DOC - Permit Finaled | | | 5/23/2019 | | DONE |
|
|
|
passed final on 5-21-2019
|
BLD-Final | 5/20/2019 | 5/21/2019 | 5/21/2019 | P | PASS |
Tony Young
|
|
|
Re inspection Phone #: ###-#### Inspection requested via web by Josh Strasser,, received letter from engineer,, ok
|
BLD-Final | 5/16/2019 | 5/16/2019 | 5/16/2019 | P | PART |
Tony Young
|
|
|
I will be on site today Josh Strasser Phone #: ###-#### Inspection requested via web by Josh Strasser,, ok pending final okay letter from engineer
|
BLD-Wall Bracing | 1/22/2019 | 1/23/2019 | 1/23/2019 | A | PASS |
Jim Sly
|
|
|
Sheer inspection Area D Phone #: ###-#### Inspection requested via web by Josh Strasser
|
BLD-Wall cover | 1/18/2019 | 1/22/2019 | 1/22/2019 | P | DEFR |
Dave Hannah
|
|
|
Sheer inspection Area D Phone #: ###-#### Inspection requested via web by Josh Strasser out of time
|
BLD-Framing/Rough-in | 1/15/2019 | 1/16/2019 | 1/16/2019 | P | PASS |
Tony Young
|
|
|
Area D to the Left of Rite Aid. Final area of the Northgate Remodel. Phone #: ###-#### Inspection requested via web by Josh Strasser
|
BLD-Framing/Rough-in | 1/14/2019 | 1/15/2019 | 1/15/2019 | A | NR |
Tony Young
|
|
|
Area D to the Left of Rite Aid. Final area of the Northgate Remodel. Phone #: ###-#### Inspection requested via web by Josh Strasser,, needs trades 1st,, fire and electrical
|
BLD-Framing/Rough-in | 12/27/2018 | 12/27/2018 | 12/27/2018 | P | PART |
Tony Young
|
|
|
Partial Sheer framing rough in Area E (Rite Aid) Phone #: ###-#### Inspection requested via web by Josh Strasser,, nailing ok
|
BLD-Wall Bracing | 12/7/2018 | 12/10/2018 | 12/10/2018 | A | PART |
Tony Young
|
|
|
Sheer Partial Phone #: ###-#### Inspection requested via web by Josh Strasser,, work in progress,, rite aid section,, ok
|
BLD-Wall Bracing | 12/5/2018 | 12/5/2018 | 12/5/2018 | P | PART |
Brandon Shaw
|
|
|
Partial strapping and clips to sheet walls
|
BLD-Wall Bracing | 11/28/2018 | 11/29/2018 | 11/29/2018 | A | PART |
Jim Storey
|
|
|
Partial Roof cover and wall cover to get water tight in the area from above. Phone #: ###-#### Inspection requested via web by Josh Strasser stud framing ok at roof rafters and bearing walls w/sheer clips per plan// 18x24 plate steel to cmu wall rfi as to two difernent bolt sizes not on plan need verrifacation as built is ok
|
BLD-Aging Inspection | 11/21/2018 | 11/21/2018 | 11/26/2018 | | PEND |
Tony Young
|
|
|
|
BLD-Aging Inspection | 11/20/2018 | 11/20/2018 | 11/26/2018 | | CANC |
Tony Young
|
|
|
|
BLD-Wall cover | 7/9/2018 | 7/9/2018 | 7/9/2018 | A | PART |
Tony Young
|
|
|
Area F Front of Goodwill Shear for Cover Phone #: ###-#### Inspection requested via web by Josh Strasser,, ok after renailing some areas of face and soffit,, see paint notes
|
BLD-Wall cover | 7/2/2018 | 7/2/2018 | 7/2/2018 | A | PART |
Tony Young
|
|
|
Sheer inspection Area F and G Josh Phone #: ###-#### Inspection requested via web by Josh Strasser,, ok after re-doing a few areas
|
BLD-Framing/Rough-in | 6/22/2018 | 6/22/2018 | 6/22/2018 | P | PART |
Tony Young
|
|
|
Theater Breezeway Shear to Metro PCS. Framing and Rough in Front of Goodwill Phone #: ###-#### Inspection requested via web by Josh Strasser,, see paint notes
|
BLD-Wall cover | 6/5/2018 | 6/6/2018 | 6/10/2018 | P | PASS |
Tony Young
|
|
|
Area F,G,H Approve for cover Area I Shear Nail Approve for cover Phone #: ###-#### Inspection requested via web by Josh Strasser
|
BLD-Wall Bracing | 5/14/2018 | 5/15/2018 | 5/15/2018 | A | PASS |
Tony Young
|
|
|
Area K Sheer Liquor store area Phone #: ###-#### Inspection requested via web by Josh Strasser,,
|
BLD-Wall Bracing | 5/14/2018 | 5/14/2018 | 5/15/2018 | P | PART |
Tony Young
|
|
|
Area K Sheer Liquor store area Phone #: ###-#### Inspection requested via web by Josh Strasser,, work in progress
|
BLD-Wall Bracing | 5/11/2018 | 5/14/2018 | 5/14/2018 | A | DEFR |
Tony Young
