BLD-Final | 2/16/2018 | 2/16/2018 | 2/16/2018 | P | PASS |
Dave Hannah
|
|
|
Phone #: ###-#### Inspection requested via web by Ryan Lierman
|
DOC - Permit Finaled | 2/16/2018 | 2/16/2018 | 2/16/2018 | P | PASS |
Dave Hannah
|
|
|
|
BLD-Framing/Rough-in | 10/17/2017 | 10/17/2017 | 10/17/2017 | P | PASS |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Ryan Lierman
|
BLD-Energy code compliance | 10/17/2017 | 10/17/2017 | 10/17/2017 | P | PASS |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Ryan Lierman
|
BLD-Framing/Rough-in | 10/16/2017 | 10/16/2017 | 10/16/2017 | P | PART |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Ryan Lierman,, c/n posted,, ok to insulate
|
Plan Modification Accepted | | | 9/27/2017 | | DONE |
|
|
|
new manual j report
|
Routing - MECHANICAL | 9/27/2017 | | 9/27/2017 | | PASS |
Troy James
|
|
|
resubmitted manual j report
|
BLD-Wall Bracing | 9/19/2017 | 9/20/2017 | 9/20/2017 | A | PASS |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Ryan Lierman
|
BLD-Wall Bracing | 9/15/2017 | 9/18/2017 | 9/18/2017 | A | PART |
Brandon Shaw
|
|
|
1) C Wall- back of garage to be 7/16" OSB 2) All lateral straps at second floor to be installed per plans. First floor only, no stairs at time of inspection OK to wrap exterior
|
BLD-Foundation | 7/19/2017 | 7/20/2017 | 7/20/2017 | P | PART |
Tony Young
|
|
|
Dane Phone #: ###-####,, work in progress
|
BLD-Foundation | 7/18/2017 | 7/19/2017 | 7/19/2017 | P | NR |
Mike Jordan
|
|
|
Dane Phone #: ###-####
|
BLD-Footing | 7/17/2017 | 7/18/2017 | 7/18/2017 | P | PART |
Tony Young
|
|
|
Dane Phone #: ###-####,, work in progress,, setbacks appear ok
|
BLD-Footing | 7/14/2017 | 7/17/2017 | 7/17/2017 | P | NR |
Brandon Shaw
|
|
|
Dane Phone #: ###-####
|
BLD-Footing | 7/11/2017 | 7/12/2017 | 7/13/2017 | P | NR |
Tony Young
|
|
|
Dane Phone #: ###-####
|
(F) Reprint permit | | | 7/11/2017 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 7/7/2017 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 7/7/2017 | | DONE |
|
|
|
|
OVERRIDE | | | 6/22/2017 | | |
|
|
|
|
Plan assigned to (JG) | 6/16/2017 | 6/16/2017 | 6/22/2017 | | PASS |
Javier Guzman
|
|
|
1st rev comp 6/20 L1 SFD ePlan
|
Routing - PLAN CHECK | 6/22/2017 | | 6/22/2017 | | PASS |
Javier Guzman
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/22/2017 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 6/22/2017 | | DONE |
|
|
|
|
1st review completed | | | 6/17/2017 | | FAIL |
Javier Guzman
|
|
|
|
Routing - PLAN CHECK | 6/7/2017 | | 6/17/2017 | | FAIL |
Javier Guzman
|
|
|
|
Plan assigned to (BJM) | 6/7/2017 | 6/7/2017 | 6/16/2017 | | DEFR |
Brian McGowan
|
|
|
sfd 6-20 ePlan
|
Route to Impact Fee Review | 6/7/2017 | 6/10/2017 | 6/8/2017 | | PASS |
Marissa Taylor
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - MECHANICAL | 6/7/2017 | | 6/8/2017 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | 6/7/2017 | | 6/7/2017 | | PASS |
David Moser
|
|
|
left message to call Idaho power about power line next to the property. Howver, it appears the power line was moved with the Odom Sub.
|
Routing - Addressing | 6/7/2017 | | 6/7/2017 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | 6/7/2017 | | 6/7/2017 | | PASS |
Rachael Beierle
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 6/7/2017 | | DONE |
Christina Prado
|
|
|
|
Intake Approval | | | 6/7/2017 | | PASS |
Christina Prado
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 6/7/2017 | | DONE |
Christina Prado
|
|
|
|
Application received | | | 6/5/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Jun 5 2017 4:14PM
|