Telephone call | | | 12/18/2018 | | DONE |
|
|
|
spoke to David Haase, parcel owner. Explained situation and to continue project would need to get release of plans from Archtiect to reopen existing permit or submit new plans and get new permit for remainder of project not inspected.
|
VOIDED CHANGE STATUS | | | 12/17/2018 | | DONE |
|
|
|
see attached memo from ALC Arcthiecture (plans stamped) to retract use of plans for this project. Permit is void. Called Bright Star Energy Management and left message for Andrew and Victor Clark about memo and that permit is void. Also emailed Andrew Clark same info.
|
BLD-Conference | 9/7/2018 | 9/7/2018 | 9/7/2018 | A | NH |
Brandon Shaw
|
|
|
No one home, no inspections have been done since 5/21/18 soffit...
|
BLD-Aging Inspection | 9/7/2018 | 9/7/2018 | 9/7/2018 | | CANC |
Brandon Shaw
|
|
|
|
BLD-Aging Inspection | 9/6/2018 | 9/6/2018 | 9/6/2018 | | DEFR |
Brandon Shaw
|
|
|
|
BLD-Other | 5/21/2018 | 5/22/2018 | 5/22/2018 | A | PASS |
Brandon Shaw
|
|
|
soffits and facia Phone #: ###-#### Inspection requested via web by Andrew Clark
|
BLD-Energy code compliance | 4/25/2018 | 4/25/2018 | 4/25/2018 | P | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Andrew Clark
|
BLD-Framing/Rough-in | 4/19/2018 | 4/19/2018 | 4/19/2018 | A | PART |
Brandon Shaw
|
|
|
No Foam seal at framing inspection Front deck to be finished at a later time OK to insulate
|
BLD-Footing | 4/18/2018 | 4/19/2018 | 4/19/2018 | A | PASS |
Brandon Shaw
|
|
|
For deck posts
|
PubWorks Subgrade Approval | 4/18/2018 | 4/18/2018 | 4/18/2018 | | DONE |
Jason C. Taylor
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Jason Taylor ###-####.
|
Plan Reviewer's activity | | | 4/17/2018 | | DONE |
|
|
|
MTI Footing certification letter uploaded into the ePlanReview system.
|
BLD-Energy code compliance | 3/7/2018 | 3/7/2018 | 3/7/2018 | P | FAIL |
Brandon Shaw
|
|
|
As per Description on permit- Geo subgrade approval to be submitted to Public Works. Footing and foundation poured without PW approval or inspections. Need third party approval for as built or X-ray to verify rebar is in place, as per plans.
|
Issue PAID IN FULL permit | | | 7/28/2017 | | DONE |
|
|
|
|
Telephone call | | | 7/27/2017 | | DONE |
|
|
|
called applicant. He said will come in to office pick-up/sign for permits and get esc sign
|
OVERRIDE | | | 7/25/2017 | | |
|
|
|
|
Plan assigned to (JAB) Josh | 6/2/2017 | 6/2/2017 | 7/25/2017 | | PASS |
Josh Bogle
|
|
|
1st comp. - 7-10 waiting on engineering details
|
Routing - Erosion and Sediment | 7/24/2017 | | 7/25/2017 | | PASS |
Andy J. Long
|
|
|
ESC plan approved. Valid RP desinated. Call ESC inspector with any questions or inspection needs. Call ###-####
|
Routing - PLAN CHECK | 7/25/2017 | | 7/25/2017 | | PASS |
Josh Bogle
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/25/2017 | | DONE |
Josh Bogle
|
|
|
ESC yes - Energy yes
|
Permit Ready to Issue | | | 7/25/2017 | | DONE |
|
|
|
All Met
|
Routing - PLAN CHECK | 7/17/2017 | | 7/17/2017 | | FAIL |
Josh Bogle
|
|
|
Missing vital information
|
Routing - PLAN CHECK | 7/12/2017 | | 7/12/2017 | | FAIL |
Josh Bogle
|
|
|
sent plan back to applicant to update pages
|
Routing Walk-In (Zoning) | 6/19/2017 | 6/19/2017 | 6/19/2017 | P | PASS |
Sue Cummings
|
|
|
|
1st review completed | | | 6/9/2017 | | FAIL |
Josh Bogle
|
|
|
|
Routing - PLAN CHECK | 6/2/2017 | | 6/9/2017 | | FAIL |
Josh Bogle
|
|
|
|
Routing PW Grading-Hillside | 6/5/2017 | | 6/9/2017 | | PASS |
Jason C. Taylor
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Jason Taylor at ###-####
|
Plan assigned to (BJM) | 6/2/2017 | 6/2/2017 | 6/6/2017 | | DEFR |
Brian McGowan
|
|
|
remodel
|
Application received | | | 6/2/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Jun 2 2017 2:04PM
|
Plans ACCEPTED BY PLAN TECH | | | 6/2/2017 | | DONE |
|
|
|
|
Intake Approval | | | 6/2/2017 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 6/2/2017 | | DONE |
|
|
|
|
Routing - PLANNING | 6/2/2017 | | | | FAIL |
|
|
|
Permit removes required two car off street parking. Need to show where compliant parking will now be located.
|