|
|
|
Area K Sheer Liquor store area Phone #: ###-#### Inspection requested via web by Josh Strasser
|
BLD-Wall cover | 5/11/2018 | 5/11/2018 | 5/11/2018 | P | NR |
Tony Young
|
|
|
Area K Sheer Liquor store area Phone #: ###-#### Inspection requested via web by Josh Strasser,, need to re-do some areas,,
|
BLD-Framing/Rough-in | 5/2/2018 | 5/2/2018 | 5/2/2018 | P | PART |
Tony Young
|
|
|
Area J and K From Liquor Store to Mongolian Phone #: ###-#### Inspection requested via web by Josh Strasser,, ok pending trades
|
BLD-Wall cover | 4/10/2018 | 4/10/2018 | 4/10/2018 | P | PART |
Tony Young
|
|
|
Sheer inspection Area C early PM if possible Phone #: ###-#### Inspection requested via web by Josh Strasser,, work in progress,, re-nail some areas,, needs 3/8" on sides
|
BLD-Wall Bracing | 4/5/2018 | 4/6/2018 | 4/9/2018 | P | PASS |
Tony Young
|
|
|
Partial Area C Reinspect sheer partial Area C Josh Strasser Phone #: ###-#### Inspection requested via web by Josh Strasser
|
BLD-Framing/Rough-in | 4/4/2018 | 4/5/2018 | 4/5/2018 | P | PART |
Tony Young
|
|
|
Partial Area C Reinspect sheer partial Area C Josh Strasser Phone #: ###-#### Inspection requested via web by Josh Strasser,, work in progress,, needs sprinklers passed
|
BLD-Wall Bracing | 4/3/2018 | 4/4/2018 | 4/4/2018 | P | PASS |
Tony Young
|
|
|
Partial Area C Sheer Phone #: ###-#### Inspection requested via web by Josh Strasser
|
BLD-Wall cover | 4/2/2018 | 4/3/2018 | 4/3/2018 | P | PART |
Tony Young
|
|
|
Partial Area C Sheer Phone #: ###-#### Inspection requested via web by Josh Strasser// work in progress,, needs some intermediate nailing/screws
|
BLD-Framing/Rough-in | 3/20/2018 | 3/20/2018 | 3/20/2018 | P | PART |
Jim Sly
|
|
|
Partial Area C Phone #: ###-#### Inspection requested via web by Josh Strasser Area C OK.
|
BLD-Framing/Rough-in | 3/9/2018 | 3/12/2018 | 3/12/2018 | A | PART |
Tony Young
|
|
|
Partial for Area A and west side of Area B Josh Strasser Phone #: ###-#### Inspection requested via web by Josh Strasser,, ok pending trades in this area,, by vape
|
BLD-Framing/Rough-in | 3/9/2018 | 3/9/2018 | 3/9/2018 | P | PART |
Tony Young
|
|
|
Partial for Area A and west side of Area B Josh Strasser Phone #: ###-#### Inspection requested via web by Josh Strasser,, need more screws,, also trades
|
BLD-Wall Bracing | 2/20/2018 | 2/21/2018 | 2/21/2018 | A | PART |
Tony Young
|
|
|
Partial A Wall sheeting for cover Phone #: ###-#### Inspection requested via web by Josh Strasser,, late am,, fasteners ok per ICC report,, shear ok to cover
|
BLD-Wall cover | 2/20/2018 | 2/20/2018 | 2/20/2018 | P | NR |
Tony Young
|
|
|
Partial A Wall sheeting for cover Phone #: ###-#### Inspection requested via web by Josh Strasser,, need to redo per plan,, need equivalent for the fasteners
|
BLD-Framing/Rough-in | 2/13/2018 | 2/14/2018 | 2/14/2018 | P | PART |
Tony Young
|
|
|
Partial Area A for cover. Late PM Phone #: ###-#### Inspection requested via web by Josh Strasser,, west end of Area A ok
|
BLD-Wall Bracing | 2/1/2018 | 2/1/2018 | 2/1/2018 | P | PART |
Tony Young
|
|
|
Partial for roof sheathing. Josh Strasser Phone #: ###-#### Inspection requested via web by Josh Strasser,, frame members ok above Sallys and Weightwatchers
|
BLD-Foundation | 11/14/2017 | 11/15/2017 | 11/15/2017 | A | PASS |
Mike Jordan
|
|
|
Pouring 3 Piers at 1:15 PM I pier in front of the gold store 1 pier front of old hall mark 1 pier in front of old blockbuster Phone #: ###-#### Inspection requested via web by Josh Strasser
|
BLD-Footing | 10/30/2017 | 10/31/2017 | 10/31/2017 | A | PART |
Brandon Shaw
|
|
|
7 Footings 3 Piers Area A and C
|
BLD-Footing | 10/26/2017 | 10/27/2017 | 10/27/2017 | A | PART |
Jim Sly
|
|
|
Phone #: ###-#### Inspection requested via web by Josh Strasser Strata OK'd sub grade......STRATA inspecting rebar.....1st 5 footing pads starting from West end.
