PubWorks Occupancy Approval | 6/11/2018 | 6/11/2018 | 6/11/2018 | | DONE |
Melissa Jannusch
|
|
|
A letter from the applicant’s civil engineer indicating that the final grading and drainage is acceptable has been received by Public Works. Final occupancy may be approved by the building department. Melissa Jannusch ###-####.
|
BLD-Final | 6/6/2018 | 6/8/2018 | 6/8/2018 | P | PASS |
Jim Sly
|
|
|
Garage Code: 6365 Phone #: ###-#### Inspection requested via web by Jessica Bradley
|
DOC - Permit Finaled | 6/8/2018 | 6/8/2018 | 6/8/2018 | P | PASS |
Jim Sly
|
|
|
|
BLD-Conference | 6/5/2018 | 6/6/2018 | 6/6/2018 | A | PASS |
Tony Young
|
|
|
Jay would like a call 45 minutes prior to conference. Phone # ###-#### Phone #: ###-#### Inspection requested via web by Jessica Bradley// walk through on the final ,, needs hillside
|
BLD-Other | 3/8/2018 | 3/9/2018 | 3/9/2018 | P | PEND |
Tony Young
|
|
|
Sheetrock at the sofit Phone #: ###-#### Inspection requested via web by Jessica Bradley
|
BLD-Other | 3/8/2018 | 3/8/2018 | 3/8/2018 | P | PART |
Tony Young
|
|
|
Sheetrock at the sofit Phone #: ###-#### Inspection requested via web by Jessica Bradley,, waiting on can light protection
|
BLD-Other | 3/6/2018 | 3/6/2018 | 3/6/2018 | P | PART |
Tony Young
|
|
|
Sheetrock at the soffit Phone #: ###-#### Inspection requested via web by Jessica Bradley,, work in progress,, need can light protection on patio,, talked to RW
|
BLD-Energy code compliance | 2/27/2018 | 2/27/2018 | 2/27/2018 | P | PASS |
Dave Hannah
|
|
|
Garage Code: 6365 Phone #: ###-#### Inspection requested via web by Jessica Bradley
|
BLD-Framing/Rough-in | 2/21/2018 | 2/22/2018 | 2/22/2018 | P | PASS |
Brandon Shaw
|
|
|
OK to insulate
|
BLD-Wall Bracing | 2/5/2018 | 2/6/2018 | 2/6/2018 | A | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Jessica Bradley
|
BLD-Foundation | 11/28/2017 | 11/29/2017 | 11/29/2017 | P | PART |
Tony Young
|
|
|
Phone #: 2089495359 >> Inspection requested via mobile web by Ricardo ,, work in progress
|
BLD-Footing | 11/28/2017 | 11/29/2017 | 11/29/2017 | A | PASS |
Tony Young
|
|
|
James; Phone #: ###-####
|
BLD-Footing | 11/28/2017 | 11/29/2017 | 11/29/2017 | A | PASS |
Tony Young
|
|
|
Phone #: 2089495359 >> Inspection requested via mobile web by Ricardo
|
PubWorks Subgrade Approval | 11/13/2017 | 11/13/2017 | 11/13/2017 | | DONE |
Melissa Jannusch
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Melissa Jannusch ###-####.
|
Issue PAID IN FULL permit | | | 11/13/2017 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 11/13/2017 | | DONE |
|
|
|
|
OVERRIDE | | | 11/6/2017 | | |
|
|
|
|
Permit Ready to Issue | | | 11/6/2017 | | DONE |
|
|
|
All Met
|
Plan assigned to (BJM) | 10/10/2017 | 10/10/2017 | 11/1/2017 | | DONE |
Brian McGowan
|
|
|
1st review complete - Corrections required - 9/22 sfd L2 ePlan (reassigned to me)
|
Routing - PLAN CHECK | 11/1/2017 | | 11/1/2017 | | PASS |
Brian McGowan
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/1/2017 | | DONE |
Brian McGowan
|
|
|
|
Routing - MECHANICAL | 10/30/2017 | | 10/30/2017 | | PASS |
Troy James
|
|
|
|
Routing PW Grading-Hillside | 10/26/2017 | | 10/26/2017 | | PASS |
Melissa Jannusch
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Please allow 24 hours for subgrade approval processing. Call Melissa Jannusch at ###-####
Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Melissa Jannusch at ###-####.
|
1st review completed | | | 10/11/2017 | | FAIL |
Brian McGowan
|
|
|
Hillside corrections required. TOW anbd TOF needed on foundation.
|
Routing - PLAN CHECK | 9/5/2017 | | 10/11/2017 | | FAIL |
Brian McGowan
|
|
|
|
Plan assigned to (M_H) | 10/9/2017 | | 10/10/2017 | | DEFR |
Michael Hanson
|
|
|
|
Routing PW Grading-Hillside | 9/5/2017 | | 9/27/2017 | | FAIL |
Jason C. Taylor
|
|
|
Geotechnical concerns, discussed in the meeting on 9-18-2017, will need to be addressed before the permit can pass hillside review.
|
Routing - FIRE | 9/5/2017 | 9/5/2017 | 9/19/2017 | | PASS |
Scott Arellano
|
|
|
No comments attached. Plans approved as shown.
|
Routing - Erosion and Sediment | 9/5/2017 | | 9/8/2017 | | PASS |
Andy J. Long
|
|
|
ESC site plan and narrative approved. Valid RP and PD Site preparation inspection is required at beginning of project. Call ###-#### to schedule
|
Route to Impact Fee Review | 9/5/2017 | 9/8/2017 | 9/6/2017 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - Addressing | 9/5/2017 | | 9/6/2017 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 9/5/2017 | | 9/6/2017 | | PASS |
Morgan Webb
|
|
|
|
Routing - MECHANICAL | 9/5/2017 | | 9/6/2017 | | FAIL |
Troy James
|
|
|
emailed corrections to legends mech
|
Plan assigned to (BJM) | 9/5/2017 | 9/5/2017 | 9/5/2017 | | DEFR |
Brian McGowan
|
|
|
1st review complete - Corrections required - 9/22 sfd L2 ePlan
|
Routing - PLANNING | 9/5/2017 | | 9/5/2017 | | PASS |
Nicolette Womack
|
|
|
|
Intake Approval | | | 9/5/2017 | | FAIL |
Christina Prado
|
|
|
Need stamped foundation plan, wall bracing calcs & soil report
|
Plans ACCEPTED BY PLAN TECH | | | 9/5/2017 | | DONE |
|
|
|
|
Intake Approval | | | 9/5/2017 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 9/5/2017 | | DONE |
|
|
|
|
Application received | | | 6/2/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Jun 2 2017 3:07PM
|