Permit Information
Permit NumberBLD17-01764
StatusFinaled
Name SILVER LINING LLC
Site Address 10173 W OVERLAND RD
Project NameWilner & O'Reilly Law Office
Customer Number 
ePlanReviewYes
Description
(WILNER & O’REILLY LAW OFFICE – WHOLE BUILDING TENANT) (DRH15-00284) This building does not have a fire sprinkler system. To construct interior tenant improvements within a 3,531 square foot shell building for an office tenant. This tenant will occupy the entire building. Work is to include two layers of 5/8” Type “X” gypsum board installed as the ceiling membrane of a 1-hr fire-resistance-rated roof-ceiling assembly, a 1-hr attic access hatch, a 1-hr fire-resistance-rated eave and soffit at the East exterior wall, a 1-hr fire-resistance-rated East exterior wall rated for fire exposure from each side, and 1-hr fire-resistance-rated bearing walls (i.e. North, West, and South exterior walls) for fire exposure from the inside. Additional work includes interior nonbearing walls, two toilet rooms accessible to the disabled, interior doors, millwork, and finishes. The work is required to comply with the approved drawings, with the plan review report, and with all applicable codes and ordinances. **CJW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
First Notice 10/19/201711/14/2017 DONE
Mailed 11-15-17
BLD-Final10/9/201710/9/201710/9/2017PPASS
DetailsMike Jordan
Richard Phone #: ###-####. All issues have been resolved.
Print Occupancy Form  10/9/2017 DONE
Permanent Occupancy  10/9/2017 DONE
BLD-Final9/28/20179/29/20179/29/2017APART
DetailsMike Jordan
call for access code - RIchard Phone #: ###-####. Ok for temp occ. Needs to provide listed attic acces doors.
FIRE-Final Inspection9/26/20179/27/20179/27/2017APASS
DetailsTroy Cobbley
life safety passed
BLD-Framing/Rough-in8/15/20178/16/20178/16/2017APASS
DetailsMike Jordan
Richard Phone #: ###-####
BLD-Energy code compliance8/16/20178/16/20178/16/2017APASS
DetailsMike Jordan
Richard Phone #: ###-####
BLD-Framing/Rough-in8/14/20178/15/20178/15/2017APASS
DetailsMike Jordan
Richard Phone #: ###-####
BLD-Framing/Rough-in8/10/20178/11/20178/11/2017PNR
DetailsMike Jordan
Richard Phone #: ###-####
BLD-Framing/Rough-in8/4/20178/9/20178/9/2017AFAIL
DetailsMike Jordan
Richard Phone #: ###-####. Remove all foam from top plate penetrations and provide a UL listed firestop for 1hr. ceiling assembly. All mech openings in 1hr. ceiling assembly will require fire dampers. Need plumbing rough in inspection. No cover at this time. Correction notice issued.
Route to Impact Fee Review7/29/20178/1/20178/1/2017 PASS
DetailsMarissa Taylor
Review requested for Commercial Permit
Issue PAID IN FULL permit  8/1/2017 DONE
Permit Ready to Issue  7/31/2017 DONE
Need GC Form and Revised Cert of Value
Plan assigned to (CJW)6/13/20176/13/20177/29/2017 PASS
DetailsCarl Westfall
(7a) (July 3 - 15 days) (18 sheets) Wilner & O'Reilly Law
Routing - PLAN CHECK6/13/2017 7/29/2017 PASS
DetailsCarl Westfall
1st review approved
1st review completed  7/29/2017 DONE
PLANS/APPL TAKEN TO FRONT DESK  7/29/2017 DONE
Routing - FIRE6/13/20176/13/20176/14/2017 PASS
DetailsKatie Marron
Shell and Core was completed under BLD15-02837. Basic Life Safety. Plans indicated two exits are required, unless determined otherwise by IBC plan review, emergency exit discharge lighting shall be required.
Routing - MECHANICAL6/13/2017 6/14/2017 PASS
DetailsTroy James
Routing - PLUMBING6/13/2017 6/14/2017 PASS
DetailsBill VanDegrift
per plans and ISPC
Routing - Addressing6/13/2017 6/13/2017 PASS
DetailsLaura Hunter
Routing - PUBLIC WORKS6/13/2017 6/13/2017 PASS
DetailsRachael Beierle
Plan Reviewer's activity  6/13/2017 PASS
Plan intake review approved
Intake Approval  6/13/2017 PASS
DetailsAdele J Schaffeld-Griffin
Carl W completed pre screen
Intake Approval  6/9/2017 FAIL
(6-9-17) See the unresolved circled items in the plan intake checklist. Please resolve this item as directed. CJW
Intake Approval  6/6/2017 FAIL
(6-6-17) See the circled items in the plan intake checklist. Please resolve each item as directed. CJW
Application received  6/5/2017 DONE
Application submitted via PDS Online on Jun 5 2017 11:42AM