner is to install ductless mini split system for heating
|
Routing - PLANNING | 6/7/2017 | | 6/7/2017 | | FAIL |
Nicolette Womack
|
|
|
Required to provide recorded deed restriction. Only one entrance allowed on the front elevation. "Future Carport" does not meet required setbacks, not approved. Requires a Variance and Historic Approval.
|
Routing - Addressing | 6/6/2017 | | 6/7/2017 | | PASS |
Laura Hunter
|
|
|
Created new address for ADU: 1512 N 8th St
|
Routing - PUBLIC WORKS | | | 6/7/2017 | | PASS |
|
|
|
|
Intake Approval | | | 6/6/2017 | | |
|
|
|
|
Intake Approval | | | 6/2/2017 | | FAIL |
|
|
|
missing electircal sheet and rescheck
|
Application received | | 6/2/2017 | | | |
|
|
|
|