|
Issue PAID IN FULL permit | | | 10/25/2017 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 10/25/2017 | | DONE |
|
|
|
|
OVERRIDE | | | 9/27/2017 | | |
|
|
|
|
Permit Ready to Issue | | | 9/27/2017 | | DONE |
|
|
|
all met - Final early start permit Bld17-03276 when this permit is issued
|
Routing - PLAN CHECK | 9/21/2017 | | 9/26/2017 | | PASS |
Carl D Madsen
|
|
|
|
Routing Off Site - STRUCTURAL | 9/21/2017 | | 9/26/2017 | | PASS |
Carl D Madsen
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/26/2017 | | DONE |
|
|
|
|
Plan assigned to (CDM) | 6/14/2017 | 6/14/2017 | 9/12/2017 | | PASS |
Carl D Madsen
|
|
|
1st Comp 7/5 Northgate Facade
|
Routing - PLAN CHECK | 8/10/2017 | | 9/12/2017 | | FAIL |
Carl D Madsen
|
|
|
Failed pending structural
|
Routing Off Site - STRUCTURAL | 9/6/2017 | | 9/12/2017 | | FAIL |
Carl D Madsen
|
|
|
|
Routing Off Site - STRUCTURAL | 8/10/2017 | | 9/6/2017 | | FAIL |
Carl D Madsen
|
|
|
|
Routing - Design Review | 8/10/2017 | | 8/10/2017 | | PASS |
Andrea Tuning
|
|
|
|
Route to Impact Fee Review | 7/8/2017 | 7/11/2017 | 7/10/2017 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
1st review completed | | | 7/8/2017 | | FAIL |
|
|
|
|
Routing Off Site - STRUCTURAL | 6/14/2017 | | 7/8/2017 | | FAIL |
Carl D Madsen
|
|
|
|
Routing - PLAN CHECK | 6/14/2017 | | 7/8/2017 | | FAIL |
Carl D Madsen
|
|
|
|
Routing - Erosion and Sediment | 6/29/2017 | | 6/29/2017 | | PASS |
Andy J. Long
|
|
|
ESC plan and site map submitted and approved. Valid PD, RP to be determined upon contract reward.
|
Routing - FIRE | 6/14/2017 | 6/14/2017 | 6/19/2017 | | PASS |
Katie Marron
|
|
|
Renovations to exterior store front/canopy. Work does involve remodeling the front vestibule of the rite aid tenant, this work may require fire alarm modification. Per email with architect, emergency egress can lighting will be provided above doors as required.
|
Routing - PLANNING Land Div | 6/14/2017 | | 6/19/2017 | | PASS |
Todd Tucker
|
|
|
|
Routing - PUBLIC WORKS | 6/14/2017 | | 6/16/2017 | | PASS |
Rachael Beierle
|
|
|
|
Routing PW Drainage | 6/16/2017 | | 6/16/2017 | | PASS |
Brian Murphy
|
|
|
ROOF REPLACING
|
Routing - Erosion and Sediment | 6/14/2017 | | 6/15/2017 | | FAIL |
Andy J. Long
|
|
|
Please submit ESC plan or ESC plan waiver due to scope of exterior work
|
Routing - Addressing | 6/14/2017 | | 6/14/2017 | | PASS |
Laura Hunter
|
|
|
|
Routing - Design Review | 6/14/2017 | | 6/14/2017 | | FAIL |
Andrea Tuning
|
|
|
All awnings/canopies are required to be 5-feet in depth.
|
Intake Approval | | | 6/14/2017 | | PASS |
|
|
|
|
Intake Approval | | | 6/9/2017 | | FAIL |
Javier Guzman
|
|
|
Please provide and upload the following:
• Please provide a site specific fire flow at hydrants letter from Suez Water or other public water provider. Include static pressure if sprinklers are to be installed.
• Please provide a vicinity map that shows location of the property with street names identified, the current vicinity map only shows nothing other than the building
• Please provide and upload plan sheets E0.00, E1.01, E1.02, E1.03, E1.04, E1.05, E1.06, E1.07, E1.08, E1.09, E1.10 in the horizontal position (landscape format) as these sheets were uploaded in the vertical position
|
Application received | | | 6/5/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Jun 5 2017 12:38PM
|