First Notice | | 8/26/2018 | 8/16/2018 | | DONE |
|
|
|
Filled out when occupancy sign off card was brought in
|
Print Statement | | | 8/16/2018 | | DONE |
|
|
|
|
Permanent Occupancy | | | 8/16/2018 | | DONE |
|
|
|
|
BLD-Final | 8/10/2018 | 8/13/2018 | 8/14/2018 | P | PASS |
Dave Hannah
|
|
|
Not on site, please call ahead so we can make sure the door is open for you and can meet you there. Scott Phone #: ###-#### Inspection requested via web by Scott Henderson ok after fire finals
|
FIRE-Final Inspection | 8/13/2018 | 8/14/2018 | 8/14/2018 | A | PASS |
Jim Page
|
|
|
Fire sprinkler inspection is complete, no fire alarm modifications, firee xtinguisher are placed with current inspection tags. Final life fire safety inspection for area of work complete.
Request for Fire Life Safety final. Not on site. Bldg is secure. Please call ahead so I can meet you there. Scott, ###-#### Inspection requested via web by Scott Henderson
|
BLD-Framing/Rough-in | 7/17/2018 | 7/18/2018 | 7/18/2018 | A | PASS |
Tony Young
|
|
|
Framing inspection for joist reinforcing that has been completed in the basement. Dustin Palmer will be onsite contact, ###-####. Phone #: ###-#### Inspection requested via web by Scott Henderson
|
BLD-Framing/Rough-in | 7/11/2018 | 7/12/2018 | 7/12/2018 | A | PASS |
Tony Young
|
|
|
For Stage Expansion framing. Phone #: ###-#### Inspection requested via web by Scott Henderson
|
BLD-Framing/Rough-in | 7/10/2018 | 7/11/2018 | 7/11/2018 | P | PEND |
Tony Young
|
|
|
For Stage Expansion framing. Phone #: ###-#### Inspection requested via web by Scott Henderson,, needs trades 1st
|
BLD-Framing/Rough-in | 7/10/2018 | 7/10/2018 | 7/10/2018 | P | NR |
Tony Young
|
|
|
For Stage Expansion framing. Phone #: ###-#### Inspection requested via web by Scott Henderson,, need trades,, add studs under single plate loads
|
Issue PAID IN FULL permit | | | 5/16/2018 | | DONE |
|
|
|
|
Print Occupancy Form | | | 5/16/2018 | | DONE |
|
|
|
|
Expiration Notice | 5/7/2018 | 5/28/2018 | 5/7/2018 | | DONE |
Brittany Hill
|
|
|
|
Extend Review Timeline | | | 11/17/2017 | | DONE |
|
|
|
1st Approved 180 day extension per Adele. See documents
|
Expiration Notice | 11/15/2017 | 12/7/2017 | 11/15/2017 | | DONE |
Brittany Hill
|
|
|
|
Plan assigned to (CDM) | 6/19/2017 | 6/19/2017 | 9/29/2017 | | PASS |
Carl D Madsen
|
|
|
1st comp. 6/29 Boise High Stage
|
Routing - PLAN CHECK | 9/12/2017 | | 9/29/2017 | | PASS |
Carl D Madsen
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/29/2017 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 9/29/2017 | | DONE |
|
|
|
SCOTT.HENDERS@PACIFICSOURCE.NET
MET
Need:
Revised value
GC form
|
Routing - PLAN CHECK | 7/6/2017 | | 7/15/2017 | | FAIL |
Carl D Madsen
|
|
|
All original items not adequately addressed.
|
Routing - FIRE | 7/6/2017 | 7/6/2017 | 7/11/2017 | | PASS |
Scott Arellano
|
|
|
|
Route to Impact Fee Review | 7/3/2017 | 7/6/2017 | 7/4/2017 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
Routing - PLAN CHECK | 6/19/2017 | | 7/3/2017 | | FAIL |
Carl D Madsen
|
|
|
|
1st review completed | | | 7/3/2017 | | FAIL |
|
|
|
|
Routing - ELECTRICAL | 6/19/2017 | | 6/22/2017 | | PASS |
Javier Guzman
|
|
|
Relocation of existing electrical to new front stage extension, no review required
|
Routing - FIRE | 6/19/2017 | 6/19/2017 | 6/19/2017 | | PASS |
Katie Marron
|
|
|
Comments attached to case.
|
Intake Approval | | | 6/19/2017 | | PASS |
|
|
|
|
Pending Assignment by CDM | 6/19/2017 | | 6/19/2017 | | DONE |
Carl D Madsen
|
|
|
|
Application received | | | 6/7/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Jun 7 2017 10:02AM
|